661
|
Tuesday, May 07, 2024, 06:20 |
Darwin Ortiz Rosales | TaC | | TARGET BOAT | Done | Sintering TaC coating on endcaps | Tuesday, May 07, 2024, 06:16
TP was swapped on previous day (May 6th)
protective screen installed.
Loaded 9 TaC coated end caps (groups of 4 and 5) and 2 TaC coated springs.
OMEGA Slope 0.99
Will heat to 1850-1900 C and hold for 4 hours
Good Vac = 5.0e-4 Torr
Bad Vac= 5.0 e-02 Torr
Initial IGP1=6.7E-07 Torr
|
662
|
Monday, May 27, 2024, 07:12 |
Darwin Ortiz Rosales | SiC | | LP TUBE | Done | SiC (PAA dispersant experiment) | Monday, May 27, 2024, 07:09
Small graphite cartridge was loaded with SiC discs 240523-1 and 240523-2. Discs produced without milling using PAA as a dispersant.
The coated container tube was wrapped in four Ta foil heatshields.
two Tac Coated springs at the ends in case plugs are pushed outwards.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final TGHT current= ~400A (adjustable)
Heating autoramp 2A/min to 90 A
Then at 2A/min to 120A.
Good vacuum = 5.0 e-02 Torr
Bad vacuum = 5.0E-04 Torr
IGP1 initial 4.8e-07 Torr
Monday, May 27, 2024, 09:13
Pressure started coming down. Heat at 2A/min to 120A.
Monday, May 27, 2024, 10:21
Started ramp 2A/30s to 400A will monitor temperature
stopped at 490A and will hold for 4 hours.
Monday, May 27, 2024, 12:41
temperature started creeping up past 1870C so decreased current to 461A
Current temperature is 1842 C at 461A, 7.6V
Monday, May 27, 2024, 12:55
dropped current to 441 because temperature climbed to 1899 C
Monday, May 27, 2024, 15:08
final pressure IGP1 =9.9 e-07 Torr
OMEGA= 1830 C at 410 A (reduced as needed)
Start rampdown at -2A/min
Wednesday, May 29, 2024, 10:07
Final pressure is 2.7e-7 Torr
Wednesday, May 29, 2024, 14:42
Experiment failed. Too hot probably. Bad temperature readings. Will repeat after redesigning experiment. |
663
|
Wednesday, May 29, 2024, 22:55 |
Darwin Ortiz Rosales | SiC | | LP TUBE | Done | Repeat of SiC experiment with mixed only casts | Wednesday, May 29, 2024, 22:52
Small graphite cartridge was loaded with SiC discs 240523-1 and 240523-2 and 220727-2 (baseline discs). Test Discs produced without milling using PAA as a dispersant.
The coated container tube was wrapped in four Ta foil heatshields.
two Tac Coated springs at the ends in case plugs are pushed outwards.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final TGHT current= ~400A (adjustable)
Heating autoramp 2A/min to 90 A
Then at 2A/min to 120A.
Good vacuum = 5.0 e-02 Torr
Bad vacuum = 5.0E-04 Torr
IGP1 initial 4.8e-07 Torr
Wednesday, May 29, 2024, 22:54
Kept at 400 A for 4 hours.
Starting autoramp down at -2A/min
Monday, March 10, 2025, 16:53
RD TGHT = 686A set to 700 A , 10.8V
TBHT = 230A, 3.2V
OMEGA reads 1700 but will keep here for 4 hours. |
664
|
Wednesday, June 05, 2024, 07:18 |
Darwin Ortiz Rosales | SiC | | LP TUBE | Done | sinterin experiment 240604 | Wednesday, June 05, 2024, 07:14
SiC discs loaded into tantalum tube. New mixing (two types) and old mixing.
The coated container tube was wrapped in four Ta foil heatshields.
Tac Coated springs at the ends in case plugs are pushed outwards.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:=* 0.980*
Target time at max temperature = 4 hours
Final TGHT current= ~400A (adjustable)
Heating autoramp 1A/min to 90 A
Then at 2A/min to 120A.
Good vacuum = 5.0 e-02 Torr
Bad vacuum = 5.0E-04 Torr
IGP1 initia1.3e-06Torr
Wednesday, June 05, 2024, 11:04
Continuing to ramp at 2A/min to 350A
Wednesday, June 05, 2024, 12:22
Leaving at 369 A for 4 hours (until 4 pm). Temperature readings do not appear good.
