159
|
Thursday, October 02, 2014, 11:26 |
John Wong | Empty | | | Maintenance | Broken insulators | Thursday, October 02, 2014, 11:22
It was found that after the last process, Evap#2 has broken insulators - the cylinder insulator that supports the target centre legs and the block insulator that supports the terminals.
Informed Anders/Rick.
|
161
|
Friday, October 03, 2014, 13:02 |
Anders Mjos | Empty | | | Maintenance | Broken insulators |
John Wong wrote: |
Thursday, October 02, 2014, 11:22
It was found that after the last process, Evap#2 has broken insulators - the cylinder insulator that supports the target centre legs and the block insulator that supports the terminals.
Informed Anders/Rick.
|
Friday, October 03, 2014
- Insulators replaced. Torque 55 in lbs on all fasteners.
- Cleaned TGHT terminals with scotch-brite and methanol.
- New (clean) heat shield prepared WO-39230-2.
- Re-installed right side heat shield alignment pin (previously removed to allow line of sight to the target).
|
Attachment 1: NewInsulators.jpg
|
|
Attachment 2: BrokenInsulators.jpg
|
|
172
|
Wednesday, November 26, 2014, 14:09 |
Laura Lambert | | | | Maintenance | OMEGA-IR dark patch and backing pump trip | Wednesday, November 26, 2014, 13:47
OMEGA-IR laser had a dark patch on it [see picture]
Cleaned window, still dark patch
When tested by itself, through air, not through window, patch still visible - cleaned lens of OMEGA-IR, still no change.
Conclusion: assuming laser used to be able to focus the OMEGA-IR to a specific area - so visual only, but the measurements itself will not be affected.
Wednesday, November 26, 2014, 13:53
Backing pump trips off every time roughing valve turned on through epics.
Requested further investigation...
Friday, November 28, 2014, 12:09
Backing Pump has been replaced, waiting on a reply from OMEGA re: dark patch on laser
Pancake monitor was also acting funny. Background was reading 100cpm and jumping up to as high as 400cpm by simply moving the probe piece.
The wire connecting the probe to the monitor was replaced and works fine now.
Tuesday, December 09, 2014, 15:55
Finally got a reply from the OMEGA people:
"That [ dark patch] would happen because of sharp bends in the fiber, or simply defective fiber cable.
As manufacturer we allow 2% of broken fibers, out of 870 in the bundle.
As far as measurements is concerned, if IR2 is used in dual colour mode,
the field of view can be obstructed as much as 50%,
without changing the readings accuracy. This laser issure should not affect readings."
-Quote from Brian Newport from OMEGA
|
Attachment 1: IR_focus.jpeg
|
|
173
|
Thursday, December 11, 2014, 10:20 |
Laura Lambert | | | | Maintenance | water supply shut off for lab closure over holidays | Thursday, December 11, 2014, 10:17
water supply and return valves closed for lab closure over the holidays.
all taps leading into evap2 have been closed.
evap2 was fully flushed leaving no water left inside the system.
|
174
|
Wednesday, January 14, 2015, 13:46 |
Anders Mjos | Empty | | | Maintenance | Pumping down for water leak test | Wednesday, January 14, 2015, 13:46: Roughing
Wednesday, January 14, 2015, 14:57: Starting turbo
Monday, January 19, 2015, 13
Water opened up to one circuit at at time. No response on the vacuum could be seen.
IGP1 at 1.7E-7 T
IGP2 at 3E-8 T
Tuesday, January 20, 2015, 13:11: Stopped turbo and roughing pump.
Wednesday, January 21, 2015, 15:46: Venting
Rick and Anders found CG1A to be reading too high a value. A borrowed gauge from the vacuum group confirmed this. A new gauge will be installed
Thursday, January 22, 2015, 14:06: Roughing
Thursday, January 22, 2015, 14:18: Venting
The reading is consistent between CG1A and CG1B, which simplifies pump down. |
175
|
Thursday, January 22, 2015, 14:21 |
Anders Mjos | Empty | | | Problems resolved | CG1A replaced | See previous e-log entry for details |
218
|
Thursday, June 18, 2015, 11:39 |
Rick Maharaj | | | | | Installation of Extraction Electrode Insulator - New Material | Tuesday June 16, 2015
An Extraction Insulator ITD0381 made from a different grade of AiN was installed in Evaporator 2 for testing purposes. The sub assembly included the SIS Restraint Housing ITD0389, New Extraction Insulator ITD0381, Repeller Electrode ITD0377, Extraction Electrode ITD0374 with fingerstock mounted.
The standoff insulator ITD0400 was found to be swelled up and broken. It was replaced with and glazed alumina insulator.
The tube heater Insulator ITD0342 - central support helicoil was repaired. |
231
|
Thursday, July 30, 2015, 17:07 |
John Wong | | | | Maintenance | Connect NALCW to EVAP1 | Thursday, July 30, 2015, 17:02
EVAP1 cooling system is now on the NALCW. The city water has been removed from the system.
