532
|
Monday, March 01, 2021, 13:58 |
Aaron Schmidt | | | | | Flex - line HS installed | Flex-Line HS had been fully scrubbed out earlier. All gaskets replaced.
Empty. Quick check for leaks.
Monday, March 01, 2021, 13:57: Roughing.
Monday, March 01, 2021, 14:13: TP1 on.
Monday, March 01, 2021, 15:18: Vacuum @ 1.01e-05T. Open HS waterline.
Monday, March 01, 2021, 15:24: Vacuum @ 9.30e-06T & dropping. Waterline ok.
Monday, March 01, 2021, 15:25: Turbo pump off. Vent when ready. |
|
537
|
Tuesday, March 23, 2021, 08:07 |
Aaron Schmidt | | | | | Re - Ta test. Leak check. | Modified HS installed with new brackets as per Marla.
Tuesday, March 23, 2021, 08:02: Vacuum @ 3.64e-07T. Waterlines opened.
Tuesday, March 23, 2021, 08:06: Vacuum @ 3.60e-07T. Stable.
|
|
538
|
Tuesday, March 23, 2021, 11:28 |
Marla Cervantes | Empty | 44489-6 | | Done | Re-coating test 3 | Objective: Coating the inner surface of a short tantalum boat with rhenium.
Result:
- The wire snnaped around 376 W (53 A, and 7.09 V) and 2170 °C (measured with filament pyrometer)
- The tube does not have indications of coating
Thursday, March 25, 2021, 11:23
Yesterday a heat shield was installed in the EVAP2.
The desired temperature of the Re wire is 2500 degC
A water leak was performed (elog 539 describes it), no leak was detected.
Tuesday, March 23, 2021, 11:01
Pressure 3.8e-7 Torr, current rate set to 6 A @ 0.5 A/min
The wire started glowing at TGHT = 4W, 7A, 0.56V
When reaching 7A the current was increased 0.5 A manually
When reaching 16 A, the current was increased 1 A manually until reaching 54 A when the wire snapped |
|
539
|
Thursday, March 25, 2021, 07:57 |
Aaron Schmidt | | | | | Re - Ta test. Leak check. | Thursday, March 25, 2021, 07:55: Vacuum @ 5.12e-07T. Waterlines opened.
Thursday, March 25, 2021, 07:55: Vacuum @ 5.09e-07T. Stable.
|
|
540
|
Thursday, March 25, 2021, 11:24 |
Marla Cervantes | Empty | NA (Cu-Tube | | Done | Re-coat test 4 | Objective: Coating the inner surface of a short tantalum tube with rhenium.
Result:
- The wire snnaped around 376 W (53 A, and 7.09 V) and 2170 °C (measured with filament pyrometer)
- The tube is coated
Thursday, March 25, 2021, 11:23
Yesterday a heat shield was installed in the EVAP2.
The desired temperature of the Re wire is 2500 degC
A water leak was performed (elog 539 describes it), no leak was detected.
Tuesday, March 23, 2021, 11:01
Pressure 3.8e-7 Torr, current rate set to 6 A @ 0.5 A/min
The wire started glowing at TGHT = 4W, 7A, 0.56V
When reaching 7A the current was increased 0.5 A manually
When reaching 16 A, the current was increased 1 A manually until reaching 54 A when the wire snapped |
|
541
|
Friday, March 26, 2021, 13:58 |
Marla Cervantes | Empty | 44489-6 | | Done | Re-coat 1 | Friday, March 26, 2021, 13:55
Yesterday a heat shield was installed in the EVAP2.
A 1mm thick rhenium wire was held within two copper brackets to pass through a Cu tube with the intention of coating its inside face.
