  468   Thursday, September 26, 2013, 14:31 Bevan MossSouth Hot-CellRepairTM3NiO#2Activities September 24 - 25September 24
 After the manipulator repair
Maico installed the NiO#2 onto the target
 elec_check.pdf 
  467   Thursday, September 26, 2013, 09:46 maicodallavalleConditioning StationRepairTM3 Leak check / Pressure TestTM3 has had all of the water lines pressurized
with Helium and the Helium Leak detector
was connected to the turbo pumps. There were
  
  466   Wednesday, September 25, 2013, 13:48 Travis CaveConditioning StationStandard OperationTM3NiO#2Electrical checkElectrical check of TM#3 in the conditioning
station under vacuum see attached PDF for
details.
 TM#3_elec_chk_NiO#2_CS.PDF 
  465   Wednesday, September 25, 2013, 11:08 Travis CaveSouth Hot-CellStandard OperationTM3NiO#2Electrical checkThe module was checked electrically this
morning before the module move. See the attached
PDF for details.
 TM#3_elec_chk_NiO#2_SHC.PDF 
  464   Wednesday, September 25, 2013, 10:00 Travis CaveSouth Hot-CellStandard OperationTM3NiO#2module moveTM#3 with NiO#2 has been moved from the
south hot cell to the conditioning station.
  
  463   Wednesday, September 25, 2013, 06:59 maicodallavalleSouth Hot-CellStandard OperationTM3 Containment box coverThe containment box cover has had all 
the bolts installed and all bolts were checked
with a mirror. TM3 has been raised and is
  
  462   Tuesday, September 24, 2013, 14:46 Bevan MossSouth Hot-CellRepair  Right manipulator repair    
  461   Tuesday, September 24, 2013, 08:15 Travis CaveSouth Hot-CellStandard OperationTM3no targetElectrical checkElectrical check was done on TM#3 yesterday
and again the coil lines to the 60kV common
and the coil line to each other failed, as
 TM#3_elec_chk_no_target.PDF 
  460   Monday, September 23, 2013, 16:10 Bevan MossSouth Hot-CellRepairTM3 Activities Sept 20 - 23 2013 September 20th
Today was a trying day. When attempting
to make the water line  connections for the
  
  459   Monday, September 23, 2013, 13:55 David WangSouth Hot-CellStandard OperationTM3 window circuit leak checkThis morning, Bevan and I leak checked
window circuit on TM3 at SHC after containment
box was installed. It took about 20minutes
  
  458   Thursday, September 19, 2013, 15:56 Bevan MossSouth Hot-CellRepairTM3 Activities for September 18th and 19thSeptember 18th
The wiring harness was completed
by Maico and Travis today (see pics) and
 IMG_1127.JPGIMG_1134.JPGIMG_1137.JPGIMG_1139.JPGIMG_1143.JPG 
  457   Thursday, September 19, 2013, 11:09 Travis CaveSouth Hot-CellMaintenanceTM3no targetElectrical checkElectrical check of TM#3 with no target
was performed and it failed.
  
  456   Thursday, September 19, 2013, 09:08 Travis CaveSouth Hot-CellStandard OperationTM3no targetwiring harnessThe wiring harness for TM#3 was made and
a continuity and megger test was done on
it and it passed, it has since been installed
  
  455   Tuesday, September 17, 2013, 14:36 Bevan MossSouth Hot-CellStandard OperationTM3 Containment Box has been removed The containment box has been removed.
Tomorrow the wiring harness will be installed.
  
  454   Friday, September 13, 2013, 08:05 David WangSouth Hot-CellRepairTM4 TM4 coil 1 leak check in SHCLeak checked TM4 coil1 in SHC with Isaac
. The leak detector only can pump down to
1.5xE-7 atm.cc/sec. The leak detector got
 TM4_coil_1_leak_check.pdf 
  453   Friday, September 13, 2013, 07:49 David WangConditioning StationDevelopmentTM3 TM3 water lines leak check at CSI leak checked TM3 water lines at CS with
60 psi and 80psi helium. The base leak rate
is 5.0xe-9 atm.cc/sec. Each circuit 3 minutes
 TM3_water_lines_leak_check_at_CS.pdf 
  452   Thursday, September 12, 2013, 10:35 Travis CaveSouth Hot-CellStandard OperationTM4SiC#29Electrical checkTM#4 with SiC#29 post beam electrical check
in the south hot cell see PDF for details.
 TM#4SiC#29FEBIADelechkpostbeam.PDF 
  451   Thursday, September 12, 2013, 09:29 Travis CaveITWStandard OperationTM4SiC#29module moveTM#4 with SiC#29 has been moved to the
south hot cell move went well.
  
  450   Wednesday, September 11, 2013, 15:37 Bevan MossSouth Hot-CellRepairTM3 C-Seal leak checking and repair This e-log is to cover the work completed
from September 9th until the 11th. 
September 9th
  
  449   Wednesday, September 11, 2013, 13:43 David WangConditioning StationDevelopmentTM3 Started 3 turbo pumps on CS for TM3TM3 has been connected in CS.Three turbo-
pumps have been started. The pumping down
is fine so far.
  