Monday, June 15, 2015, 15:30, John Wong, Empty, 41177-2, LP-SIS, Done, Re-Sintering TaC coating container for ZrC back-up
| +
Thursday, June 25, 2015, 16:20, Laura Lambert, ZrC, 41177-2, LP-SIS, In progress, Sintering back-up ZrC
| +
Monday, June 29, 2015, 07:05, John Wong, ZrC, 41177-2, LP-SIS, Done, Sintering back-up ZrC
| +
Monday, June 29, 2015, 16:18, Laura Lambert, Empty, 41369-2, LP-SIS, In progress, Sintering TaC coating container
| +
Monday, June 29, 2015, 23:42, John Wong, Empty, 41369-2, LP-SIS, In progress, Sintering TaC coating container
| +
Tuesday, June 30, 2015, 09:50, Laura Lambert, Empty, 41369-2, LP-SIS, In progress, Sintering TaC coating container
| +
Monday, July 06, 2015, 12:07, John Wong, Empty, 41369-2, LP-SIS, In progress, Sintering TaC coating container
| +
Monday, July 06, 2015, 16:30, Laura Lambert, Empty, 41369-2, LP-SIS, Done, Sintering TaC coating container
| +
Thursday, September 24, 2015, 12:18, John Wong, Empty, 41077-5, LP-SIS, Done, Sintering TaC coating container for UCx Target
| +
Tuesday, October 06, 2015, 15:18, John Wong, Empty, 41077-5, LP-SIS, In progress, Test#1: Measuring temp with thermocouple (centre) & 2C-IR
| +
Thursday, October 08, 2015, 12:26, John Wong, Empty, 41077-5, LP-SIS, In progress, Test#2: Measuring temp with thermocouple (away from centre) & 2C-IR
| +
Wednesday, October 21, 2015, 17:39, John Wong, Empty, 41077-3, LP-SIS, In progress, Sintering TaC on LPSIS (small block) container
| +
Thursday, October 22, 2015, 11:41, Laura Lambert, Empty, 41077-3, LP-SIS, In progress, Sintering TaC on LPSIS (small block) container
| +
Thursday, October 22, 2015, 17:10, John Wong, Empty, 41077-3, LP-SIS, In progress, Sintering TaC on LPSIS (small block) container
| +
Monday, October 26, 2015, 16:14, Laura Lambert, Empty, 41077-3, LP-SIS, Done, Sintering TaC on LPSIS (small block) container & temp measurements with 1xTa h.s
|
Monday, October 26, 2015, 16:17, Laura Lambert, Empty, 41077-3, LP-SIS, Done, temp measurements with 2xTa h.s on LPSIS (small block) container 6x
|
Monday, November 02, 2015, 16:29, Laura Lambert, Empty, 41077-3, LP-SIS, Done, temp measurements with 3xTa h.s on LPSIS (small block) container
| +
Thursday, November 05, 2015, 16:20, Laura Lambert, , 41077-3, LP-SIS, In progress, Sintering TaC coating on 'temporary endcaps' springs
| +
Monday, November 09, 2015, 12:56, John Wong, , 41077-3, LP-SIS, In progress, Sintering TaC coating on 'temporary endcaps' springs (Slope changed to 1.04)
| +
Monday, November 09, 2015, 14:22, Laura Lambert, , 41077-3, LP-SIS, Done, Sintering TaC coating on 'temporary endcaps' springs (Slope changed to 1.04)
|
|