Entry  Friday, March 21, 2014, 16:18, John Wong, TiC, 38817-8, HP-SIS, In progress, Sintering TiC  
 Friday, March 21, 2014, 16:09
Target container is loaded with 360 Discs of TiC.  
Target length = 11.7cm.  
    Reply  Wednesday, March 26, 2014, 11:07, Laura Lambert, TiC, 38817-8, HP-SIS, In progress, Sintering TiC  


    
        
            John Wong wrote:
        
        
            
             Friday, March 21, 2014, 16:09
    Reply  Wednesday, March 26, 2014, 18:23, John Wong, TiC, 38817-8, HP-SIS, Done, Sintering TiC#4 


    
        
            Laura Lambert wrote:
        
        
            
            
            
              
Entry  Wednesday, August 06, 2014, 16:10, John Wong, Ta, 38817-9, HP-SIS, In progress, Conditioning Ta target 
Wednesday, August 06, 2014, 15:59
Target consists of 400 Ta discs. 
Total packed length 4.5cm
    Reply  Friday, August 08, 2014, 15:16, Laura Lambert, Ta, 38817-9, HP-SIS, Done, Conditioning Ta target 


    
        
            John Wong wrote:
        
        
            
            Wednesday, August 06, 2014, 15:59
Entry  Monday, March 09, 2015, 16:50, Laura Lambert, Ta, 38817-5, HP-SIS, In progress, Conditioning Ta target first_ramp_up.JPGsecond_ramp_up_with_Ta_heat_shields.JPG
 Monday, March 09, 2015, 16:47
Target consists of 400 discs.
Total packed length 3.4cm
    Reply  Monday, March 16, 2015, 17:38, John Wong, Ta, 38817-5, HP-SIS, Done, Conditioning Ta target 


    
        
            Laura Lambert wrote:
        
        
            
             Monday, March 09, 2015, 16:47
Entry  Thursday, April 09, 2015, 09:38, Laura Lambert, Empty, 38817-7, HP-SIS, Done, Sintering TaC coating container for SiC#32 sintering_TaC_coating_for_container.JPG
 Thursday, April 09, 2015, 09:33
Target container is coated with TaC and wrapped with 3-Ta heat shields, not incl center block.
TGHT and TBHT will be ramped up to 820A and 230A, respectively.
Entry  Friday, April 17, 2015, 16:14, Laura Lambert, SiC, 38817-7, HP-SIS, In progress, Sintering SiC#31 
 Friday, April 17, 2015, 16:01
Total number of foils: 520 discs
Total mass of materials [incl graphite foils]: 60.2441g
    Reply  Thursday, April 23, 2015, 10:17, John Wong, SiC, 38817-7, HP-SIS, Done, Sintering SiC#31 Screen_Shot_2015-04-23_at_3.04.01_PM.png


    
        
            Laura Lambert wrote:
        
        
            
             Friday, April 17, 2015, 16:01
Entry  Monday, June 22, 2015, 13:11, John Wong, Empty, 38817-6, HP-SIS, In progress, RUSH! Sintering TaC coated container for SiC  
Monday, June 22, 2015, 13:00
Containers is coated with TaC. Wrapped with 3 layers of Ta heat-shield.  Air blown to for quick dry.
Installed, and pumped down, vac currently at 6.7e-6 Torr. 
    Reply  Tuesday, June 23, 2015, 10:18, Laura Lambert, Empty, 38817-6, HP-SIS, Done, RUSH! Sintering TaC coated container for SiC  


    
        
            John Wong wrote:
        
        
            
            Monday, June 22, 2015, 13:00
Entry  Tuesday, June 23, 2015, 12:26, John Wong, SiC, 38817-6, HP-SIS, In progress, RUSH! SiC backup target undergoes sintering process 
Tuesday, June 23, 2015, 12:21
Target container is loaded with 485 discs of SiC with packed length of 17.4cm. 
Container is wrapped with 3 Ta-heat shields and previously coated/sintered with TaC.
    Reply  Thursday, June 25, 2015, 16:13, Laura Lambert, SiC, 38817-6, HP-SIS, Done, RUSH! SiC backup target undergoes sintering process IMG_20150625_152233125.jpgIMG_20150625_152256456.jpg


    
        
            John Wong wrote:
        
        
            
            Tuesday, June 23, 2015, 12:21
Entry  Tuesday, August 18, 2015, 16:02, Laura Lambert, Ta, , HP-SIS, In progress, Conditioning Ta#46 Target 
Tuesday, August 18, 2015, 15:53
Target consists of 505 discs.
Total packed length 3.4cm.
    Reply  Wednesday, August 19, 2015, 17:26, John Wong, Ta, , HP-SIS, In progress, Conditioning Ta#46 Target 


    
        
            Laura Lambert wrote:
        
        
            
            Tuesday, August 18, 2015, 15:53
    Reply  Thursday, August 20, 2015, 10:07, Laura Lambert, Ta, , HP-SIS, In progress, Conditioning Ta#46 Target 


    
        
            John Wong wrote:
        
        
            
            
            
    Reply  Thursday, August 20, 2015, 17:15, John Wong, Ta, , HP-SIS, Done, Conditioning Ta#46 Target 


    
        
            Laura Lambert wrote:
        
        
            
            
            
              
Entry  Wednesday, December 16, 2015, 10:22, Laura Lambert, Ta, 41369-5, HP-SIS, Done, Conditioning back-up Ta Target & emissivity measurements 
 Wednesday, December 16, 2015, 10:09
Target consists of 505 discs.
Total packed length 3.4cm.
Entry  Thursday, January 07, 2016, 09:19, Aurelia Laxdal, Ta, 41369-5, HP-SIS, In progress, Temperature measurements Jan_9_and_10_2016_measurements.docx
Temperature measurements in progress this week for Ta HP-SIS.
See attachment for the current settings and rampings of the TGHT/TBHT  for the temperature measurements taken on  Jan. 9-10, 2016 .
Note: TBHT PS tripped off on Jan. 9, 2016 (see first page of the attached file) and couldn't turn it ON again over the week-end.