Wednesday, June 05, 2024, 16:01
Start rampdown at -2A/min
IGP1=2.0 e-6 Torr |
674
|
Friday, August 30, 2024, 11:33 |
Darwin Ortiz Rosales | TaC | 45447-8 | LP-IG-LIS | Done | TaC coating sintering | Friday, August 30, 2024, 11:31
The coated container was wrapped in 4 Ta foil heatshields.
Vacuum IGP1 initial =3.1 e-07 Torr
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~400A (adjustable)
Heating autoramp starged at 1A/min on TGHT 100A and TBHT
Then at 1A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
note: Left TBHT hole is off from center by a good margin
Sunday, September 01, 2024, 07:32
Starting initial ramp at 1A/min to 50A
Sunday, September 01, 2024, 15:20
have ramped ;up at 1A/min on both TGHT and TBHT but had two issues.
1) Set current and readback current have discrepancies but the TBHT discrepancy is significant (TBHT Set at 188 while RD is 231.9 A @ 1.9V)
TGHT also has odd behavior with set point 405 giving 392A RD and 0.067V. Will hold until 430pm before starting ramp down
Sunday, September 01, 2024, 16:30
Started rampdown at -2A/min TGHT and -1A/min TBHT
Note: OMEGA not able to give any reasonable readings
Tuesday, September 03, 2024, 13:51
After troubleshooting EVAP2 it was found that a copper line was touching the metal encasement grid most likely resulting in a short. A short was seeing and it disappeared after moving the copper line away from the grid.
Upon restarting on epics the PS went to maximum current and it was shut off after 30seconds to a minute. The system was checked again by Arthur and TGHT was manually increased to 5A and then set to Zero again. Arthur thinks that the PS probably requires this step after switching from local controls to remote. Will start the sintering again as the container is coated but not sintered.
Tuesday, September 03, 2024, 14:03
ramping at 1A/min on both TGHT and TBHT to 90A.
Tuesday, September 03, 2024, 22:25
Started rampdown at -2A/min TGHT and -1A/min TBHT. HIgh temperature from OMEGA was 1825 C at 430A readback on TGHT. |
675
|
Saturday, September 07, 2024, 09:55 |
Darwin Ortiz Rosales | TaC | 45447-13 | LP-SIS | Done | TaC coating sintering | Saturday, September 07, 2024, 09:54
The coated container was wrapped in 4 Ta foil heatshields.
Vacuum IGP1 initial =8.1 e-07 Torr
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~400A (adjustable)
Heating ramp manually to 50A on TGHT and TBHT
Then at 1A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Saturday, September 07, 2024, 17:38
At 400 A set point on TGHT, read back is 392A and OMEGA reads 1840C. TBHT set to 230A reads 233A.
It will be kept at this current for four hours before rampdown. |
676
|
Monday, September 09, 2024, 19:08 |
Darwin Ortiz Rosales | TaC | | LP-SIS | Done | TaC coating sintering LP-SIS with gas line | Monday, September 09, 2024, 19:06
The coated container was wrapped in 4 Ta foil heatshields.
Vacuum IGP1 initial =2.6 e-06 Torr
Target temperature on OMEGA= 1800-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~400A (adjustable)
Heating autoramp starged at 1A/min on TGHT and TBHT until outgassin peak passed
Then at 1A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Monday, September 09, 2024, 19:08
Peak passed around 70A will continue ramp up at 1A/min to 400A on TGHT and 230A TBHT
Tuesday, September 10, 2024, 13:13
Was ramped down at -2 A/min TGHT and -1 A/min TBHT
|
677
|
Tuesday, September 10, 2024, 13:16 |
Darwin Ortiz Rosales | Endcaps | | TARGET BOAT | Done | TaC coating sintering | A boat lined up with graphite and wrapped in 3 Ta heatshileds
Vacuum IGP1 initial =6.1 e-06 Torr
Target temperature on OMEGA= 1800-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final TGHT current= ~400A (adjustable)
Heating autoramp started semi-manually on TGHT to 65A and then at continue to 100A
After peak heat at 1A/min to =400 A TGHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Tuesday, September 10, 2024, 22:22
1810C OMEGA at 439A TGHT readback |
678
|
Wednesday, October 02, 2024, 19:24 |
Darwin Ortiz Rosales | TiC | | LP TUBE | Done | sintering TiC Experiment | Wednesday, October 02, 2024, 19:21
Ta endcup at front end of container
End-caps on the graphite cartridge have holes for outgassing.
initial heating @ 2A/min to 85 A then 2A/min to 120A TGHT. Allow pressure to drop and then ramp to 400 A at 2A/min, leave 4 hours and start ramp down.