The desired temperature of the Re wire is 2500 degC
A water leak was performed and no leak was detected
|
|
542
|
Friday, March 26, 2021, 16:23 |
Marla Cervantes | Empty | 44489-7 | | Done | Re-coat 2 | Objective: Coating the inner surface of a tantalum tube to make a destructive test and use a reference for the tantalum boats coatings
Results:
Sunday, March 27, 2021, 11:23
No water leak
IGP1 = 3.7e-7 torr
Sunday, March 27, 2021, 16:10
The wire was heated in the same manner as the last three runs
From 0A to 7A the autoramp was set to 0.5A/min
At 8A the wire started the glow dimmly
Above 8A, the wire was heated manually at 0.5A until 16A where the step was changed to 1A,
the temperature was measured with the filament pyrometer every 2 A starting at 10A
At 42 A the step was changed to 0.6A until 42.6A, 4.38V (2020 °C), the wire was kept at that temperature for 90 min
After that time, the current was ramped down at 0.5A/min until ~20A when the current rampping was changed too 1A/min
|
|
543
|
Sunday, March 28, 2021, 11:24 |
Marla Cervantes | | NA (Ta-tube) | | Done | Re-coat 3 | Objective: Coating the inner surface of a tantalum tube to make a destructive test and use a reference for the tantalum boats coatings
Results: The tube was coated
Sunday, March 28, 2021, 11:23
No water leak
IGP1 = 2.3e-7 torr
Sunday, March 28, 2021, 16:10
The wire was heated in the same manner as the last three runs
From 0A to 7A the autoramp was set to 0.5A/min
At 8A the wire started the glow dimmly
Above 8A, the wire was heated manually at 0.5A until 16A where the step was changed to 1A,
the temperature was measured with the filament pyrometer every 2 A starting at 10A
At 42 A the step was changed to 0.6A until 42.6A, 4.38V (2020 °C), the wire was kept at that temperature for 90 min
After that time, the current was ramped down at 0.5A/min until ~20A when the current rampping was changed too 1A/min
|
|
544
|
Tuesday, March 30, 2021, 19:49 |
Ferran Boix Pamies | Empty | 44139-7-SK | | Done | Parasitic target thermal tests | 2021-03-30 7:48 Target loaded with parasitic target only. No container. Leaving under vacuum over night.
2021-03-31 13:43 Leak check performed. Water on. Need to vent system, electric connection disconnected.
2021-03-31 15:02 First test successfully finished. Venting to introduce container with radiating heating gun.
2021-04-01 14:58 Vacuum 3.5E-7 torr. Leak check done. Ramping up target heater to 100A at 1A/10s
2021-04-01 14:58 Vacuum 5E-7, 100A all ok. Temp foil 24.3DegC. ramping to 500A at 1A/10s.
2021-04-01 14:58 Temp of foil not increasing much. Probably issue with TC. ramping down at 1A/10s to vent and inspect.
2021-04-02 11:03 Target reinstalled, foil TC reinstalled. Vacuum 3E-7 torr. Leak check done. Ramping up container to 500A 1A/10s.
2021-04-02 13:07 Still isues with TC. Container ramped down at 1A/10s. Venting, brought heat gun to check TC.
2021-04-02 15:10 TC connection fixed, origin of issues. Vacuum down to 3E-5 torr. Ramping up container to 200A 1A/10s.
2021-04-02 18:32 TGTH 200A Tc temp 327.5degC. ramping up to 300A. 1A/10s.
2021-04-02 18:32 TGTH 300A Tc temp 500degC. ramping up to 400A. 1A/10s.
2021-04-02 19:17 TGTH 400A Tc temp 618degC. ramping down.
2021-04-03 13:37 Foil was changed, ramped up to 200A at 1A/10s, Temp TC 360degC. Ramping to 300A. Vac 8.6E-6 torr.
2021-04-03 13:59 300A Temp TC 580degC. Ramping to 500A, 1A/10s. Vac 7.6E-6 torr.
2021-04-03 14:36 500A Temp TC 836degC. Ramping to 600A, 1A/10s. Vac 9E-6 torr.
2021-04-03 14:36 600A Temp TC 960degC. Vac 1.1E-5 torr. Ramping down.
2021-04-03 19:00 After venting an opening the evap2, it was found that remaining from a past heat treatment where on the Tantalum container. The sublimation of the material coated the inner walls of the evap.2. Now cleaned.
|
Attachment 1: 20210403_174815.jpg
|
|
Attachment 2: 20210403_183102.jpg
|
|
|
547
|
Tuesday, April 13, 2021, 10:44 |
Marla Cervantes | Empty | NA (Ta- tube Eagle Alloys) | | Done | Re-coat 4 | Tuesday, April 13, 2021, 09:51
IGP1 = 2.5e-7 Torr
Tuesday, April 13, 2021, 10:17
The wire was heated in the same manner as the last three runs
From 0A to 7A the autoramp was set to 0.5A/min
At 8A the wire started the glow dimmly
Above 8A, the wire was heated manually at 0.5A until 15A where the step was changed to 1A,
the temperature was measured with the filament pyrometer every 2 A starting at 10A
At 42 A the step was changed to 0.5A until 44.5A, 4.61V (2120 °C), the wire was kept at that temperature for 6 hours.
After that time, the current was ramped to 0A at 0.5A/min. |
Attachment 1: voltage-increment-Re-coating.JPG
|
|
|
557
|
Wednesday, October 13, 2021, 08:35 |
Aaron Schmidt | | | | Problems | Troubleshoot - Pump down issues. | Swapped out the Cu gaskets for SS gaskets in the HS top lines. (x2)
Wednesday, October 13, 2021, 08:35: Roughing.
