  1268   Monday, June 27, 2016, 13:45 David WangITEStandard Operation  5 Shielding blocks have been transferred from ITW to ITE.ITE is configured to take proton beam.   
  1267   Tuesday, June 21, 2016, 13:47 Travis Cave/ Dan McDonaldSpent Target VaultRepair  Spent Target Vault DoorThe spent target vault door does not open
or close. The emergency door closing did
have to be used to close the door as it was
  
  1266   Wednesday, June 15, 2016, 09:39 Travis CaveSpent Target VaultStandard Operation Ta#47Spent Target moveThe spent Ta#47 target has been moved from
the south hot cell to the spent target vault.
It was placed in pail #137 in spot 4C of
 Vault_Storage_June_15_2016.pdf 
  1265   Tuesday, June 14, 2016, 11:20 David WangITEStandard OperationTM4 TM4 has been connected in ITETM4 and ITE are under roughing now.   
  1264   Tuesday, June 14, 2016, 10:51 Travis CaveITEStandard OperationTM4UC#16module movedTM#4 with UC#16 has been moved from the
conditioning station to the east target station.
  
  1263   Tuesday, June 14, 2016, 08:04 David WangConditioning StationStandard OperationTM4UC#16TM4 has been disconnected at TCSThe TM4 and TCS are vented with argon.    
  1262   Thursday, June 09, 2016, 10:04 David WangConditioning StationStandard Operation  Target Hall schedule for beam schedule 130 (Apr- Sep)Weekly update .  Target_Hall_shedule_130_Apr_to_Sep.mppTarget_Hall_shedule_130_Apr_to_Sep.pdf 
  1261   Thursday, June 09, 2016, 09:44 David WangConditioning StationStandard OperationTM4UC#16TM4 has been connected at TCSIt is ready for HV conditioning/ heating.    
  1260   Thursday, June 09, 2016, 08:37 David WangConditioning StationStandard OperationTM4UC#16TM4 with UCx16 helium pressure test at TCSI did a helium pressure test on TM4 at
TCS with UCX16 target installed on the module.
No leak has been found on all using water
 TM4_withUCx16_helium_pressure_test_at_TCS.pdf 
  1259   Wednesday, June 08, 2016, 08:25 Anders MjosConditioning StationStandard OperationTM4UC#16Conditioning UC#16 Wednesday, June 08, 2016, 08:15:
RGA on

Thursday, June 09, 2016,
 UC#16.docxTCS-2016-06-08_UC#16.rga 
  1258   Tuesday, June 07, 2016, 18:17 David WangConditioning StationStandard OperationTM4UC#16TM4 and TCS turbo pumps are started.TM4 and TCS vacuum system are connected.
  Turbo pumps are started.  Everything
is fine so far.
  
  1257   Tuesday, June 07, 2016, 17:14 David WangConditioning StationStandard OperationTM4UC#16TM4 with UCx16 target has been moved from SHC to TCS.Bill and Yasmine did the move remotely
this afternoon. The move is successful.
  
  1256   Tuesday, June 07, 2016, 17:11 David WangConditioning StationStandard OperationTM4UC#16TM4 UCx16 electrical check and leak check at SHCChad and I finished the TM4 UCx6 electrical
check and leak check at SHC. Leak check result
on HS line is good. There is a dead short
 UCX_16_electrical_test.pdfelectrical_check._TM4_UCx16_at_TCS..pdf 
  1255   Tuesday, June 07, 2016, 11:42 David WangSouth Hot-CellStandard OperationTM4Ta#47electrical check on TM4 with old Ta target at SHC.I did an electrical check on TM4 with the
old target still installed. The number is
a little bit low on 500V mega check between
 electrical_check_2016-06-07._TM4_with_old_Lp_Ta_target..pdfelectrical_check_2016-06-07._TM4_with_old_Lp_Ta_target..pdf 
  1254   Tuesday, June 07, 2016, 11:37 David WangITEStandard OperationTM4Ta#47TM4 has been moved from ITE to SHCBill and Yasmine did the move. Everything
is good.
  
  1253   Tuesday, June 07, 2016, 11:36 David WangITEStandard OperationTM4Ta#47TM4 has been disconnected in ITE.Dan and I disconnected TM4 in ITE. HS water
lines has been purged.
  
  1252   Friday, June 03, 2016, 16:04 Aurelia LaxdalSouth Hot-CellRepairTM3 5K mega test on TM3

    

       
            
  
  1251   Friday, June 03, 2016, 11:35 Travis CaveSouth Hot-CellStandard OperationTM3no targetmodule movedTM#3 has been moved back to the north east
silo.
  
  1250   Thursday, June 02, 2016, 18:04 Aurelia LaxdalSouth Hot-CellRepairTM3 5K mega test on TM3

    

       
            
 DSC_0821.JPGDSC_0822.JPG 
  1249   Thursday, June 02, 2016, 11:59 David WangSouth Hot-CellRepairTM3 5K mega test on TM3I did a 5KV mega test on TM3.  Only5Mohm
@5kV between coli line PQ and chassis(ground).
It confirmed the close gap between P,Q and
 5K_mega_check_on_TM3.pdf 