2648
|
Thursday, August 08, 2024, 13:58 |
David Wang | South Hot-Cell | Standard Operation | TM3 | SiC #46 | TM3 SiC#46 electrical check at SHC with target on (After operation) | ABCD is short to 60KV bias. Othjer are
ok. see attachment.
Found afterwards that this short |
|
2647
|
Thursday, August 08, 2024, 11:41 |
David Wang | South Hot-Cell | Standard Operation | TM3 | SiC #46 | Tm3 was moved from ITE to TCS this Tuesaday, then to SHC this morning. | Tm3 was moved from ITE to TCS this Tuesday,
then to SHC this morning. Both moves
are successful. |
|
2646
|
Tuesday, August 06, 2024, 09:16 |
Frank Song | ITE | Standard Operation | TM3 | SiC#46 | module disconnection | TM3 with spent target SiC#46 was
disconnected in ITE and ready to move to
TCS soon. |
|
2645
|
Wednesday, July 24, 2024, 10:10 |
Frank Song | ITE/ITW/Storage Area | Standard Operation | | | shielding blocks transfer | 5 shielding blocks have been transferred
from ITE to ITW. MAA is secured again after
moving. |
|
2644
|
Thursday, July 18, 2024, 11:22 |
Travis Cave | Spent Target Vault | Standard Operation | | UC#45 | Spent Target Move | The UC#45 target was moved from the
south hot cell to the spent target vault.
It was place in Pail#292 spot 1A of the vault, |
|
2643
|
Wednesday, July 17, 2024, 15:06 |
Adam Newsome | Facilities | Standard Operation | | | Safety Walkaround Complete - SHC/NHC Area | A safety walkaround for July 2024 was completed
for the B2 level by A. Newsome. No deficiencies
to report. |
|
2642
|
Tuesday, July 16, 2024, 13:14 |
Frank Song | ITW | Standard Operation | TM4 | TiC#7 | Module Connection | TM4 with TiC#7 was connected in ITW,
all TPs are running at full speed. |
|
2641
|
Tuesday, July 16, 2024, 11:15 |
David Wang | ITW | Standard Operation | TM4 | TiC #7 febiad. | TM4 has been moved from TCS to ITW. | TM4 has been moved from TCS to ITW.
the move is smooth. |
|
2640
|
Tuesday, July 16, 2024, 11:15 |
David Wang | ITW | Standard Operation | TM4 | TiC #7 febiad. | TM4 has been moved from TCS to ITW. | TM4 has been moved from TCS to ITW.
the move is smooth. |
|
2639
|
Friday, July 12, 2024, 08:51 |
Riley Sykes | Safe Module Parking | Maintenance | | | SMP chain guard | SS washers were added to all slotted
holes on SMP chainguard cover plate |
|
2638
|
Wednesday, July 10, 2024, 10:44 |
Riley Sykes | South Hot-Cell | Maintenance | | | Spring idler install | New spring idlers were installed
onto rotational chain drive for SHC roof.
Operation ran smoothly in both directions |
|
2637
|
Wednesday, July 10, 2024, 09:55 |
Adam Newsome | Safe Module Parking | Maintenance | | | Annual electrical and mechanical inspection of Safe Module Parking | An annual electrical and mechanical inspection
was performed on the SMP today by Adam
Newsome, Travis Cave, Riley Sykes, Maico |
|
2636
|
Tuesday, July 09, 2024, 16:14 |
Carla Babcock | ITE | Repair | | | Attempts to reduce ITE:EL trips from HV sparks | ITE:EL has been tripping off due to HV
sparks. Usually this also trips ITE:Q1/2.
These are sitting in side-by-side racks. |
8x |
2635
|
Monday, July 08, 2024, 10:40 |
David Wang | Conditioning Station | Standard Operation | TM4 | TiC#7 | TM4 has been moved from SHC to TCS. | TM4 has been moved from SHC to TCS. The
move is successfully. |
|
2634
|
Friday, July 05, 2024, 14:13 |
Adam Newsome | Waste Package/Ship | Standard Operation | | | F-308 flask loading - five flasks loaded | Today (2024-07-05), five flasks were loaded
in preparation for shipment with the following
targets: SiC#43 (Pail 272), SiC#44 (Pail |
|
2633
|
Friday, July 05, 2024, 12:50 |
David Wang | South Hot-Cell | Standard Operation | TM4 | TiC#7 | TM4 and TiC#7 target electrical check and HS leak check at SHC after target installation . | TM4 and TiC#7 target electrical check and
HS leak check at SHC after target installation
have been done. all results are good. |
|
2632
|
Thursday, July 04, 2024, 13:23 |
David Wang | South Hot-Cell | Standard Operation | TM4 | UCx#45 | electrical check on TM4 UCx#45 target at SHC after operation. | electrical check on TM4 UCx#45 target
at SHC after operation is done.
see attachment. |
|
2631
|
Thursday, July 04, 2024, 11:45 |
Frank Song | ITW | Standard Operation | TM4 | UCx#45 | module disconnection | TM4 with spent target UCx#45 was disconnected
in ITW and moved to SHC.
TM4 move from ITW to SHC is |
|
2630
|
Thursday, July 04, 2024, 01:20 |
Carla Babcock | ITE | Development | TM3 | SiC#46 | TM3 conditioning with protons | Initial Summary:
TM3 sparking behaviour in ITE has
been very disruptive both with and without |
|
2629
|
Wednesday, July 03, 2024, 14:01 |
David Wang | Conditioning Station | Standard Operation | TM2 | | Tm2 has been moved from TCS to SW silo. | Tm2 has been moved from TCS to SW silo.
the move is smooth. |
|