Wednesday, October 13, 2021, 08:50: Turbo pump on. TP Current 6.06-6.10A.
Wednesday, October 13, 2021, 08:59: TP maxed out at 3-4 KRPM, yet went "Green/On".
Wednesday, October 13, 2021, 09:00: Change FULL to Low setting. Restart. TP Current 6.15A.
Wednesday, October 13, 2021, 09:08: Timed out. Restarted from 5 KRPM.
Wednesday, October 13, 2021, 09:14: Stalling @ 5 KRPM. Stop TP. Contact vacuum group.
Monday, October 18, 2021, 09:03: Roughing. Reboot TP controller.
Monday, October 18, 2021, 09:25: Walkthrough soft start w/ vacuum group. TP timed out. Soft start failed.
Monday, October 18, 2021, 09:31: EVAP 2 vented. TP to be disconnected & removed.
Monday, October 18, 2021, 09:55: TP removed. Quick check, barely spins when spin by hand gently. Replacement or refurbishment needed.
500 lpm turbo pumps installed. TV551 Varian. SN: 202311 (Slightly active from BL1A - will not cross contaminate. Field only - Tagged)
Wednesday, October 20, 2021, 11:35: Roughing.
Wednesday, October 20, 2021, 11:52: TP on.
Wednesday, October 20, 2021, 11:59: TP at speed.
Wednesday, October 20, 2021, 12:02: Vacuum @ 6.13e-05T. Open HS waterline.
Wednesday, October 20, 2021, 12:03: Vacuum @ 5.63e-05T & dropping.
Wednesday, October 20, 2021, 12:04: Vacuum @ 5.32e-05T. TGHT PS on. |
|
565
|
Thursday, November 25, 2021, 14:00 |
Aaron Schmidt | | | | | Lower insulator replaced | The Helicoil had mostly pulled out of the old one.
Thursday, November 25, 2021, 13:58: Insulator replaced. EVAP 2 is ready for use with ISAC targets. |
|
571
|
Tuesday, April 12, 2022, 13:41 |
Aaron Schmidt | | | | Maintenance | New Flex - line HS installed | Old HS sprang a leak in the copper tubing.
HS#44378-15
Tuesday, April 12, 2022, 13:35: Roughing.
Tuesday, April 12, 2022, 13:49: TP1 switched on.
Tuesday, April 12, 2022, 13:57: TP1 stable (green).
Tuesday, April 12, 2022, 14:10: Vacuum @ 3.71e-05T & dropping.
Tuesday, April 12, 2022, 14:11: HS waterline opened.
Tuesday, April 12, 2022, 14:12: Vacuum @ 3.32e-05T.
Tuesday, April 12, 2022, 14:22: Vacuum @ 2.19e-05T (Stable).
|
|
575
|
Tuesday, May 10, 2022, 14:43 |
Aaron Schmidt | | | | Maintenance | Active TP removed / Swap / Slow start TP | Tuesday, May 10, 2022, 14:42: TV551 Varian. SN: 202311 (Slightly active from BL1A - will not cross contaminate. Field only - Tagged) was removed as it was meant to be a temporary fix. Replacement (Refurbished) pump is to be installed. (Tomorrow - Use slow start function as per vacuum group)
Thursday, May 12, 2022, 13:30: Agilent TP & hardware installed.
SN: IT21381010
Thursday, May 12, 2022, 13:41: Roughing.
Thursday, May 12, 2022, 13:46: Halt.
Friday, May 13, 2022, 07:05: Roughing.
Friday, May 13, 2022, 07:18: TP1 on.
Friday, May 13, 2022, 07:23: Up to 14 KRPM. Pause/Halted startup (Whining?). Slow start w/ vacuum group.
Process to perform a TP slow start:
- Hold both top buttons on the controller for about 3 seconds
- Right Yes/No left to continue.
- Advance to soft start - 20 min.
- Back to remote start & go.
Friday, May 13, 2022, 08:26: TP1 on w/ slow start.
Friday, May 13, 2022, 08:39: 13 KRPM & climbing.
Friday, May 13, 2022, 09:10: TP at full speed. 38 KRPM. 0.5A 9w. This pump whines, but is operating fine. Likely will switch again when another is available. (It appears to have been dropped, Noted by Edi. Likely when shipped)
Friday, May 13, 2022, 09:14: TP off. Slow start function off. Back to normal function. |
|
579
|
Wednesday, June 08, 2022, 10:00 |
Flora Wu | | boat | | Done | carbonize PAN 10% discs | Thursday, June 09, 2022, 11:25
Total number of foils: 14 electrospun fiber pellets
Total weight = 208.3 g
container has 3 Ta heat shields.
