Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  RH-Cyclotron, Page 9 of 11  Not logged in ELOG logo
ID Date Author Category Type Subject
  42   Tuesday, April 08, 2014, 10:45 Travis CaveShieldingStandard OperationLarge shield door on the RH B2 level

The large shield door on the RH B2 level of the remote handling building has been shut.

  41   Monday, March 03, 2014, 15:07 Grant MinorElevation JackStandard OperationCyclotron Lid-Down Report Monday 3-March-2014

The Cyclotron Lid Down was successfully completed today on Work Permit C2014-03-03-6.

The system only tripped twice on the way down.  Both trips were at Station 9, at the following Master Syncro readings: 43194, 39198.

Oil was observed on the Jack #1 platform, but it was determined that it was coming from the crane when it's parked in the beam-on position, and not actually from the elevating system.

The final counter readings after the lower limit was reached were recorded:

Final Lid-Down counter readings
Station Reading
1 32
2 33
3 28
4 32
5 32
6 32
7 33
8 30
9 33
10 35
11 34
12 32

The Master Syncro was recorded at 28.  All station yoke gaps were very loose on the .25" shim, which makes sense, as they are about 70 thou lower than the starting position before lid-up this year (100 counts at each station).

The system was NOT re-indexed.  The decision was made to wait until lid-up next year to re-index.  The lit should be raised until the Master is at about 100 counts, then the yoke gaps checked and adjusted as required.

Regards,

Grant

  40   Monday, March 03, 2014, 13:09 Travis CaveCyclotronStandard Operationshields

all shields, porthole covers and ladder out and copper blockers in. Some conmination was found on the pads of the ladders (about a 1000 count or so) and was removed.

  39   Wednesday, February 26, 2014, 14:55 Travis CaveShieldingStandard Operationshields

More shields have been removed from the cyclotron only 16 remain. I was also noted that the lift trolley is making an odd noise and will be looked at after the shutdown.

  38   Tuesday, February 25, 2014, 15:00 Travis CaveShieldingStandard Operationshields

Started on the removal of shields.

  37   Friday, February 21, 2014, 15:58 Bevan MossCyclotronStandard OperationOld Monitor Box Removed, New installed

During the electrical test the was no contact.  To help investigate further the Montitor box was removed from the Cyclotron. It was found to have zero counts. The issue is believed to have to do with the fit of the box but confirmation of the writing harness continuity needs to be completed. This will continue on Monday. 

 

Bevan Moss wrote:

 One of the beam spill monitor boxes was removed and placed into a lead coffin. The fields around the coffin prior to the monitor being placed in were 145 uSv/hr just above the box and 33.5 uSv/hr inside of it. A swipe was taken inside the box at this time and a count of zero was found. The tray for the monitor box was then placed into the coffin and the monitor removed from the cyclotrons. The field above the coffin with the monitor box was 1.0 Sv/hr. Safety hinted that it may be possible to put this in the decay storage tunnel. The copper block was then returned to the coffin. The fields above the the coffin were now 9 Sv/hr. The lid was returned to the coffin and returned to it storage place. The new monitor box was then installed into the Cyclotron. The box only hung up on the pins once and there was some slight difficulties unlatching. From previous experience once fully unlatched a slight tap in the latch direction seems to allow it to release easier.  Overall the installation was considered very smooth. 

 

  36   Friday, February 21, 2014, 11:05 Bevan MossCyclotronStandard OperationOld Monitor Box Removed, New installed

 One of the beam spill monitor boxes was removed and placed into a lead coffin. The fields around the coffin prior to the monitor being placed in were 145 uSv/hr just above the box and 33.5 uSv/hr inside of it. A swipe was taken inside the box at this time and a count of zero was found. The tray for the monitor box was then placed into the coffin and the monitor removed from the cyclotrons. The field above the coffin with the monitor box was 1.0 Sv/hr. Safety hinted that it may be possible to put this in the decay storage tunnel. The copper block was then returned to the coffin. The fields above the the coffin were now 9 Sv/hr. The lid was returned to the coffin and returned to it storage place. The new monitor box was then installed into the Cyclotron. The box only hung up on the pins once and there was some slight difficulties unlatching. From previous experience once fully unlatched a slight tap in the latch direction seems to allow it to release easier.  Overall the installation was considered very smooth. 

