271
|
Thursday, January 14, 2016, 11:48 |
Laura Lambert | | | | Maintenance | Backing Pump Replaced | Thursday, January 14, 2016, 11:47
Backing pump was making very loud
high pitched noises during last couple processes |
|
292
|
Tuesday, May 03, 2016, 14:44 |
Laura Lambert | | | | | VACUUM PUMP REPLACEMENT | Tuesday, May 03, 2016, 14:29
Turned vacuum pump on this morning,
sounded awful: loud grinding bad noises. |
|
313
|
Friday, August 12, 2016, 11:08 |
Laura Lambert | | | | Maintenance | NEW PUMP FOR GLOVE BOX | Wednesday, August 03, 2016, 16:16
Tues July 26th had some problems
with the transfer chamber |
|
315
|
Thursday, August 18, 2016, 10:37 |
Anders Mjos | | | | Maintenance | New cooling lines for Heat Shield | Dan made a set of new cooling lines
for the Source Tray Heat Shield cooling yesterday.
No joints on the lines. Use same VCR fitting |
|
342
|
Tuesday, December 20, 2016, 15:04 |
Laura Lambert | | | | Maintenance | RETURN and SUPPLY valves CLOSED for xmas break | Tuesday, December 20, 2016, 15:05
confirmed ~full tank of Ar for glove
box --> ~1600psi |
|
345
|
Monday, February 06, 2017, 11:17 |
Anders Mjos | | | | Problems resolved | IOC restart after power outagae | Dave Morris did a remote restart
of the IOC after the outage. Turbo pump started. |
|
346
|
Thursday, February 09, 2017, 11:49 |
Laura Lambert | | | | Maintenance | New heatshield with flexible water lines | Thursday, February 09, 2017, 11:47
A new heatshield with flexible water
lines has been put into evap2 last Friday |
|
364
|
Monday, May 08, 2017, 10:05 |
Laura Lambert | | | | Maintenance | Turbo pump control box replaced | Monday, May 08, 2017, 10:05
Turbo pump control box died last
week. |
|
369
|
Thursday, May 11, 2017, 11:30 |
Laura Lambert | | | | Maintenance | New Ion Gauge for IGP2 | Thursday, May 11, 2017, 11:25
IGP2 has been having problems where
sometimes it turns off and requires simply |
|
379
|
Tuesday, July 18, 2017, 15:30 |
Laura Lambert | | | | Maintenance | Paddle wheel replacement for all evap2 water supplies | Tuesday, July 18, 2017, 15:26
Problems occured with TGHT water
supply paddle wheel stopped and therefore |
|
381
|
Tuesday, August 01, 2017, 15:34 |
Laura Lambert | | | | Problems | IGP1 mis-communicating with EPICS - PLC problem? | Monday, July 31, 2017, 15:24
Turned on BV and TP this afternoon.
Started ramping down, ~1min after |
|
382
|
Wednesday, August 02, 2017, 16:12 |
Marla Cervantes | | 40282-5 | | Done | Sintering La(OH)3/C pellets | Monday, July 31, 2017,
Pellets previously pressed by |
|
385
|
Tuesday, August 08, 2017, 15:00 |
Laura Lambert | Empty | | | Problems resolved | Wiring in PLC replaced re: IGP1 mis-communicating | Tuesday, August 08, 2017, 14:57
See elog i.d's #384 and #381
Investigated wiring in PLC. |
|
387
|
Tuesday, September 12, 2017, 13:08 |
Aaron Schmidt | | | | | Window shutter added | Tuesday, September 12, 2017, 12:00:
The coated back window was changed
to a shuttered window. |
|
399
|
Monday, December 11, 2017, 14:22 |
Laura Lambert | | | | Maintenance | Interlock limits updated to 500mTorr | Monday, December 11, 2017, 14:21
Dave updated evap2 interlock limits
to 500mTorr for TGHT and TBHT on friday |
|
406
|
Wednesday, April 25, 2018, 07:21 |
Aaron Schmidt | | | | Done | HS swap evap 2 | Wednesday, April 25, 2018, 07:05: TGHT
& TBHT off
Wednesday, April 25, 2018, 07:15: |
|
407
|
Saturday, April 28, 2018, 16:12 |
John Wong | Empty | Tube container | | Done | TaC coating/sintering of Tube container | Saturday, April 28, 2018, 16:09
Container is coated with TaC and
wrapped with TaC heatshield. |
|
408
|
Tuesday, May 01, 2018, 18:07 |
John Wong | np-SiC | Tube container | | Done | NanoSiC thermal treatment batch#1 | Tuesday, May 01, 2018, 18:06
21 fibrous discs of nanoSiC are loaded
into a tube container (coated/Sintered with |
|
409
|
Tuesday, May 08, 2018, 15:06 |
John Wong | np-SiC | Tube container | | Done | NanoSiC thermal treatment batch#2 | Tuesday, May 08, 2018, 15:02
22 np-SiC fibrous discs loaded in
the tube container (coated and sintered with |
|
411
|
Friday, June 08, 2018, 08:33 |
Aaron Schmidt | | | | Problems resolved | Chiller tripped / Alarm | Alarm noted on passing Hot Lab. RPG notified,
no radiological hazards. ISAC ops contacted,
drop in DI water last night. |
|