Entry  Wednesday, August 06, 2014, 16:10, John Wong, Ta, 38817-9, HP-SIS, In progress, Conditioning Ta target 
    Reply  Friday, August 08, 2014, 15:16, Laura Lambert, Ta, 38817-9, HP-SIS, Done, Conditioning Ta target 
Message ID: 154     Entry time: Friday, August 08, 2014, 15:16     In reply to: 152
Author: Laura Lambert 
Target Material: Ta 
Target Oven W.O#: 38817-9 
Source: HP-SIS 
Status: Done 
Subject: Conditioning Ta target 

John Wong wrote:

Wednesday, August 06, 2014, 15:59

Target consists of 400 Ta discs. 

Total packed length 4.5cm

Total mass 47.490g.

Re foil inserted.


Wednesday, August 06, 2014, 16:07

Chamber is currently being pumped down.

No Ta heat-shield wrapped (Want to check the temperature without it) 

One end-cap inserted on left (wrt ionizer into the page).

TGHT and TBHT will be ramped up to 820A/230A at 2A/min.


 Wednesday, August 06, 2014, 18:07

Vacuum at 2.3e-6 Torr.  HS water valve opened.  No leaks.

Initiated auto-ramping.


 Thursday, August 07, 2014, 11:39

Target has been heated for 11hrs at TGHT/TBHT = 820A/230A.

Temperature measured with pyrometer:

Target leg = 1600C + (250 correction for e=0.25) = 1850C

Inside target material = dark, temp can't be measured.

Cooling down at 2A/min for TGHT and 1A/min TBHT.


 

 Friday, August 08, 2014, 15:14

Vented in air and opened up up this morning.

Endcaps inserted and expanded.

Rh foil and salts added.


 