Attachment 1: IMG_1346.JPG
IMG_1346.JPG
Attachment 2: IMG_1345.JPG
IMG_1345.JPG
Attachment 3: IMG_1344.JPG
IMG_1344.JPG
Attachment 4: IMG_1343.JPG
IMG_1343.JPG
Attachment 5: IMG_1342.JPG
IMG_1342.JPG
Attachment 6: IMG_1341.JPG
IMG_1341.JPG
Attachment 7: IMG_1339.JPG
IMG_1339.JPG
  35   Friday, February 07, 2014, 10:50 Travis CaveCyclotronStandard Operation2C install

2C has been installed into the cyclotron.

  34   Friday, January 31, 2014, 10:07 Travis CaveCyclotronStandard Operation2C removal

2C has been successfully removed from the cyclotron and is now currently sitting in the B2 level of the RH building. A tank access was needed to feel the stuck QDL.

  33   Thursday, January 30, 2014, 13:47 Travis CaveCyclotronStandard Operationshields

All shields, pothole covers, and ladders have been installed into the cyclotron.

  32   Wednesday, January 29, 2014, 15:08 Bevan MossCyclotronStandard OperationShielding and Port Hole Covers

 The Shielding and the Port Hole Covers have all been installed. No issues with the installation have caused any problems. This orbit, radial, and vertical read back continues to be an issue.

  31   Tuesday, January 28, 2014, 14:59 Travis CaveShieldingStandard Operationshields

200's, 400's, 500's, 600's, and a pallet of 700's have been installed

  30   Monday, January 27, 2014, 14:42 Travis CaveShieldingStandard Operationshields and radiation survey

The cyclotron radiation survey was aborted due to the orbit not working recording the numbers correctly. One shield has been in installed.

Jan 29th: uploaded meeting minutes from January 28th regarding the orbital counter problem. - Grant Minor

 

Attachment 1: Meeting_Orbital_Counter_Problem_Jan_2014.pdf
Meeting_Orbital_Counter_Problem_Jan_2014.pdf
  29   Friday, January 24, 2014, 14:10 Travis CaveCyclotronStandard OperationCopper blockers

The copper blockers have been removed from the cyclotron and placed into the coffins.

  28   Thursday, January 23, 2014, 18:47 Grant MinorElevation JackStandard OperationCyclotron Lid-Up Report - 22 Jan 2014

Yesterday Grant Minor (me), Maico Dalla Valle, Dan Louie, and Arthur Leung worked with Operations to perform the Cyclotron Lid-Up task for the 2014 winter maintenance.

Work Permit 2014-01-22-2 was issued for this job.

In general, the lid up operation was rough at the beginning.  The system began to trip-out within about 500 counts on the mechanical counter, just when the jacks started taking the load, then continued to trip within the first ~ 3 inches of travel.  Multiple station jogs, complete lowerings, and complete raisings were required to get beyond the rough spot. 

I tried as best as possible to record the mechanical counters for each trip event, as well as confirm the master synchro count and culprit station with Arthur.  The data I collected is summarized below:

Start of Operation: All stations were indexed with yoke gaps within .005" and .010" of the .250" nominal shim stock (see previous e-logs).  Mechanical counters were all set to 100 counts (each count is approximately .001").

1. First lid up attempt tripped at less than 1" of travel.  Station 9 was found to be lagging adjacent stations.  It as jogged in local mode as shown:

Table 1
Jack Stn. # Count Jog Val.
8 699  
9 576 705
10 706  

2. Lid was raised again and stalled.  Station 11 was found to be lagging and was jogged:

Table 2
Jack Stn. # Count Jog Val.
8 724  
9 715  
10 735  
11 668 725
12 728  

3. Lid was raised again and stalled.  The decision was made to lower completely and raise again.  All station counters were recorded before lowering:

Table 3
Jack Stn. # Count
1 804
2 812
3 795
4 811
5 805
6 808
7 804
8 797
9 783
10 809
11 802
12 801

4. Lid stalled on the way down.  Station 9 was found to be lagging and was jogged:

Table 4
Jack Stn. # Count Jog Val.
8 550  
9 672 555
10 559  

5. Lid was lowered completely and then raised again.  It tripped at Station 9.  It was examined and found not to be lagging a great deal.