Tested all the cooling system interlocks by shutting off each individual valve, and the main supply valve to the lab - All Passed!
|
232
|
Friday, July 31, 2015, 15:10 |
John Wong | | | | Maintenance | Installed leftside port | Friday, July 31, 2015, 15:09
The left side port was installed on the evaporator #2. Leak check was performed and no leak was detected.
|
240
|
Monday, August 24, 2015, 12:58 |
John Wong | | | | Maintenance | Replacing turbo pump, IEVAP2TP1 | Monday, August 24, 2015, 12:54
The turbo pump was found to be faulty. The pump couldn't get on full speed and eventually timed out. Vacuum group inspected the pump and it is time for a service.
A new pump has been installed. Leak check was performed and no leaks were detected.
Pump is now fully operational.
Back in business….
|
249
|
Thursday, September 24, 2015, 09:48 |
Laura Lambert | Empty | 41077-5 | | In progress | Sintering TaC coating container for UCx Target | Thursday, September 24, 2015, 08:39
IGP1 = 6.5e-7Torr
HS water valves opened, no leaks detected.
Tapped up manually to 35A.
Waited ~20min.
Vacuum stable, IGP1 = 1.5e-6 Torr.
Initiated auto-ramp at 0.2A/min and 0.1A/min for the TGHT and TBHT respectively with final setpoints of 250A and 230A.
Final temp of 1200C on auto-ramp in order to initiate temperature measurements starting at ~1200C.
Thursday, September 24, 2015, 10:24
IGP1 = 8.7e-7 Torr
TGHT = 44A, TBHT = 38A
Increasing auto-ramp to 0.5A/min and 0.2A/min for the TGHT and TBHT respectively.
Thursday, September 24, 2015, 12:03
Vacuum spiking rapidly.
Stopped auto-ramp, tapped TGHT and TBHT down manually, allowing vacuum to stabilize.
IGP1 = 3.5e-6 Torr.
Re-initiating auto-ramp at 0.2A/min and 0.1A/min for the TGHT and TBHT respectively.
|
271
|
Thursday, January 14, 2016, 11:48 |
Laura Lambert | | | | Maintenance | Backing Pump Replaced | Thursday, January 14, 2016, 11:47
Backing pump was making very loud high pitched noises during last couple processes in the evaporator.
Replaced with a new one this morning.
|
292
|
Tuesday, May 03, 2016, 14:44 |
Laura Lambert | | | | | VACUUM PUMP REPLACEMENT | Tuesday, May 03, 2016, 14:29
Turned vacuum pump on this morning, sounded awful: loud grinding bad noises.
Called vacuum group, will replace pump tomorrow morning.
Sounds like materials coming out from all the out-gassing during sintering processes has ruined the bearings.
|
313
|
Friday, August 12, 2016, 11:08 |
Laura Lambert | | | | Maintenance | NEW PUMP FOR GLOVE BOX | Wednesday, August 03, 2016, 16:16
Tues July 26th had some problems with the transfer chamber
Transfer chamber was not going below -20in pressure, when usually it will drop all the way to -30in
To by pass and put the uranium target into the glove box, the transfer chamber was flushed 10x - when opened, no change in H2O and O2 in glove box; therefore, 'bypass' worked.
Pump removed and tested by vacuum group - showed no reading on gauge when being tested, how was it even pumping?
New pump installed July 27th.
New pump = bigger/ faster/ quieter 
|
315
|
Thursday, August 18, 2016, 10:37 |
Anders Mjos | | | | Maintenance | New cooling lines for Heat Shield | Dan made a set of new cooling lines for the Source Tray Heat Shield cooling yesterday. No joints on the lines. Use same VCR fitting 3/8 -> 1/4" as for the Heat Shield. The old lines had worn threads on the male VCR nut. |
342
|
Tuesday, December 20, 2016, 15:04 |
Laura Lambert | | | | Maintenance | RETURN and SUPPLY valves CLOSED for xmas break | Tuesday, December 20, 2016, 15:05
confirmed ~full tank of Ar for glove box --> ~1600psi |
345
|
Monday, February 06, 2017, 11:17 |
Anders Mjos | | | | Problems resolved | IOC restart after power outagae | Dave Morris did a remote restart of the IOC after the outage. Turbo pump started. |
346
|
Thursday, February 09, 2017, 11:49 |
Laura Lambert | | | | Maintenance | New heatshield with flexible water lines | Thursday, February 09, 2017, 11:47
A new heatshield with flexible water lines has been put into evap2 last Friday Feb3rd
|
364
|
Monday, May 08, 2017, 10:05 |
Laura Lambert | | | | Maintenance | Turbo pump control box replaced | Monday, May 08, 2017, 10:05
Turbo pump control box died last week.
Replaced with a new one.
|
369
|
Thursday, May 11, 2017, 11:30 |
Laura Lambert | | | | Maintenance | New Ion Gauge for IGP2 | Thursday, May 11, 2017, 11:25
IGP2 has been having problems where sometimes it turns off and requires simply unplugging and plugging back in.
Ion gauge has been replaced.
At first the vacuum box appeared red on epics and when attempting to reset everything nothing would work and the backing pump would try and turn on then timeout.
Apparently this new ion gauge draws slightly more than the old one and this blew a fuse in the PLC.
Old fuse was 2A, so a new 3A fuse has been replaced - seems to be working fine now.
|
|