  878   Monday, March 30, 2015, 09:03 Anders MjosConditioning StationStandard OperationTM4Ta#45Ta#45 ConditionoingMonday, March 30, 2015, 08:59: Reset chiller
by switching on off power (fault 2)
Monday, March 30, 2015, 09:02: Switched
 Ta#45_Conditioning.docx 
  877   Monday, March 30, 2015, 07:38 David WangITEStandard OperationTM4 TH Shut Down Activities Schedule Feb 23th- Apr 15th updateUpdated schedule this morning after last
Fridays ISAC facility support group meeting.
Updated schedule on 2015-April -02.
 Target_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mpp 
  876   Friday, March 27, 2015, 11:29 David WangConditioning StationStandard OperationTM4Ta#45TM4 is connected at CSTM4 has been connected at CS which includes
high current cables, water lines, EE cable,
and Enizel lens cable. The HV cover has been 
 010.JPG013.JPG012.JPG 
  875   Friday, March 27, 2015, 10:03 David WangConditioning StationStandard OperationTM4Ta#45Helium pressure test on TM4 HS line at CSThe helium pressure test on TM4 HS line
at conditioning station is done. No leak.
I also leak checked all vacuum seals on TM4
 001.JPG005.JPG006.JPG 
  874   Thursday, March 26, 2015, 09:20 Travis CaveConditioning StationStandard OperationTM4Ta#45Electrical checkElectrical check of TM#4 with Ta#45 at
the conditioning station, see attached pdf
for details.
 TM4_Ta#45_tgt_elec_chk_CS.PDF 
  873   Wednesday, March 25, 2015, 14:34 David WangConditioning StationStandard OperationTM4Ta#45 TM4 and CS turbo- pumps are started .I connected TM4 and CS vacuum system after
TM4 move. CS roughing pump was started first
this morning. Later, Anders, Bill and I started
  
  872   Wednesday, March 25, 2015, 14:25 David WangSouth Hot-CellStandard OperationTM4Ta#45Leak check on TM4 HS water line with new Ta#45 target. at SHCChad and I leak checked TM4 HS water line
with new Ta#45 target installed at SHC. Leak
detector base leak rate 0.0Xe-9 atm.cc/sec,
  
  871   Wednesday, March 25, 2015, 10:37 chad fisherSouth Hot-CellDevelopment  TM2 optics tray buildTM2 optics tray build is continuing. Going
well. Hope to have assembly and alignment
finished by Friday.
 20150325_101718.jpg20150325_101735.jpg20150325_102024.jpg 
  870   Tuesday, March 24, 2015, 13:57 Travis CaveSouth Hot-CellStandard OperationTM4Ta#45Electrical checkTM#4 electrical checks with and without
the target installed, installed target is
Ta#45.
 TM4_no_tgt_elec_chk_CS.PDFTM4_Ta45_elec_chk_SHC.PDF 
  869   Tuesday, March 24, 2015, 09:47 chad fisherSouth Hot-CellStandard OperationTM4Ta#45Ta#45 installedTa#45 has been installed onto TM4 and is
ready for leak and electrical check. High
current fasteners torqued to 130 in.lbs.
  
  868   Tuesday, March 24, 2015, 08:46 Travis CaveConditioning StationStandard OperationTM4No targetModule moveTM#4  with no target has been moved
from conditioning station to the south hot
cell.
  
  867   Monday, March 23, 2015, 14:03 chad fisherSouth Hot-CellStandard Operation Ta#45Ta#45 inserted into hot cellTa#45 has been inserted into the hot cell.
Swipe taken of inner tool port area: 100000
counts/min.
  
  866   Monday, March 23, 2015, 07:56 David WangITEStandard Operation  TH Shut Down Activities Schedule Feb 23th- Apr 15th updateThis schedule is following Dons schedule
on module moves. See attachments for updating.
2015-03-27: Weekly update the schedule.
 Target_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mppTarget_Hall_shut_down_activities.pdfTarget_Hall_shut_down_activities.mpp 
  865   Friday, March 20, 2015, 13:37 chad fisherSouth Hot-CellDevelopment  TM2 Optics TrayFinal assembly and alignment of TM2 optics
tray continued today. Front section is "aligned".
 20150320_113132[2].jpg20150320_113018_1[1].jpg 
  864   Tuesday, March 17, 2015, 10:33 Travis CaveSpent Target VaultStandard Operation UC#11Spent Target MoveThe spent UC#11 has benn moved from the
south hot cell to the spent target vault.
See attached PDF for details.
 Vault_Storage_March_17_2015.pdf 
  863   Monday, March 16, 2015, 14:16 Travis CaveConditioning StationStandard OperationTM4No targetModule moveTM#4 from south hot cell to the conditioning
station no target is attached to the module.
  
  862   Monday, March 16, 2015, 09:41 Travis CaveITEStandard OperationTM4UC#11Module moveTM#4 with UC#11 moved from the east target
station to the south hot cell.
  
  861   Friday, March 13, 2015, 13:36 Travis CaveSpent Target VaultStandard Operation ThO#1Spent Target MoveThe ThO#1 has been placed in the storage
vault placed in pail #122 in spot 2B of the
vault. It was 6.2mSv/hr upon removal from
 Storage_Vault_March_13_2015.pdf 
  860   Thursday, March 12, 2015, 13:33 Anders MjosSouth Hot-CellStandard OperationTM1ThO#1Target inspectionChad, Anders and Alex inspected the target
this morning. The target had no significant
visible damage to the container. Some material
  
  859   Thursday, March 12, 2015, 13:04 David WangITEStandard OperationTM4 5 Shielding blocks have been transferred from ITE to ITW.5 shielding blocks have been transferred
from ITE to ITW for next week TM4 move.
  