Entry  Saturday, April 04, 2020, 09:47, Dan McDonald, Cyclotron, Standard Operation, Lid down operations lid_down_2020.xlsx
Lid down operations for 2019/2020 shutdown went ahead as planned on March 10th 2020 with Dan Louie and Arthur Leung absent due to a conference. Please
see attached file for station counter numbers. Station two right side Highfield gear box was making intermittent growling from outboard bearing, this station
is next on scheduled maintenance and will be inspected post removal next shutdown. Station 3 has spare jack set 13 in place, using Operations thermal camera
Entry  Friday, April 19, 2024, 15:18, Adam Newsome, Cyclotron, Standard Operation, Lid down operation - 2024 Elevation_System_Checklist_-_2024.xlsx
The lid down operation took place on April 19, 2024. 

The  system was energized a few minutes ahead of time.
Entry  Friday, March 31, 2023, 13:22, Adam Newsome, Cyclotron, Standard Operation, Lid down operation - 2023 Elevation_System_Checklist_-_March_31_2023.pdf
The lid down operation took place on Mar. 31, 2023. 

The  system was energized a few minutes ahead of time.
Entry  Wednesday, April 27, 2022, 16:05, Adam Newsome, Cyclotron, Standard Operation, Lid down operation - 2022 
The lid down operation took place on Apr. 27, 2022. 

The  system was not energized well ahead of time to allow to "warm up",
Entry  Tuesday, April 30, 2024, 15:00, Adam Newsome, Cyclotron, Standard Operation, Lid down operation (second) - 2024  Elevation_System_Checklist_-_2024_-_Second_Lid_Down.pdf
A second lid down operation took place on April 30, 2024. 

The  system was energized a few minutes ahead of time.
Entry  Thursday, April 02, 2015, 12:09, Dan McDonald, Cyclotron, Standard Operation, Lid Down operations April, 2, 2015 
Lid down Start at 11:17, lid went down without any issues or stop's. Lid finish at 11:45 
 
 
Entry  Friday, March 15, 2013, 15:18, Grant Minor, Cyclotron, Standard Operation, Lid Down Successful - Mechanical Counter Readings 
Prior to the lid-down operation today, the Cyclotron was lowered by 0.75" and then raised again to confirm that the upper limit switches were working. 
Dan Louie confirmed this from the control racks.
Maico and Grant walked around the perimeter of the cyclotron to inspect each station and ensure that there were no interferences, e.g. dial indicator
Entry  Tuesday, March 15, 2016, 13:56, Dan McDonald, Cyclotron, Standard Operation, Lid Down 2016 
Lid down Started at 12:15, station and count numbers. Lid went down with out incident as station 1 and 7 show the counters will need replacing. We are
going to change counters before the end of this shutdown to ensure proper orientation in case of emergency lid up scenario. 
Start          12:15                  
Entry  Tuesday, April 08, 2014, 10:45, Travis Cave, Shielding, Standard Operation, Large shield door on the RH B2 level 
The large shield door on the RH B2 level of the remote handling building has been shut.
Entry  Wednesday, February 03, 2021, 12:37, Adam Newsome, Cyclotron, Development, Ladder Handling Tool - First In-Tank Test (SAS0824) Capture.PNGCapture5.PNGCapture14.PNG
The newly developed Ladder Handling Tool (TRH1401), which is used to move the maintenance ladders from the #5 resonator area closer to the centre post,
was tested inside the cyclotron tank to perform the actual operation. This is a task that was historically performed by operators, resulting in dose received
(typically 0.1 - 0.3 mSv for two people, twice per annual shutdown). This tool completely eliminates the need for people to receive this dose - only a
Entry  Wednesday, June 29, 2022, 12:12, Adam Newsome, Probe, Development, LE1/LE2 Probe Frame - Updates PXL_20220629_175832571.jpg
The LE1/LE2 Probe Frame was mounted on the Upper Resonator Trolley in the mockup with the intention of confirming functionality and making some updates
to the probe installation/removal procedure document.
 
