120
|
Saturday, April 04, 2020, 09:47 |
Dan McDonald | Cyclotron | Standard Operation | Lid down operations | Lid down operations for 2019/2020 shutdown
went ahead as planned on March 10th 2020
with Dan Louie and Arthur Leung absent due |
|
170
|
Friday, April 19, 2024, 15:18 |
Adam Newsome | Cyclotron | Standard Operation | Lid down operation - 2024 | The lid down operation
took place on April 19, 2024. |
|
152
|
Friday, March 31, 2023, 13:22 |
Adam Newsome | Cyclotron | Standard Operation | Lid down operation - 2023 | The lid down operation
took place on Mar. 31, 2023. |
|
140
|
Wednesday, April 27, 2022, 16:05 |
Adam Newsome | Cyclotron | Standard Operation | Lid down operation - 2022 | The lid down operation
took place on Apr. 27, 2022. |
|
172
|
Tuesday, April 30, 2024, 15:00 |
Adam Newsome | Cyclotron | Standard Operation | Lid down operation (second) - 2024 | A second lid down
operation took place on April 30, 2024. |
|
67
|
Thursday, April 02, 2015, 12:09 |
Dan McDonald | Cyclotron | Standard Operation | Lid Down operations April, 2, 2015 | Lid down Start at 11:17, lid went down
without any issues or stop's. Lid finish
at 11:45 |
|
20
|
Friday, March 15, 2013, 15:18 |
Grant Minor | Cyclotron | Standard Operation | Lid Down Successful - Mechanical Counter Readings | Prior to the lid-down operation today,
the Cyclotron was lowered by 0.75" and
then raised again to confirm that the upper |
|
87
|
Tuesday, March 15, 2016, 13:56 |
Dan McDonald | Cyclotron | Standard Operation | Lid Down 2016 | Lid down Started at 12:15, station and
count numbers. Lid went down with out incident
as station 1 and 7 show the counters will |
|
42
|
Tuesday, April 08, 2014, 10:45 |
Travis Cave | Shielding | Standard Operation | Large shield door on the RH B2 level | The large shield door on the RH B2 level
of the remote handling building has been
shut. |
|
128
|
Wednesday, February 03, 2021, 12:37 |
Adam Newsome | Cyclotron | Development | Ladder Handling Tool - First In-Tank Test (SAS0824) | The newly developed Ladder Handling Tool
(TRH1401), which is used to move the maintenance
ladders from the #5 resonator area closer |
|
145
|
Wednesday, June 29, 2022, 12:12 |
Adam Newsome | Probe | Development | LE1/LE2 Probe Frame - Updates | The LE1/LE2 Probe Frame was mounted on
the Upper Resonator Trolley in the mockup
with the intention of confirming functionality |
|
100
|
Tuesday, March 14, 2017, 17:07 |
Jason Kapalka | Probe | Maintenance | LE probe removal simulation exercise | A simulated removal of the LE2 Probe from
the Cyclotron tank was performed by the RH
and Probes group using the
|
|
163
|
Wednesday, January 31, 2024, 11:39 |
Adam Newsome | Elevation Jack | Maintenance | Jack station 11: synchro replaced | Because of observed noise on the synchro
at jack station 11 during recent shutdown
lid up/down operations, the synchro at this |
|
90
|
Wednesday, September 14, 2016, 11:30 |
Dan McDonald | Elevation Jack | Maintenance | Jack station 10B | Annual jack maintenance : Jack 10b upon
inspection it was found that the output shaft
seal on 10b was in need of replacement. In |
14x |
187
|
Wednesday, July 24, 2024, 11:39 |
Adam Newsome | Cyclotron | Standard Operation | Investigation of faulty Al-ALCW signal | Fault 16710 was initially assigned
to Remote Handling: |
|
14
|
Wednesday, February 27, 2013, 12:08 |
Travis Cave | Cyclotron | Standard Operation | Installation of 2C | 2C has been installed located on all QDLs
and all the numbers, continuity check done
and passed. Bridge has been removed from |
|
162
|
Tuesday, January 23, 2024, 14:03 |
Adam Newsome | Elevation Jack | Maintenance | Inspection of elevating system motor contacts | Motor contactors for the cyclotron elevating
system jacks were inspected on 2025-01-23
by Joel Semilla under work permit C2024-01-19-1. |
|
27
|
Monday, January 20, 2014, 12:00 |
Grant Minor | Elevation Jack | Standard Operation | Indexing Check of Cyclotron Jack Stations | Maico Dalla Valle and Grant Minor, supported
by Dan Louie and Arthur Leung, entered the
Cyclotron Vault on January 15th, 2014 to |
|
10
|
Wednesday, February 06, 2013, 17:42 |
Grant Minor | Elevation Jack | Maintenance | In-situ jack power screw lubrication inspection - Stations 9, 10, 11, and 6 | Due to concerns raised regarding the state
of the lubrication of the power screws at
Station 9, the lubrication was visually inspected |
16x |
9
|
Monday, February 04, 2013, 13:52 |
Grant Minor | Service Bridge | Repair | Hydraulic cylinder failure on service bridge | The hydraulic cylinder on the West side
of the service bridge (used to raise the
bridge for insertion into the Cyclotron) |
6x |