Table 5
Jack Stn. # Count
8 589
9 577
10 594

6. System was reset and lid was raised further.  It continued to trip.  Station 9 was examined and not found to be out.

Table 6
Jack Stn. # Count
8 812
9 807
10 818

7. Lid was lowered completely and then raised again.  It tripped again, and Station 9 was found to be out.  It was jogged with some intentional overshoot.

Table 7
Jack Stn. # Count Jog Val.
8 855  
9 814 870
10 862  

8. Lid was raised again and tripped.  The decision was made to lower lid completely.  Some counter values were recorded when the lid had reached the lower limit, for comparison to the starting reference.

Table 8
Jack Stn. # Count
8 035
9 041
10 039

9. Lid was raised again and traveled more smoothly until tripping at around 850 counts.  6 counter values were recorded.  Station 9 was found to be lagging and was jogged:

Table 9
Jack Stn. # Count Jog Val.
8 826  
9 826 836
10 835  
11 853  
12 852  
1 854  
2 836  

10. Lid was raised again and tripped.  Station 9 was found to be lagging and was jogged:

Table 10
Jack Stn. # Count Jog Val.
8 965  
9 932 973
10 973  

11. Lid was raised again and tripped.  Station 9 was found to lag very slightly (but within the normal variation band), and was jogged:

Table 11
Jack Stn. # Count Jog Val.
7 998  
8 988  
9 984 998
10 994  

12. Lid was raised further and tripped again.  Four of the counters recorded and the group broke for lunch (approximately 1 hr).  The lid was left at this position over lunch.

Table 12
Jack Stn. # Count
8 1033
9 1025
10 1042
11 1035

13. After lunch, the lid was raised up to about 1090 counts with 4 trips.  Counters were read as below:

Table 13
Jack Stn. # Count
8 1089
9 1088
10 1097

14.  Lid was raised but tripped almost immediately.  Decision was made to lower again.  Counters at bottom limit were read again:

Table 14
Jack Stn. # Count
8 0038
9 0046
10 0043

15. Lid was raised with 3 trips.  Station 9 was found to be lagging and was jogged:

Table 15
Jack Stn. # Count Jog Val.
8 1202  
9 1107 1216
10 1212  

16. Lid was lowered completely, then raised.  It went up fairly smoothly and tripped out at about 1350 counts.  All counters were recorded:

Table 16
Jack Stn. # Count
1 1347
2 1354
3 1337
4 1354
5 1347
6 1352
7 1350
8 1339
9 1334
10 1349
11 1350
12 1350

17.  A few more attempts were made to raise the lid with a few more trips.  The system traveled in longer bursts and more smoothly between trips.  Counters were recorded and stations 9 and 11 were jogged:

Table 17
Jack Stn. # Count Jog Val.
8 1956  
9 1901 1972
10 1967  
11 1938 1968
12 1969  

18. System was reset and lid was raised again with a few more trips close together.  The decision was made to lower the lid completely and raise again.  Master synchro was recorded at 2285 before lowering.

19. Lid was lowered completely and raised fairly smoothly up to a master count of 2363 before tripping out on stations 1 & 9.

20. A few attempts were made to lower the lid slightly (not all the way) and then raise again.  This did not seem to reduce the frequency of trips.  The system tripped out around 2820 and all counters were recorded before taking a short break to allow the contactors to cool down:

Table 20
Jack Stn. # Count
1 2809
2 2822
3 2805
4 2827
5 2803
6 2822
7 2809
8 2817
9 2806
10 2823
11 2810
12 2826

21. After the break, there was a raise and lower cycle within about 3600 counts that I was not present for.  When I had returned the system was still rising in small bursts and tripping out on station 9 mostly.  Over a span of 5 trips, Station 9 was jogged 5 times by between 20 and 50 counts, with 20-count overshoot.

22. The master synchro passed 3600 counts and then the system tripped.  Stations 9 and 10 were recorded and Station 9 was jogged:

Table 22
Jack Stn. # Count Jog Val.
9 3612 3665
10 3645  

23.  The master passed 3800 counts, and then they system went up smoothly for the first time by about 1500 counts before stopping. Some counters were recorded:

Table 23
Jack Stn. # Count
8 5396
9 5385
10 5405
11 5405

24.  Lid was raised again and stopped around 6350.  The group paused to check the tank seal and all counters were recorded:

Table 24
Jack Stn. # Count
1 6377
2 6338
3 6334
4 6336
5 6342
6 6348
7 6346
8 6346
9 6319
10 6333
11 6343
12 6347

25. The lid was raised further with 2 trips at station 9.  Stations 9 and 10 were checked and station 9 was jogged:

Table 25
Jack Stn. # Count Jog Val.
9 7178 7224
10 7204  

26. Lid was raised again with 2 trips initially and then smooth travel up to a Master count of 9600.  After 3 more trips and resets, I began recording just the station trips and master counts at each trip.  No jogs were required during this period.