Entry  Tuesday, March 14, 2017, 17:07, Jason Kapalka, Probe, Maintenance, LE probe removal simulation exercise 
A simulated removal of the LE2 Probe from the Cyclotron tank was performed by the RH and Probes group using the 
service bridge, upper resonator trolley, LE probe attachment, and the (soon to be) attached LE Probe removal 
procedure on 2017-02-23.
Entry  Wednesday, January 31, 2024, 11:39, Adam Newsome, Elevation Jack, Maintenance, Jack station 11: synchro replaced 
Because of observed noise on the synchro at jack station 11 during recent shutdown lid up/down operations, the synchro at this station was replaced on
Jan. 31, 2024. The procedure in Document-234859 was followed. 
Entry  Wednesday, September 14, 2016, 11:30, Dan McDonald, Elevation Jack, Maintenance, Jack station 10B 14x
Annual jack maintenance : Jack 10b upon inspection it was found that the output shaft seal on 10b was in need of replacement. In past years RH personal
had to remove a LoveJoy coupling which required cutting of the coupler due to galling and possible interference tolerances being out. We sourced sample
split seals from Motion Canada that can be installed with out coupling removal we will install and monitor to determine the effectiveness and the possibility
Entry  Wednesday, July 24, 2024, 11:39, Adam Newsome, Cyclotron, Standard Operation, Investigation of faulty Al-ALCW signal 
Fault 16710 was initially assigned to Remote Handling: IBOP0206 giving false positive - Al-ALCW water pressure shows "off" when it isn't; The safety system
is reporting that Al-ALCW water pressure is "off" (page SVG) when the system is still on and at normal operating pressure.
Entry  Wednesday, February 27, 2013, 12:08, Travis Cave, Cyclotron, Standard Operation, Installation of 2C 
2C has been installed located on all QDLs and all the numbers, continuity check done and passed. Bridge has been removed from the cyclotron tank.
Entry  Tuesday, January 23, 2024, 14:03, Adam Newsome, Elevation Jack, Maintenance, Inspection of elevating system motor contacts Elev_Motor_1.jpgElev_Motor_2.jpg
Motor contactors for the cyclotron elevating system jacks were inspected on 2025-01-23 by Joel Semilla under work permit C2024-01-19-1.
Joel's assessment is as follows:
"All the twelve magnetic contactors have the same contact tips condition. Last year, I have [sic] to take out the contacts from the housing
Entry  Monday, January 20, 2014, 12:00, Grant Minor, Elevation Jack, Standard Operation, Indexing Check of Cyclotron Jack Stations 
Maico Dalla Valle and Grant Minor, supported by Dan Louie and Arthur Leung, entered the Cyclotron Vault on January 15th, 2014 to check the indexing of
the jacking stations.  520MeV work permit 2014-01-15-4 was filled out for this work.
Yoke gaps at all stations were found to be within .005" to .010" of the .25" shim stock, and all mechanical counters were found
Entry  Wednesday, February 06, 2013, 17:42, Grant Minor, Elevation Jack, Maintenance, In-situ jack power screw lubrication inspection - Stations 9, 10, 11, and 6 16x
Due to concerns raised regarding the state of the lubrication of the power screws at Station 9, the lubrication was visually inspected by me and Ron
Kuramoto on February 4th.
Photos are attached.
Entry  Monday, February 04, 2013, 13:52, Grant Minor, Service Bridge, Repair, Hydraulic cylinder failure on service bridge 6x
The hydraulic cylinder on the West side of the service bridge (used to raise the bridge for insertion into the Cyclotron) failed this morning, leaking
oil in the vault tunnel.  Most likely this was due to a failed seal or gasket.
Maico Dalla Valle has removed both the East and West cylinders for refurbishment and is pursuing repair kits from Hyseco.