ID Date Author Target Material Target Oven W.O#down Source Status Subject Text Attachments
  187   Thursday, April 23, 2015, 10:17 John WongSiC38817-7HP-SISDoneSintering SiC#31

    

       
            
 Screen_Shot_2015-04-23_at_3.04.01_PM.png 
  219   Monday, June 22, 2015, 13:11 John WongEmpty38817-6HP-SISIn progressRUSH! Sintering TaC coated container for SiC Monday, June 22, 2015, 13:00
Containers is coated with TaC. Wrapped
with 3 layers of Ta heat-shield.  Air
  
  220   Tuesday, June 23, 2015, 10:18 Laura LambertEmpty38817-6HP-SISDoneRUSH! Sintering TaC coated container for SiC

    

       
            
  
  221   Tuesday, June 23, 2015, 12:26 John WongSiC38817-6HP-SISIn progressRUSH! SiC backup target undergoes sintering processTuesday, June 23, 2015, 12:21
Target container is loaded with 485
discs of SiC with packed length of 17.4cm. 
  
  222   Thursday, June 25, 2015, 16:13 Laura LambertSiC38817-6HP-SISDoneRUSH! SiC backup target undergoes sintering process

    

       
            
 IMG_20150625_152233125.jpgIMG_20150625_152256456.jpg 
  183   Monday, March 09, 2015, 16:50 Laura LambertTa38817-5HP-SISIn progressConditioning Ta target Monday, March 09, 2015, 16:47
Target consists of 400 discs.
Total packed length 3.4cm
 first_ramp_up.JPGsecond_ramp_up_with_Ta_heat_shields.JPG 
  184   Monday, March 16, 2015, 17:38 John WongTa38817-5HP-SISDoneConditioning Ta target

    

       
            
  
  82   Wednesday, August 21, 2013, 12:30 John WongTa38817-10HP-SISDoneConditioning Ta target Wednesday, August 21, 2013, 12:28
Container is filled with 400 discs
of Ta foils, and wrapped with 3 layers of
 Ta#41_conditioning.PNG 
  79   Monday, July 22, 2013, 15:03 John WongEmpty38634-7LP-SISDoneSintering empty target oven coated with TaC for UCx#7Monday, July 22, 2013, 15:00
Target container is coated with TaC
- this container will be used for UCx#7.
  
  37   Sunday, July 22, 2012, 20:51 John WongNiO38481-7HP-FEBIADDoneSintering NiO#1 Sunday, July 22, 2012, 20:30
The NiO target materials were loaded
into the container today.  
 NiO#1_sinteringevap2.pngNIO#1_TGHT_TBHT_250_220.pngSintered_NiO.GIFEndcap.GIF 
  75   Tuesday, May 14, 2013, 17:15 John WongEmpty38481-6HP-FEBIADDoneSinteringTaC coatingTuesday, May 14, 2013, 17:04
Target oven is coated with TaC, and
wrapped with 3-Ta heat shields.
  
  77   Monday, June 17, 2013, 16:59 Laura LambertSiC38481-6HP-FEBIADDoneSintering of SiC #29Monday, June 17, 2013, 16:57
Target is loaded with 510 SiC discs
Container was previously coated with
  
  78   Tuesday, June 18, 2013, 16:40 John WongSiC38481-6HP-FEBIADDoneSintering of SiC #29

    

       
            
  
  71   Tuesday, April 30, 2013, 11:20 Anders MjosEmpty38481-5HP-FEBIADDoneCTL thermal test CTL block on T/C F/T Ch 1
Supply on Ch 3
HS Return on Ch 4
 StripTool_2013-05-02.pngCTL_ITD0431_Evap2.pdf2013-04-30_Evap2_ITD0431_CTL_Thermal_Test.pdf 
  60   Wednesday, March 06, 2013, 10:41 Anders MjosEmpty38481-4HP-FEBIADDoneCTL thermal testWednesday, March 06, 2013
The Cool Transfer Line (CTL) test
target is installed for thermal tests. Drawing
 CTL_1st_Assebmly_Thermal_Test_Evap2.pdf2013-03-08_Evap2_First_Thermal_Test.pdf 
  61   Wednesday, March 06, 2013, 17:53 John WongEmpty38481-4HP-FEBIADDoneCTL thermal test

    

       
            
 rampingup_1.PNGrampingup_2.PNGautorampingdown_23.PNG 
  62   Monday, March 11, 2013, 12:23 Anders MjosEmpty38481-4HP-FEBIADDoneCTL thermal test 2 

    
 2013-03-11_Evap2_Second_Thermal_Test.pdf 
  63   Monday, March 11, 2013, 15:59 John WongEmpty38481-4HP-FEBIADDoneCTL thermal test 2

    

       
            
 autorampingup_110.PNG 
  64   Wednesday, March 13, 2013, 16:08 Anders MjosEmpty38481-4HP-FEBIADDoneThermal testWednesday, March 13, 2013 
Thermocouple channels (see attached
PDF for photos)
 HP-FEBIAD-A_TC_at_fins.pdf 
  65   Thursday, March 14, 2013, 12:27 Anders MjosEmpty38481-4HP-FEBIADDoneCTL thermal test 3 (w/o CTL block)Thursday, March 12, 2013 
The CTL was removed and target heated
to 580A / 300A
 2013-03-13_-_FEBIAD-HP-A_TargetLeg_and_HeatShield_TC.pdf2013-03-13_-_FEBIAD-HP-A_TargetLeg_and_HeatShield_TC.xlsx 
ELOG V2.9.2-2455