27. Jacks 1 & 5 tripped at 10,200 counts on the master.

28. Jacks 1 & 9 tripped at 11,500 counts on the master.

29. Jack 9 tripped at 13,400 counts on the master.  Several trips occurred immediately after this.  Counter readings were taken and station 1 was jogged:

Table 29
Jack Stn. # Count Jog Val.
1 13,409 13,500
2 13,508  
3 13,461  
4 13,501  
5 13,410 13,500
6 13,498  
7 13,444 13,500
8 13,489  
9 13,436 13,500
11 - 13.500
12 13,496  

30. Lid was raised again with trips at station 1, 5, 7 & 9.  Master synchro count was 15,600.

31. Lid was raised again with trip at stations 1 & 7.  Master synchro count was 18,800.

32. Lid was raised again with trips at stations 5, 7, and 9.  Master synchro count was 21,650.

33. Lid was raised again with trips at stations 1, 3, 5, 7, 9, 11.  Master synchro count was 23,360.

34. Lid was raised again with trips at stations 1, 5, 7, 9. Master synchro count was 23,700.

35. Lid was raised again with trip at station 9.  Master synchro count was 25,420.

36. Lid was raised again with trip at station 7. Master synchro count was 27,700.

37. Lid was raised again with trip at station 5.  Master count was 27,700.

38. Lid was raised again with trip at station 7. Master count was 30,300.

39. Lid was raised again with trip at stations 1 & 3. Master count was 33,650.

40. Lid was raised with trip at station 7.  Master count was 37,400.

41.  A moaning / groaning noise was heard from the structure around 38,000 counts.  This noise was also observed during the 2013 lid-up.

42. Lid was raised with trip at station 7. Master count was 39,722.

43. Lid was raised with trip at station 1.  Master count was 41,600.

44. Lid was raised with trip at station 9.  Master count was 42,857.

45.  All counters were read and selected stations were jogged:

Table 45
Jack Stn. # Count Jog Val.
1 42,774  
2 42,797  
3 42,751 42,808
4 42,799  
5 42,769 42,808
6 42,794  
7 42,731 42,800
8 42,812  
9 42,761 42,801
10 42,800  
11 42,769 42,803
12 42,815  
Master Sync 42,857  

46. Lid was raised but tripped at station1.  Station one count was found to be behind and was jogged from 42,804 to 42,880.

47. Lid was raised until limit switches were contacted.  All final counter readings were recorded:

Table 47 - Final Counts
Jack Stn. # Count
1 47,396
2 47,410
3 47,402
4 47,403
5 47,396
6 47,409
7 47,399
8 47,401
9 47,400
10 47,403
11 47,39? (misread?)
12 47,400

***

Photos of the limit switches and the reference "stick" relative to the roof beam are attached.  The stick appears to be between 1/16" and 1/8" clear of the roof beams.

Attachment 1: Lid_Up_Limit_and_Stick_22jan2014_(1).JPG
Lid_Up_Limit_and_Stick_22jan2014_(1).JPG
Attachment 2: Lid_Up_Limit_and_Stick_22jan2014_(2).JPG
Lid_Up_Limit_and_Stick_22jan2014_(2).JPG
Attachment 3: Lid_Up_Limit_and_Stick_22jan2014_(3).JPG
Lid_Up_Limit_and_Stick_22jan2014_(3).JPG
Attachment 4: Lid_Up_Limit_and_Stick_22jan2014_(4).JPG
Lid_Up_Limit_and_Stick_22jan2014_(4).JPG
Attachment 5: Lid_Up_Limit_and_Stick_22jan2014_(8).JPG
Lid_Up_Limit_and_Stick_22jan2014_(8).JPG
Attachment 6: Lid_Up_Limit_and_Stick_22jan2014_(9).JPG
Lid_Up_Limit_and_Stick_22jan2014_(9).JPG
  27   Monday, January 20, 2014, 12:00 Grant MinorElevation JackStandard OperationIndexing Check of Cyclotron Jack Stations

Maico Dalla Valle and Grant Minor, supported by Dan Louie and Arthur Leung, entered the Cyclotron Vault on January 15th, 2014 to check the indexing of the jacking stations.  520MeV work permit 2014-01-15-4 was filled out for this work.

