Wednesday, October 21, 2015, 17:35
This container is prepared for a backup UCx target (otherwise it will be used for development purposes).
The container is coated with TaC; one layer of Ta-heat shield is used.
TGHT will be ramped up to reach 1900C (previous container had TGHT ramped up to 440A).
TBHT will be ramped up to max 230A.
Chamber is currently being pumped down.
Heating can begin once the vacuum is good, currently at 4.8e-5 Torr.
Friday, October 23, 2015, 16:15
TGHT reached to 500A and temp measured at 1940C. More about the temp plot can be found in the dropbox.
Initiated cooling down at 2A/min.
Target will be inspected next Monday.
|