  29   Friday, January 24, 2014, 14:10 Travis CaveCyclotronStandard OperationCopper blockersThe copper blockers have been removed from
the cyclotron and placed into the coffins.
  
  32   Wednesday, January 29, 2014, 15:08 Bevan MossCyclotronStandard OperationShielding and Port Hole Covers The Shielding and the Port Hole Covers
have all been installed. No issues with the
installation have caused any problems. This
  
  33   Thursday, January 30, 2014, 13:47 Travis CaveCyclotronStandard OperationshieldsAll shields, pothole covers, and ladders
have been installed into the cyclotron.
  
  34   Friday, January 31, 2014, 10:07 Travis CaveCyclotronStandard Operation2C removal2C has been successfully removed from the
cyclotron and is now currently sitting in
the B2 level of the RH building. A tank access
  
  35   Friday, February 07, 2014, 10:50 Travis CaveCyclotronStandard Operation2C install2C has been installed into the cyclotron.   
  36   Friday, February 21, 2014, 11:05 Bevan MossCyclotronStandard OperationOld Monitor Box Removed, New installed One of the beam spill monitor boxes
was removed and placed into a lead coffin.
The fields around the coffin prior to the
 7x 
  37   Friday, February 21, 2014, 15:58 Bevan MossCyclotronStandard OperationOld Monitor Box Removed, New installedDuring the electrical test the was no contact.
 To help investigate further the Montitor
box was removed from the Cyclotron. It was
  
  40   Monday, March 03, 2014, 13:09 Travis CaveCyclotronStandard Operationshieldsall shields, porthole covers and ladder
out and copper blockers in. Some conmination
was found on the pads of the ladders (about
  
  50   Tuesday, January 27, 2015, 14:40 Travis CaveCyclotronStandard OperationDay one of in tank workDay one of RH in tank work for the cyclotron
(shields and blockers stuff like that) many
pictures were taken.
  
  51   Wednesday, January 28, 2015, 14:33 Travis CaveCyclotronStandard OperationDay two of in tank workAll copper blocker removed from the cyclotron
and first radiation survey done. Shields
start tomorrow.
  
  52   Thursday, January 29, 2015, 14:53 Travis CaveCyclotronStandard OperationDay three of in tank workOver 50% of the shields are in some 700's
left and the monitor box covers.
  
  53   Friday, January 30, 2015, 15:02 Travis CaveCyclotronStandard OperationDay four of in tank workAll shields, ladders and pothole covers
are in. One rad survey left to do.
  
  54   Monday, February 02, 2015, 14:28 Travis CaveCyclotronStandard OperationDay five of in tank workFinal Radiation Survey done. All in tank
work completed bridge removed from the tank.
  
  55   Wednesday, February 04, 2015, 13:57 Travis CaveCyclotronStandard Operation2C removal2C has been removed from the cyclotron.   
  57   Tuesday, February 17, 2015, 11:28 Travis CaveCyclotronStandard Operation2C Installation2C extraction probe has been re-installed
in the cyclotron. After some problems on
the first install attempt, do to a busted
  
  58   Friday, March 06, 2015, 14:38 Travis CaveCyclotronStandard OperationShield RemovalAll shields and ladders have been removed
from the tank, all the port holes have been
uncovered, the tank seal has been vacuumed,
  
  62   Tuesday, March 17, 2015, 13:04 maicodallavalleCyclotronMaintenanceUpper Bearings Station #5 and #10The Upper bearings on Station #5 and Station
#10 have been serviced. The Upper Bearing
were disassembled. The old gear was removed
  
  65   Friday, March 27, 2015, 07:31 Dan McDonaldCyclotronRepairLid up operationsLid up recap for  March 26th 2015.

Start time 14:50       
  
  66   Friday, March 27, 2015, 11:25 Travis CaveCyclotronStandard OperationCopper BlockersCopper Blockers have been removed from
the cyclotron and one ladder has been installed.
  
  67   Thursday, April 02, 2015, 12:09 Dan McDonaldCyclotronStandard OperationLid Down operations April, 2, 2015Lid down Start at 11:17, lid went down
without any issues or stop's. Lid finish
at 11:45 
  