Thursday, January 30, 2020, 06:55, Dan McDonald, Cyclotron, Standard Operation, Lid up operations
|
Lid up operations took place on January 21st starting at 10:25 lid went up without issue. Couple things to note are station 11 had a number of spikes
in the first ten inches of travel and number five had a couple in the first five inches of travel. We will monitor these stations and perform maintenance
as needed. Station three which has spares #13 saw above normal heat generation in the right side High field gear box, we will investigate next week. |
Thursday, October 31, 2019, 14:31, Adam Newsome, Service Bridge, Repair, Outrigger 2 Vertical Drive Repair
|
Outrigger 2 vertical drive repair is complete - ball screws were replaced to resolve a jamming issue (this work was done in the summer).
The outrigger has been recalibrated and all limit switches and feedback signals tested. All ranges of motion were tested multiple times as well.
|
Wednesday, September 04, 2019, 15:29, Adam Newsome, Trolley, Maintenance, Connector faceplate and tubing upgrade
|
Tool Trolley:
The connector faceplate was replaced with a new version to allow for more space for service, and consolidate video lines into a single 9-pin CPC
connector. A model and drawing were created and are part of the overall tool trolley assembly (to be added to PDM later): TRH1394 |
Tuesday, January 22, 2019, 07:18, Dan McDonald, Elevation Jack, Maintenance, Station 11-12 jack swap and hoist plate instal
|
Prior to commencing work on jacking stations we installed a wall mounted come along plate as per Jason kapalkas instructions Completed spare jack
swap on station 11 and 12, station 11 was swapped with spare set # 13 and station 12 now has # 14 jack set in its place. Once jack stations where swapped
we proceeded to clean, inspect and re grease 11-12 upper bearings. |
Tuesday, April 03, 2018, 11:57, Travis Cave, Cyclotron, Standard Operation, Blue Shield Door Shut.
|
The Blue Shield Door on the B2 level of the RH building has been closed. |
Friday, February 23, 2018, 15:44, Jason Kapalka, Elevation Jack, Repair, Replacement of Elevating System wiring
|
On January 8, 2018, while troubleshooting the Cyclotron Elevating System during the lid-up operation, the
insulation on the three motor drive wires were repaired (w/ electrical tape) and the two motor brake wires were
replaced (w/ crimped butt splices) between the horizontal conduit below the Cyclotron and the terminal block on
|
Monday, February 19, 2018, 12:58, maicodallavalle, Trolley, Repair, Lift Trolley Repair
|
We had just finished pulling out the ladders from the cyclotron with the lift trolley. We started to run the lift trolley into the cyclotron when it
stopped moving. The radial drive gearbox was the problem. We pulled the gearbox off. Replaced the key and the lift trolley is all repaired. |
Friday, February 02, 2018, 14:14, Don Jackson, Trolley, Repair, Overcurrent on radial drive motor
|
Lower resonator trolley radial motor overcurrent was causing control system to drop
out momentarily. All controlled devices acted as expected and reverted to their fail-safe mode. |
Wednesday, January 31, 2018, 11:20, Isaac Earle, Cyclotron, Standard Operation, HE1 probe reinstalled
|
HE1 probe was reinstalled in the cyclotron this morning as per the procedure in Document 126165. Hardware for the probe head motion had been
repaired/replaced by Probes Group, so the probe head could be put in the fully retracted position. The job went smoothly and nothing unusual was
encountered. |
Thursday, January 25, 2018, 17:16, Isaac Earle, Cyclotron, Standard Operation, HE1 probe removed
|
The HE1 probe was removed from the cyclotron today using the procedure in Document 126165. The reason for removal is so that Probes Groups
can attempt to repair a problem with stuck probe head drive. Due the failure, the probe head was almost at the inboard travel limit (towards cyclotron
center post) at the time of removal. Additional cut-outs were added to the HE probe frame to accommodate the probe head and ribbon cable wheel which were |
Tuesday, January 16, 2018, 13:43, Travis Cave, Cyclotron, Standard Operation, Cyclotron in tank work
|
All cyclotron in tank work has been completed. |
Tuesday, January 09, 2018, 15:54, Jason Kapalka, Cyclotron, Standard Operation, Lid-up sequence (in-tank work)
|
2018-01-09
07:00-10:00 - Pre-job meeting, informed main control room of operation startup, lowered inflector (Operations
Group)
|
Monday, January 08, 2018, 09:04, Maico Dalla Valle / Jason Kapalka, Cyclotron, Standard Operation, Cyclotron Lid Up
|
Remote Handing is ready for January, 8 2018 Cyclotron lid up. Elevating system service has been completed.
A Cyclotron Lid raise was attempted on Monday, January 8 at 12:00, however this attempt was aborted after lifting the lid several millimeters due the motor
|
Tuesday, March 14, 2017, 17:57, Jason Kapalka, Cyclotron, Standard Operation, Lid raising and lowering operations
|
Lid up (Attempt #1)
Pre-indexed
|
Tuesday, March 14, 2017, 17:28, Jason Kapalka, Cyclotron, Maintenance, Lower resonator removal simulation exercice
|
A simulated removal of a lower resonator from the Cyclotron tank was attempted by the RH group using the
service bridge, lower resonator trolley, lower resonator attachment, and the (soon to be) attached lower
resonator removal procedure on 2017-02-27. Prior to aligning the attachment over a lower resonator, a small
|
Tuesday, March 14, 2017, 17:07, Jason Kapalka, Probe, Maintenance, LE probe removal simulation exercise
|
A simulated removal of the LE2 Probe from the Cyclotron tank was performed by the RH and Probes group using the
service bridge, upper resonator trolley, LE probe attachment, and the (soon to be) attached LE Probe removal
procedure on 2017-02-23. |
Tuesday, March 14, 2017, 12:02, Jason Kapalka, Cyclotron, Standard Operation, Radiation survey
|
The unshielded radiation survey was performed in the Cyclotron tank by the RH group using the service bridge,
tool trolley, and radiation survey attachment on 2017-01-30 (see attached plot).
|
Tuesday, March 14, 2017, 11:23, Jason Kapalka, Cyclotron, Standard Operation, Start/end of shutdown photo and video survey
|
The start of shutdown photo and video survey was performed in the Cyclotron tank by the RH group using the
service bridge and video trolley on 2017-01-27 (see attached pictures).
|
Tuesday, March 07, 2017, 09:31, Jason Kapalka, Shielding, Standard Operation, Blockers/Shields/Covers/Ladders
|
The seven copper blockers were removed from the Cyclotron tank by the RH group using the service bridge, lift
trolley, and attached checklist on 2017-01-30.
|
Friday, March 03, 2017, 13:30, Jason Kapalka, Cyclotron, Standard Operation, CP continuity test
|
Performed continuity test at Cyclotron center post with RH and Operations group members using the service bridge,
tool trolley, and probe attachment on 2017-03-03.
|
|