ID |
Date |
Author |
Target Material |
Target Oven W.O# |
Source |
Status |
Subject |
Text |
 |
|
486
|
Monday, June 01, 2020, 12:03 |
Aaron Schmidt | Ta | 44139-13 | LP-SIS | In progress | Ta#60 Conditioning | Ta#60 LP-SIS target
description: |
|
|
489
|
Monday, July 13, 2020, 11:03 |
Aaron Schmidt | | | | | Pump down / leak / vacuum check. | Darwin reported that he was unable
to achieve vacuum of 150mTorr. The flex-line
HS had been removed last week for modifications. |
|
|
494
|
Wednesday, August 05, 2020, 13:38 |
Aaron Schmidt | | | | | RP Swap on EVAP 2 | BP1 swapped with RP2 (TS beamline)
U-line installed.
Wednesday, August 05, 2020, 13:37: |
|
|
497
|
Wednesday, August 12, 2020, 08:58 |
Aaron Schmidt | | | | In progress | Install Flex line HS | Flex line HS installed. New SS gaskets.
Wednesday, August 12, 2020, 08:56:
Roughing (Check). |
|
|
506
|
Thursday, September 10, 2020, 07:53 |
Aaron Schmidt | Empty | 41790-8 | LP-FEBIAD | Done | Fernando FEBIAD / Anode testing. | FEBIAD installed. Anode PS installed.
ANODE connected!.
Leak check |
|
|
509
|
Thursday, September 24, 2020, 13:37 |
Aaron Schmidt | Nb | | TARGET BOAT | | Nb Test SRF group | Sample loaded into a vertical target boat.
Flex line HS removed, SS waterline HS installed
-AS. |
|
|
513
|
Tuesday, October 06, 2020, 14:23 |
Aaron Schmidt | Ta | 44508-1 | LP-SIS | In progress | Conditioning Ta#61 | Ta#61 LP-SIS target description:
Total Ta foils = 470 [6x20 packs |
|
|
514
|
Wednesday, October 07, 2020, 12:25 |
Aaron Schmidt | | | | In progress | IEVAP2:TP1 Swap out. | Wednesday, October 07, 2020
TP1 was not spinning up past 4krpm.
Stalling & tripping out. Examined with |
|
|
519
|
Wednesday, October 21, 2020, 14:39 |
Aaron Schmidt | Nb | 44508-2 | LP-SIS | In progress | Conditioning Nb#9 | Nb#9 LP-SIS target description:
|
|
|
524
|
Tuesday, November 24, 2020, 08:13 |
Aaron Schmidt | | | | | Flex - line HS installed | Monday, November 23, 2020, 17:01: Flex-line
HS installed.
Tuesday, November 24, 2020, |
|
|
527
|
Tuesday, February 09, 2021, 06:48 |
Aaron Schmidt | | NA | | Done | Ta coating test | Monday, February 08, 2021, 17:00: Installed
brackets w/ Ta wire and a small piece of
Re to test voltage drop. |
|
|
532
|
Monday, March 01, 2021, 13:58 |
Aaron Schmidt | | | | | Flex - line HS installed | Flex-Line HS had been fully scrubbed out
earlier. All gaskets replaced.
Empty. Quick check for leaks. |
|
|
537
|
Tuesday, March 23, 2021, 08:07 |
Aaron Schmidt | | | | | Re - Ta test. Leak check. | Modified HS installed with new brackets
as per Marla.
Tuesday, March 23, 2021, 08:02: Vacuum |
|
|
539
|
Thursday, March 25, 2021, 07:57 |
Aaron Schmidt | | | | | Re - Ta test. Leak check. | Thursday, March 25, 2021, 07:55: Vacuum
@ 5.12e-07T. Waterlines opened. |
|
|
546
|
Thursday, April 08, 2021, 08:25 |
Aaron Schmidt | Ta | 44139-10 | LP-SIS | In progress | Conditioning Ta#62 & Flex - line HS installed | Ta#62 LP-SIS target
description: |
|
|
551
|
Wednesday, June 23, 2021, 17:48 |
Aaron Schmidt | Ta | 44691-4 | LP-SIS | In progress | Conditioning Ta#62 (Replacement) | Ta#62 LP-SIS target
description: (REPLACEMENT FOR 44139-10) |
|
|
557
|
Wednesday, October 13, 2021, 08:35 |
Aaron Schmidt | | | | Problems | Troubleshoot - Pump down issues. | Swapped out the Cu gaskets for SS gaskets
in the HS top lines. (x2)
Wednesday, October 13, 2021, 08:35: |
|
|
564
|
Wednesday, November 10, 2021, 18:07 |
Aaron Schmidt | Ta | 44691-11 | LP-SIS | In progress | Conditioning Ta#63 | Ta#63 LP-SIS target description:
|
|
|
565
|
Thursday, November 25, 2021, 14:00 |
Aaron Schmidt | | | | | Lower insulator replaced | The Helicoil had mostly pulled out
of the old one.
|
|
|
571
|
Tuesday, April 12, 2022, 13:41 |
Aaron Schmidt | | | | Maintenance | New Flex - line HS installed | Old HS sprang a leak in the copper tubing.
HS#44378-15
Tuesday, April 12, 2022, 13:35: Roughing. |
|