ID Date Author Category Type Module Target/Number Subject Text Attachments
  1348   Thursday, September 08, 2016, 16:30 David WangConditioning StationRepairTM3 TM3 vacuum system have been connected at TCS.start of roughing now.
 start of TCS and TM3 turbo-pumps.
Everything is good so far.
  
  1347   Thursday, September 08, 2016, 16:28 David WangConditioning StationRepairTM3 TM3 blue insulators have been replaced.All TM3 blue insulators except Gas,EL,
and 60 KV common  on top of the module
have been replaced with new designed insulators.
  
  1346   Wednesday, September 07, 2016, 11:44 Travis CaveConditioning StationStandard OperationTM3no targetmodule movedTM#3 has been moved from the NE Silo to
the conditioning station.
  
  1345   Wednesday, September 07, 2016, 11:39 Isaac EarleNorth Hot-CellDevelopment  NHC North / South Wall Gap Measurements Measurements were taken today of
the NHC north/south wall gap at the location
where the NHC/TCS partition wall will be
  
  1344   Tuesday, September 06, 2016, 10:05 David WangITWStandard OperationTM2 5 Shielding blocks have been transferred from ITE to ITW.5shielding blocks have been transferred
from ITE to ITE. ITW is configured to take
proton beam.
  
  1343   Tuesday, August 30, 2016, 13:17 David WangITWStandard OperationTM2 TM2 has been connected at ITW  ITW turbo pumps  have been
started.
  
  1342   Tuesday, August 30, 2016, 10:35 Travis CaveITWStandard OperationTM2Ta#49module movedTM#2 with Ta#49 has been moved to the west
target station from the conditioning station.
  
  1341   Monday, August 29, 2016, 13:34 David WangConditioning StationStandard OperationTM2 TM2 has been disconnected at TCSI stopped TCS water pumps and vacuum pumps
also.   TM2 and TCS will be vented tomorrow
morning.
  
  1340   Thursday, August 25, 2016, 14:25 Travis CaveSpent Target VaultStandard Operation SiC#33Spent Target moveSiC#33 was placed into pail #141 which
in turn was placed into slot 2B of the vault.
I was 295mS/hr upon removal from the south
 Vault_Storage_August_25_2016.pdf 
  1339   Thursday, August 25, 2016, 13:59 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Sep, 2016)Weekly update schedule.  See attachment
1,2.
 Target_Hall_shedule_130_Apr_to_Sep.pdfTarget_Hall_shedule_130_Apr_to_Sep.mpp 
  1338   Thursday, August 25, 2016, 08:43 David WangConditioning StationStandard OperationTM2 All TM2 connections to TCS are done.The HV cover is installed. The Faraday
cage at B2 level is locked also.The TCS and
TM2 are still pumping down. Everything is
  
  1337   Thursday, August 25, 2016, 08:36 David WangConditioning StationStandard OperationTM2 Helium pressure test on TM2 HS water lline I did a helium pressure test on TM2 HS
water line at TCS. Leak detector base leak
rate only could get to 1.8x e-8 atm.cc/sec
  
  1336   Wednesday, August 24, 2016, 14:42 Anders MjosConditioning StationStandard OperationTM2Ta#49ConditioningWednesday, August 24, 2016, 14:42: RGA
on
Wednesday, August 24, 2016, 20:27:
 TCS-2016-08-24_Ta#49.rgaTa#49.docx 
  1335   Wednesday, August 24, 2016, 14:37 Anders MjosSouth Hot-CellStandard Operation SiC#33PIE The target was inspected by Anders
and Chad. The target was in good condition
as can be seen on the photos on DocuShare.
  
  1334   Wednesday, August 24, 2016, 11:06 Travis CaveSouth Hot-CellStandard OperationTM2Ta#49module moved and electrical checkTM#2 with Ta#49 has had its electrical
check and was moved to the conditioning station.
see the attached pdf for the electrical check
 TM2_elechk_SiC34_SHC.PDF 
  1333   Wednesday, August 24, 2016, 10:45 David WangConditioning StationStandard OperationTM2 TM2 vacuum system has been connected at TCSStart of roughing now.   
  1332   Wednesday, August 24, 2016, 10:44 David WangSouth Hot-CellStandard OperationTM2 SHC, TM2 leak check on HS line.Chad and I leak checked Tm2 Hs line with
new target installed. Base LR 0.0Xe-9 atm.cc/sec.  
No leak has been found. This line will be
  
  1331   Wednesday, August 24, 2016, 10:41 David WangITWStandard OperationTM2 TM2 was disconnected in ITW yesterday.TM2 was disconnected in ITW yesterday and
moved to SHC.
  
  1330   Wednesday, August 24, 2016, 09:19 chad fisherSouth Hot-CellMaintenance  Anteroom Clean -up paint prepRemaining items from anteroom have been
bagged and removed (save the boot boxes,
1 garbage can and 1 coverall garbage can).
  
  1329   Wednesday, August 24, 2016, 09:17 chad fisherSouth Hot-CellStandard OperationTM2 Ta#49Ta#49 has been installed on TM2 and tested.
All high current fasteners torqued to 130
in lbs.
  