30
|
Monday, June 11, 2012, 12:26 |
John Wong | SiC | 38481-2 | HP-SIS | Problems | End caps vaporized |
|
|
|
38
|
Monday, July 30, 2012, 15:42 |
John Wong | | | | Problems | Chiller maybe leaky | Monday, July 30, 2012, 15:38
The evaporator was used for the processing
the NiO target for 8 days and it was discovered |
|
|
93
|
Friday, November 01, 2013, 17:20 |
Anders Mjos | | | | Problems | Backing pump needs new filter | The source of the poor vacuum in the backing
line seems to be related to a dirty filter.
We will try to find a replacement filter |
|
|
109
|
Wednesday, January 22, 2014, 18:22 |
John Wong | Empty | 40282-4 | TARGET BOAT | Problems | Sintering Ta target boat with TaC coating (IEVAP2:TBHT2 water signal problem) |
|
|
|
122
|
Friday, March 07, 2014, 22:25 |
John Wong | | 40282-3 | TARGET BOAT | Problems | Sintering TaC coated end caps |
|
|
|
199
|
Thursday, May 28, 2015, 10:23 |
Laura Lambert | Endcaps | 40282-5 | TARGET BOAT | Problems | Sintering TaC coating on Ta endcaps - not fully sintered |
|
|
|
230
|
Monday, July 13, 2015, 11:54 |
Laura Lambert | Endcaps | 40282-5 | TARGET BOAT | Problems | Sintering TaC coating on Ta endcaps | Monday, July 13, 2015, 11:53
A Ta foil is placed in the target |
|
|
312
|
Monday, August 08, 2016, 15:22 |
Laura Lambert | SiC | 40860-3 | LP-IG-LIS | Problems | Conditioning SiC#34 | Monday, August 08, 2016, 15:19
Previously sintered over weekend |
|
|
318
|
Tuesday, August 30, 2016, 15:25 |
John Wong | SiC | 40860-3 | LP-IG-LIS | Problems | Conditioning SiC#34. Note about the p/s voltage |
|
|
|
344
|
Friday, February 03, 2017, 14:18 |
Laura Lambert | Endcaps | | TARGET BOAT | Problems | Sintering TaC coating on Ta endcaps and springs | Friday, February 03, 2017, 14:17
The endcaps are stacked together |
|
|
355
|
Thursday, April 06, 2017, 08:57 |
Laura Lambert | Empty | | TARGET BOAT | Problems | Sintering TaC coating on evap1 target boat |
|
|
|
361
|
Wednesday, May 03, 2017, 13:48 |
Laura Lambert | SiC | 39530-10 | HP-FEBIAD | Problems | Sintering SiC#36 |
|
|
|
378
|
Monday, July 10, 2017, 17:36 |
John Wong | np-SiC | | TARGET BOAT | Problems | Water Sensor Problem, TGHT Tripped. (np-SiC fibrous Pellet: Applied pressure vs Density) | Monday, July 10, 2017, 17:28
Two np-SiC fibrous pellets with different
applied pressure: |
|
|
381
|
Tuesday, August 01, 2017, 15:34 |
Laura Lambert | | | | Problems | IGP1 mis-communicating with EPICS - PLC problem? | Monday, July 31, 2017, 15:24
Turned on BV and TP this afternoon.
Started ramping down, ~1min after |
|
|
383
|
Friday, August 04, 2017, 10:52 |
Laura Lambert | | 40282-5 | TARGET BOAT | Problems | Sintering La(OH)3/C pellets |
|
|
|
396
|
Thursday, December 07, 2017, 11:56 |
Laura Lambert | Endcaps | | TARGET BOAT | Problems | Sintering TaC coating on endcaps and springs |
|
|
|
417
|
Tuesday, September 04, 2018, 17:04 |
John Wong | Empty | | LP-SIS | Problems | TaC coating/sintering for UC target container | Tuesday, September 04, 2018, 16:58
Container is coated with TaC and
wrapped with Ta heat-shield ( 3 layers) |
|
|
557
|
Wednesday, October 13, 2021, 08:35 |
Aaron Schmidt | | | | Problems | Troubleshoot - Pump down issues. | Swapped out the Cu gaskets for SS gaskets
in the HS top lines. (x2)
Wednesday, October 13, 2021, 08:35: |
|
|
670
|
Wednesday, August 14, 2024, 07:23 |
Marla Cervantes | C | 44139-5 SK | LP TUBE | Problems | EVAP2 Calibration - Vanadium | Tuesday, August 13, 2024, 17:20 Pressure
kept increasing when turning the turbo pump
on |
|
|
2
|
Thursday, July 21, 2011, 17:33 |
Pierre Bricault | | | | Maintenance | | Rick mentioned to me that the evaporator is
ready for the next steps of the commissioning
process.
|
|