OMEGA slope = 0.99
Vacuum limits up to 400A: 5.0e-04 Torr -- 1.0e-02 Torr
Max current~400A (1900 C)
Wednesday, October 02, 2024, 19:25
Starting IGP1 = 6.65e-06 Torr
Thursday, October 03, 2024, 05:09
Starting rampdown. Pressure stable at 4.5 e-06 Torr
Top temperature 1850 C on OMEGA
ramping down at -2A/min |
679
|
Saturday, November 23, 2024, 11:11 |
Darwin Ortiz Rosales | ZrC | | LP TUBE | Done | ZrC 24E9T1 + std conditioning and sintering | Saturday, November 23, 2024, 11:08
No milling ZrC material sintering inside graphite cartridge
baseline standard discs included for comparison.
4 Ta foils wrapped around container
one spring at the back end to retain the graphite cartridge
One Ta cap with perforations at the front for T readings
initial heating at 2A/min to 50A, followed by heating at 1A/min to 90 A
Initial IGP1= 1.0e-6 Torr
OMEGA slope =0.990
Good and bad vacuum =5.0e-5 Torr and 5e-4 torr
Saturday, November 23, 2024, 11:20
autoramp start at 2A/min to 50A on tght
Saturday, November 23, 2024, 20:11
allowed pressure to drop to 3.3e-6 Torr after degassing.
Started ramp to 90A at 1A/min
Saturday, November 23, 2024, 23:46
started ramping at 1.5A/120s or 0.75A/min to 400A
Sunday, November 24, 2024, 07:55
Reached 1900 C at 410 A setpoint and 402 A on RD
Pressure did not increase after bumping up to 410 setpoint so will keep at this current until 11 am (four hours near 1900 C in total)
Sunday, November 24, 2024, 10:58
Final IGP1 at start of rampdown = 2.9e-6 Torr
Ramping down at -2A/min |
680
|
Thursday, January 30, 2025, 09:21 |
Darwin Ortiz Rosales | Empty | 45447-30 | HP-SIS | Done | TaC coating sintering | Thursday, January 30, 2025, 09:17
Left to pump down on previous night
The coated container was wrapped in 4 Ta foil heatshields.
Vacuum IGP1 initial =8.1 e-06 Torr
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~500A (adjustable)
Heating autoramp starged at 0.5A/min(1A/120s) to 60A on both TGHT and TBHT
Then at 0.5A/min to 90 A, both TGHT and 230A TBHT
When pressure stable will ramp at 2A/min to ~500A on TGHT and 230A on TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Thursday, January 30, 2025, 09:20
currently ramping to 90A
Thursday, January 30, 2025, 12:30
Ramping to 120A @ 0.5 A/min
Thursday, January 30, 2025, 13:59
Ramping to 140 A at 1A/min (to check pressure change. So far with slower heating, pressure has not spiked very high).
Thursday, January 30, 2025, 15:59
Started ramping @ 2A/30s to 500 A on TGHT
TBHT is at 230A
Thursday, January 30, 2025, 21:25
Target was sintered when OMEGA reading 1700-1750 C
At 640-660A on TGHT RD
Check target coating and repeat these setting if good.