Desired temperature at 1800 C
Omega slope set at 0.990
Good vac = 3.0e-5 Torr,
Bad vac = 5.0e-5 Torr.
Pumping down in progress
Thursday, June 09, 2022, 11:25
chamber pumped down below 5e-5
initiate auto ramping, 1A/min ----> 100 A
(see eLog 581)
|
|
581
|
Thursday, June 09, 2022, 19:20 |
John Wong | | boat | | Done | carbonize PAN 10% discs |
Flora Wu wrote: |
Thursday, June 09, 2022, 11:25
Total number of foils: 14 electrospun fiber pellets
Total weight = 208.3 g
container has 3 Ta heat shields.
Desired temperature at 1800 C
Omega slope set at 0.990
Good vac = 3.0e-5 Torr,
Bad vac = 5.0e-5 Torr.
Pumping down in progress
Thursday, June 09, 2022, 11:25
chamber pumped down below 5e-5
initiate auto ramping, 1A/min ----> 100 A
|
Thursday, June 09, 2022, 19:16
Pressure came down below 10e-5 Torr as TGHT ramped up to 100A.
Continue auto ramping to reach 250A at 1A/min.
Thursday, June 09, 2022, 22:52
TGHT is hovering around 127A/1.68 V due to erractic pressure, see attachment #1.. Notice the backing line is at atm pressure - I don't recall this happened in the past.
Temp is still low to be detected on Omega. Will leave this overnight.
Friday, June 10, 2022, 09:07
TGHT has been holding at 250A/3.76V since 2:45am. Pressure comes down as THGT above 200 A. Backing line is back down normal.
Temp reading at 1040 C.
see attachment #2.
Continue to ramp up to 300A, monitoring temp/pressure.
Friday, June 10, 2022, 10:31
TGHT reached to 300A/4.63V, temp at 1145C. Pressure at 1.8e-6 and coming down.
Continue to ramp up to 350A.
Friday, June 10, 2022, 11:59
TGHT at 350A/5.66V, temp at 1300 C, Pressure at 8.1e-7 Torr, and coming down.
Continue to ramp up to 400A.
Friday, June 10, 2022, 13:19
TGHT reached to 400A/6.73V. Pressure coming down from 1.04e-6 Torr.
Temp at 1690. Will set up manually to reach 1800 C.
Friday, June 10, 2022, 13:50
TGHT stepped up to 432A/7.42V. Pressure coming down from 1.3 e-6 Torr.
Temp at 1800 C. See attachment#3 and #4 for the screenshot and temp-current plot.
Dumped striptool data to /usr1/evpr/carbonize_pan10_elog581_a and b.
Will keep at this setting over the weekend, and cooling down will take place on Sunday evening.
Sunday, June 12, 2022, 22:30
TGHT has been holding at 432A/7.40V since Friday. Temperature has gone up slightly to 1825.
See attachment#5 for the overall process.
Initiated cooling down at -2A/min.
Chamber will be vented on Monday morning.
|
Attachment 1: evap2-screenshot_01.PNG
|
|
Attachment 2: evap2-screenshot_02.png
|
|
Attachment 3: evap2-screenshot_3.png
|
|
Attachment 4: temp-current-plot.xlsx
|
Attachment 5: evap2-screenshot_04.PNG
|
|
|
583
|
Monday, June 20, 2022, 14:52 |
Darwin Ortiz Rosales | Empty | | | Done | softstart of new TP | Monday, June 20, 2022, 14:50
A new Turbo pump was installed this morning and it was soft started. It has operated correctly and it is ready for use. Derek O. installed it.
Previous pump had issues at start-up and was diagnosed as finished by Edi/
|
|
635
|
Monday, June 05, 2023, 14:52 |
Aaron Schmidt | | | | | Swapped turbo pumps. | Previous TP would only spin up to 4KRPM. New TP installed.
Monday, June 05, 2023, 14:50: Roughing.
Monday, June 05, 2023, 15:10: Controller reset. TP on. |
|
668
|
Wednesday, August 07, 2024, 15:37 |
Aaron Schmidt | | | | | Turning on EVAP2's turbo pump | Wednesday, August 07, 2024, 15:36: Roughing. Had initially been roughed & TP started w/ Marla CS, however it timed out. Restarting.
Wednesday, August 07, 2024, 15:37: TP on.
Wednesday, August 07, 2024, 15:46: Tripped at 4 KRPM. Restarted. Up to 5 KRPM.
Failed to start.
Thursday, August 08, 2024, 10:00: TP started.
Thursday, August 08, 2024, 10:12: TP Tripped but nearly spun up. Reset & Restarted. TP Green / on. |
|