  RH-Cyclotron, Page 10 of 10  Not logged in ELOG logo
ID Date Author Category Type Subject Text Attachments
  15   Tuesday, March 05, 2013, 14:11 Travis CaveCyclotronStandard OperationSetup and the Installation of the HE 1 probe.Setup of the HE 1 probe is difficult has
we have no mockup of it to properly setup
cameras and equipment for it. This is problem
  
  14   Wednesday, February 27, 2013, 12:08 Travis CaveCyclotronStandard OperationInstallation of 2C2C has been installed located on all QDLs
and all the numbers, continuity check done
and passed. Bridge has been removed from
  
  13   Wednesday, February 13, 2013, 08:55 maicodallavalleService BridgeRepairService Bridge/Carrier Hydraulic JacksOn Monday February 4TH  the Service
Bridge was being lifted into  the Cyclotron
with the Carrier. It was noticed that one
 Hydraulic_Jack_RC-254.pdf 
  12   Wednesday, February 06, 2013, 18:07 Grant MinorElevation JackMaintenanceLid-down yoke gap measurements from 1994Attached is a scan of a handwritten record
from 1994 showing yoke-to-upper-structure
gap measurements from 1994, both L and R
 Elevation_Yoke_Measurements_1994.pdf 
  11   Wednesday, February 06, 2013, 17:50 Grant MinorElevation JackMaintenanceService records compiled by G. MinorAttached is a compiled record showing the
years of service of the jacks, upper bearing,
and gear reducers, prepared by Grant Minor
 Cyclotron_Elevation_Maintenance_Rotation_Record_17Dec2012.pdf 
  10   Wednesday, February 06, 2013, 17:42 Grant MinorElevation JackMaintenanceIn-situ jack power screw lubrication inspection - Stations 9, 10, 11, and 6Due to concerns raised regarding the state
of the lubrication of the power screws at
Station 9, the lubrication was visually inspected
 16x 
  9   Monday, February 04, 2013, 13:52 Grant MinorService BridgeRepairHydraulic cylinder failure on service bridgeThe hydraulic cylinder on the West side
of the service bridge (used to raise the
bridge for insertion into the Cyclotron)
 6x 
  8   Wednesday, January 30, 2013, 14:44 Grant MinorElevation JackStandard OperationFurther lid-up notes from Dan LouieDan Louie's e-mail comments from 30 Jan
2013 are attached.
- Grant
 Dan_Louie_Lid-Up_e-mail_30Jan2013.pdf 
  7   Tuesday, January 29, 2013, 18:49 Grant MinorElevation JackStandard OperationLid-up complete - summary notesLid-up was first attempted yesterday (Jan
28th) by Dan Louie, Arthur Leung, and Maico
Dalla Valle.  They experienced problems
 Jacks_Station_6_and_4_Procedure_Jan_12_2012_122.jpg 
  6   Thursday, October 25, 2012, 13:58 maicodallavalleService BridgeMaintenanceOrbit DriveIt was observed during the last time the
Cyclotron service bridge was used the orbit
drive chain had a lot of slack. The drive
  
  5   Tuesday, September 25, 2012, 08:57 maicodallavalleElevation JackMaintenance2012 Service Maintance of #4 Station Jacking System Shut down work for 2012.Replaced serviced
Jacking Station #6. Tapered alignment pins
were damaged. They were skimmed and checked
  
  4   Friday, February 17, 2012, 15:07 Don JacksonTrolleyRepairVideo Trolley Failed in Cyclotron TankAll control to the video trolley was lost
during remote photographing of components
in the cyclotron. The control system and
 Stuck_Video_Trolley_Feb_17_2012_005.jpgStuck_Video_Trolley_Feb_17_2012_001.jpg 
  3   Tuesday, February 14, 2012, 15:40 Grant MinorTrolleyStandard Operation2C Removal - all 4 QDLs were actuated remotely this year!Today Remote Handling staff (Maico Dalla
Valle, Travis Cave) used the Remote Handling
2C probe removal trolley to remove the probe
 2C_probe_Feb_14_2012_labelled.JPG2C_probe_solenoid_5_Feb_14_2012_labelled.JPG 
  2   Tuesday, February 07, 2012, 18:09 Grant MinorService BridgeRepairService Bridge Center Post Bearing Maintenance and Orbit Counter (2011/2012)Repair
of Orbit Limit Switch Plastic Belt
During
 Stripped_Orbit_Limit_Belt_Sept_23_2011.JPGBridge_Belt_Repair_Fall_2011.JPGOrbit_Counter_Wheel_Just_Before_Skip_Point.JPGD7900_detail_Feb_7_2012.JPGCyclotron_Orbit_Counter_Wheel_emails_Mar-Sep_2011.pdf 
  1   Monday, June 27, 2011, 10:38 John WongGeneralRoutineTesting RH elog    