Yoke gaps at all stations were found to be within .005" to .010" of the .25" shim stock, and all mechanical counters were found to read zero.  This is consistent with the recalibration done on March 19th, 2013.

The system is properly indexed mechanically, and ready for lid-up.

Grant

  26   Friday, January 17, 2014, 07:53 Travis CaveTrolleys servicedStandard OperationTrolley checks

All trolleys work electrically and control wise. One encoder was found non functioning on the upper resonator trolley for the vertical drive it was replaced, we've no move replacements of those current type of encoders so a wholesale replacement of all the trolley's encoders will have to be done post shutdown. Also the wiring for the outrigger is in need of replacement but will work for this shutdown it will also have to be replaced post shutdown as well. The upper resonator trolley has also been setup to remove X2C.

  25   Thursday, January 16, 2014, 08:46 maicodallavalleTrolleys servicedMaintenancePre Cyclotron work servicing and checking

This is a list of all the trolleys and other equipment witch were checked and serviced prior to work in the Cyclotron.

- Video Trolley cleaned and checked (no adjustments needed)

-Lift Trolley cleaned and checked (no adjustments needed)

- Left Outrigger cleaned and checked

 All of the bearings in the festooning wheels  were changed.

  Drive chain needed adjustment. (modification to wheel mounting bracket so that chain could be adjusted)

-Right Outrigger cleaned and checked

 All of the bearings in the festooning wheels were changed.

 Drive chain needed adjustment. (modification to wheel mounting bracket so that the chain could be adjusted)

-Tool Trolley cleaned and checked

 One of the support wheels was checked and found to be out of alignment. (an adjustment was made to correct the problem) 

-Upper Resonator Trolley cleaned and checked (no adjustments needed)

-Service Bridge cleaned and checked

  Center post mount was rotated by hand. (no adjustment needed)

-Service Bridge Carrier cleaned and checked

 The two hydraulic cylinders witch lift the Service Bridge into the Cyclotron leaked last year.They were rebuilt last year and are not leaking.

 The two drive chains witch run the Carrier North and South were found to be too tight. (an adjustment was made to correct the problem)

 

 

  24   Monday, September 30, 2013, 14:02 Travis CaveService BridgeMaintenancenew festooning

The festooning and bearings for the festooning cars for both outriggers has been replaced and it is in working order.

  23   Thursday, April 11, 2013, 19:00 Grant MinorElevation JackMaintenanceUpper Bearing at Jack Station 9 + Fall Protection Upgrades

There was a brief access period to the Cyclotron vault during April 9 to 12, 2013 due to other Cyclotron issues.

This time was utilized to perform the following Elevating System tasks:

- Drilling of 2 (two) holes for concrete anchors (DBI Sala Product 2100085) for self-retracting lifelines (see TRIUMF purchase order TR197399)

- Installation of 2 (two) ceiling-hung self-retracting lifeline units, one above the climb-up access point to the bearing, and the other above the recently installed outboard safety platform (see TRH1217)

- Complete service of the upper bearing assembly at Station 9 (dis-assembly of bearing races, cleaning off old grease, inspection of races and guide tube, application of new grease, re-assembly of races)

- Tear down of safety handrails for some minor modifications (see upcoming Rev B to TRH1217 and sub-components)

 All work was completed on Wednesday April 10th by Dan Wright and Maico Dalla Valle.

Attachment 1: station_9_ceiling_anchors_SRLs_10april2013-002.JPG
station_9_ceiling_anchors_SRLs_10april2013-002.JPG
Attachment 2: station_9_ceiling_anchors_SRLs_10april2013-003.JPG
station_9_ceiling_anchors_SRLs_10april2013-003.JPG
Attachment 3: station_9_ceiling_anchors_SRLs_10april2013-004.JPG
station_9_ceiling_anchors_SRLs_10april2013-004.JPG
Attachment 4: station_9_ceiling_anchors_SRLs_10april2013-006.JPG
station_9_ceiling_anchors_SRLs_10april2013-006.JPG
ELOG V2.9.2-2455