Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Lab Maintenance, Page 2 of 4  Not logged in ELOG logo
ID Date Author Statusdown Test Subject Text Attachments
  53   Friday, January 19, 2024, 10:20 Darwin Ortiz RosalesFixed Glovebox regeneration (B1 L06, Hotlab)Friday, January 19, 2024, 10:19 
This is a belated entry.  The
regeneration was performed successfully on
  
  55   Tuesday, March 12, 2024, 15:21 Darwin Ortiz RosalesFixed Glovebox regeneration and O2 sensor replacement(B1 L06, Hotlab)Tuesday, March 12, 2024, 15:21
Hotlab ISAC1 B1 


Normal
0
  
  57   Monday, April 15, 2024, 10:52 Aaron SchmidtFixed Ar Glove box RP swapped. Monday, April 15, 2024, 10:50: The
old IDP15 RP was not pumping the antechamber
down properly. An exchange IDP15 pump is
  
  58   Thursday, June 20, 2024, 13:33 Darwin Ortiz RosalesFixed Glovebox inspection ISAC1 B1 L06 Thursday, June 20, 2024, 13:28
All lines, pump, blower, were
  
  62   Tuesday, October 15, 2024, 09:21 Darwin Ortiz RosalesFixed Hotlab glovebox catalyst regenerationTuesday, October 15, 2024, 09:22 
The glovebox catalyst was regenerated. 
No issues.  Removed TCE and PVB from
  
  64   Monday, December 16, 2024, 12:15 Aaron SchmidtCompleted Q4 - 2024 Ball Mill Calibration & Inspection  Fritsch Pulverisette
5 Ball Mill status:
 Q4_-_2024_Ball_Mill_Calibration&_Inspection.png 
  1   Wednesday, March 30, 2011, 16:47 John Wong  All Fumehood pumps in hot and cold labs tripped off due to MCC-X powered downAll the fumehood pumps in the ISAC-I hot
and cold labs got tripped off when the MCC-X
was powered down (See ISAC WP#2011-03-30-5).
  
  2   Tuesday, April 12, 2011, 12:03 John Wong  Hot Lab Glove Box Regeneration Tue Apr 12 12:00:52 2011:  The hot
lab glove box regeneration was started yesterday
(April 11, 2011).  "Before regeneration,
  
  3   Tuesday, April 12, 2011, 12:07 John Wong  All Fumehood pumps in hot and cold labs tripped off due to MCC-X powered down

    

       
            
  
  4   Wednesday, April 13, 2011, 13:54 John Wong  Cloth booties now avaiable for hotlabWed Apr 13 13:53:46 2011

I've setup a box of cloth booties
for entering the hotlab.  They are
washable
  
  12   Tuesday, February 28, 2012, 12:01 John Wong  TIS/RH UsersTuesday, February 28, 2012, 11:31
Hi All,
Hope you all find the TIS/RH elog
  
  13   Friday, March 15, 2013, 13:55 Anders Mjos  Non active water off for a short time (10 - 15 min)ISAC operations called to check that equipment
in the labs were OK for the non active water
to be off for a short time. I gave the OK
  
  14   Wednesday, November 26, 2014, 14:01 Laura Lambert       
  18   Tuesday, August 08, 2017, 14:55 Laura Lambert  Glove box Alarm Tuesday, August 08, 2017, 14:28
Alarm for glove box went off this
afternoon.
  
  19   Wednesday, December 20, 2017, 09:16 Laura Lambert  RETURN and SUPPLY valves CLOSED for xmas break for both evap1 and evap2 Wednesday, December 20, 2017, 09:02
Replaced Argon tank
  
  20   Tuesday, January 23, 2018, 11:58 Laura Lambert  All BeO removed from Labs! Tuesday, January 23, 2018, 11:55
Portable glove box with everything
inside, contaminated beakers, pellets and
  
  21   Wednesday, January 31, 2018, 13:35 Laura Lambert  New lab safety mirrors installed in hot lab Wednesday, January 31, 2018, 13:31
3 x lab safety mirrors have been
installed in the hot lab, now all locations
 IMG_0237.JPGIMG_0239.JPG 
  23   Thursday, February 07, 2019, 10:42 Aaron Schmidt  Argon Glove box leak / regeneration failure 
A regeneration of the Ar Glove box
had been performed Monday, 04, Feb, 2019.
 7x 
  24   Thursday, March 21, 2019, 07:43 Aaron Schmidt  Argon Glove box repair & link to nuclear ventilationThe Ar glove box issues ( https://elog.triumf.ca/TIS/General/23
) have been fixed.
Quoted from work permit: 
 6x 
  26   Friday, July 26, 2019, 13:06 Aaron Schmidt  Q2 - 2019 Ball Mill Calibration & Inspection Fritsch Pulverisette
5 Ball Mill status:
SN 05.6010 / 03005: Inspected July
 Q2_-_2019_Ball_Mill_Calibration_&_Inspection.pdf 