Thursday, January 30, 2025, 21:43
Cooling started at -2A/min on TGHT and -1A/min TBHT
|
681
|
Saturday, February 01, 2025, 09:24 |
Darwin Ortiz Rosales | Empty | 45447-28 | HP-SIS | Done | TaC coating sintering | Saturday, February 01, 2025, 09:23
The coated container was wrapped in 4 Ta foil heatshield and left in evap2 over night to attain vacuum.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~650A (adjustable)
Heating autoramp starged at 1A/min on TGHT and TBHT to 120A
Then at 2 A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Initial IGP1=5.6e-07Torr
Saturday, February 01, 2025, 11:05
@ 194A, 2.5V on TGHT, the pressure is dropping (has been dropping since 150A). starting ramp at 4a/min
Thursday, February 13, 2025, 11:40
Log entries lost as computer rebooted. Max temperature on OMEGA was 1850 C and held for 4 hours. Cooled @ -2A/min TGHT and -1A/min TBHT. |
682
|
Monday, March 03, 2025, 17:58 |
Darwin Ortiz Rosales | Empty | 45447-21 | LP-FEBIAD | Done | TaC coating sintering | Monday, March 03, 2025, 17:56
LP FEBIAD WO# 45447-21 initial wt=471.0 g (without T bar)
wrapped in 4 Ta heatshields.
Will heat at 2A/min to 95A on TGHT and TBHT
Then will heat at 2A/min to 1800 C ~400A on TGHT and 230A on TBHT
Monday, March 03, 2025, 18:01
IGP1=3.3e-06 Torr
started initial ramp to 95A
Monday, March 03, 2025, 21:52
Start 4 hour count at 940 pm
OMEGA reading 1750 C
TGHT= 435 A set and RD = 426 A, 7.0V
TGHT = 230A
Tuesday, March 04, 2025, 01:42
Start rampdown |
683
|
Monday, March 10, 2025, 09:56 |
Darwin Ortiz Rosales | Empty | 45447-3 | HP-FEBIAD | Done | TaC coating sintering |
Monday, March 10, 2025, 09:50
The coated container was wrapped in 4 Ta foil heatshield and left in evap2 over weekend to decrease pressure.
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~650A (adjustable)
Heating autoramp starged at 2A/min on TGHT and TBHT to 120A
Then at 2 A/min to =400 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Initial IGP1=
Monday, March 10, 2025, 10:36
Initial IGP1= 8.5 e-06 torr
Starting ramp to 120A for both TGHT and TBHT
Monday, March 10, 2025, 16:57
RD TGHT =686A set to 700A, 10.8V
TBHT = 230A, 3.1V
OMEGA= 1710
Will leave for 4 hours
Monday, March 10, 2025, 20:42
IGP1=7.9e-06 Torr
OMEGA= 1750 C
TGHT = 686 A, 10.8V
TBHT= 230A, 3.1 V
starting rampdown at -2A/min TGHT and -1A/min TBHT
|
684
|
Wednesday, March 12, 2025, 07:10 |
Darwin Ortiz Rosales | Endcaps | | TARGET BOAT | Done | TaC coating sintering | Tuesday, March 11, 2025, 15:44
The coated container was wrapped in 3 Ta foil heatshields.
16 caps and 4 springs
Target temperature on OMEGA= 1750-1800C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= N/A
Final TGHT current= ~400A (adjustable)
Wednesday, March 12, 2025, 07:07
Heating autoramp started at 1A/min on TGHT 90A
Then at 4A/min to 400 A.
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
IGP1 initial =4.8e-07 Torr
Wednesday, March 12, 2025, 09:52
starting ramp at 2A/min to 400A
Wednesday, March 12, 2025, 10:21
increasing ramp to 4A/min (2A/30s)
Wednesday, March 12, 2025, 11:57
TGHT=441A, 7.2V
Will keep for 4 hours
1750C
Wednesday, March 12, 2025, 15:57
starting rampdown at -2A/min |
685
|
Tuesday, March 18, 2025, 06:53 |
Darwin Ortiz Rosales | Empty | 45447-6 | LP-IG-LIS | Done | TaC coating sintering | Tuesday, March 18, 2025, 06:48
The coated container was wrapped in 4 Ta foil heatshields.
Vacuum IGP1 initial =9.1 e-07 Torr
Target temperature on OMEGA= 1850-1900 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~400A (adjustable)
Heating autoramp starged a 2A/min on TGHT and TBHT
to =300 A TGHT and 230A TBHT
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Tuesday, March 18, 2025, 13:47
OMEGA read 1850C at 380A on TGHT. The temperature dropped and current was raised to 390A, 6.5V on TGHT.
TBHT was kept at 230A, 3.2V
Temperature dropped to 1756 after 4 hours of sintering. Will start rampdown at -2A/min for TGHT and -1A/min TBHT.
|
686
|
Thursday, March 20, 2025, 06:10 |
Darwin Ortiz Rosales | Empty | 45447-19 | LP-SIS | Done | TaC coating sintering | Wednesday, March 19, 2025, 13:08
The coated container was wrapped in 4 Ta foil heatshields.
Vacuum IGP1 initial =
Target temperature on OMEGA= 1800-1850 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~400A (adjustable)
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Thursday, March 20, 2025, 06:10
IGP1 initial = 6.1e-7 Torr
start ramp at 2A/min
Thursday, March 20, 2025, 07:04
paused ramp to prevent pressure spike
Thursday, March 20, 2025, 10:16
OMEGA 1800 C @ TGHT = 402A, 6.8V
Will leave for 4 hours.
Thursday, March 20, 2025, 13:53
Starting rampdown at 2A/min TGHT and 1A/min TBHT |
687
|
Tuesday, March 25, 2025, 15:26 |
Darwin Ortiz Rosales | Empty | 45447-16 | LP-SIS | Done | TaC coating sintering | Tuesday, March 25, 2025, 15:25
The coated container as wrapped in 4 Ta foil heatshields.
Vacuum IGP1 initial =e-07 Torr
Target temperature on OMEGA= 1800-1850 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~400A (adjustable)
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Will be left overnight to pump down
Wednesday, March 26, 2025, 09:07
starting ramp up at 2A/min to 230A for both TGHT and TBHT
Wednesday, March 26, 2025, 12:48
1800 C at 400A TGHT, 6.9V TGHT
Leaving for 4 hours |
688
|
Friday, March 28, 2025, 10:34 |
Darwin Ortiz Rosales | Empty | 45447-20 | LP-SIS | Done | TaC coating sintering | Friday, March 28, 2025, 06:49
The coated container was wrapped in 4 Ta foil heatshields.
Vacuum IGP1 initial =8.0e-07 Torr
Target temperature on OMEGA= 1800-1850 C
OMEGA slope:= 0.990
Target time at max temperature = 4 hours
Final Current TBHT= 230 A
Final TGHT current= ~400A (adjustable)
Good vacuum = 5.0 e-04 Torr
Bad vacuum = 5.0E-02 Torr
Starting ramp at 2A/min
Friday, March 28, 2025, 09:41
At 412A readback on TGHT OMEGA reads 1702 C. Maybe re-use of Ta heatshields resulted in loss of efficiency. Will ramp to 420 A and leave for 4 hours.
Friday, March 28, 2025, 14:25
Started rampdown at -2A/min TGHT and -1A/min TBHT |
689
|
Friday, April 04, 2025, 06:55 |
Darwin Ortiz Rosales | SiC | 45447-1 | HP-FEBIAD | Done | SiC-250402 conditioning | Friday, April 04, 2025, 06:41
Total number of foils:328
Total length packed 15.2 cm
container has 4 Ta heat shields (one inner only around fins)
No endcaps inserted to facilitate out-gassing
Ta coated spring at back, coated cap at front with perforations
ramp to 500A @ 1A/min TGHT and to 230A on TBHT
max approx 700A on TGHT and 230A on TBHT (Omega slope set = 0.990)
Then temperature = 1800C
TBHT will be set fixed at 230 A (max). TBHT heated manually and automatically to max.
Good vac at 5.00 e -4 Torr
Bad vac at 5.00 e-2 Torr
IGP1= 1e-06 Torr at start of initial ramp.
initiating ramp up
Friday, April 04, 2025, 10:54
Paused ramp at 128.5A TGHT and 130.2 A TBHT. Will hold and let pressure drop.
IGP1 = 5.43e-04 Torr currently
Friday, April 04, 2025, 14:04
restarting ramp
IGP1=2.6e-05 Torr
Friday, April 04, 2025, 16:35
increasing ramp to 3A/min
@18:15 ramp was slowed down to 2A/min and left to reach 730~A
Friday, April 04, 2025, 22:54
Current was stopped at 733A on readback and left for 3.5 hours, then manually ramped to 738A for 0.5 hours.
This is in accordance with the initial oven (Elog 619)
Friday, April 04, 2025, 23:45
starting ramp down at -1A/min TBHT and -2A/min TGHT |
|