Thursday, September 22, 2022, 07:15, Darwin Ortiz Rosales, TaC, , TARGET BOAT, Done, TaC coated endcaps and spring sintering
|
Thursday, September 22, 2022, 07:13
Each endcap is separated with a disc of graphite foil and rolled into 3 packs of 4 within a foil envelope in a target boat.
There are also 2 coated springs
The boat is wrapped with 3-layers of Ta heatshields.
Chamber pumped down over previous night
Good vacuum = 5.0e-04 Torr
bad vacuum = 5.e-02 Torr
OMEGA slope = 0.99
Will ramp TGHT up to 40 A then autoramp to 400A at 1A/min.
Final desired temperature on OMEGA (tap)= 1800C
IGP1= 3.8e-7 Torr
Thursday, September 22, 2022, 10:08
TGHT= 168A,
IGP1= 4.7E-07=6Torr
Increased ramp to 2A/min
Thursday, September 22, 2022, 12:08
TGHT= 400A, 6.7V
OMEGA= 1604C
Continuing autoramp to 450A @2A/min
Thursday, September 22, 2022, 12:36
TGHT=450A, 7.7V
OMEGA=1700C
Tapping to 1800C manually
Thursday, September 22, 2022, 12:54
OMEGA = 1750C at 505A, 8.8 V
Tapped to 540A, 9.5V
Will leave there for two more hours
OMEGA= 1800+/- 10 C
Thursday, September 22, 2022, 15:00
TGHT = 540A, 9.3V
OMEGA= 1713
start rampdown at-2A/min
Friday, September 23, 2022, 09:49
IGP1= 4.0e-7 Torr
Will dismount container
Saturday, September 24, 2022, 09:10
Endcaps looked good. The front spring sintered onto container and not usable. signs of overheating.
|
Friday, December 16, 2022, 10:03, Darwin Ortiz Rosales, TaC, , TARGET BOAT, Done, TaC coated endcaps and spring sintering
|
4 TaC coated springs and 4 Tac coated caps loaded into a target boat.
Target boat wrapped in 4 Ta heatshields
Target boat type was with endcaps at both ends.
Left in Evap2 over previous night to depressurize.
Target temperature= 1850-1900C for 4 hours
Good vacuum = 5e-04 Torr
Bad vacuum = 5e-02 Torr
Friday, December 16, 2022, 10:01
Heated @1A/min to 100A on TGHT
Then heated 2A/min to 120A
Friday, December 16, 2022, 10:08
started autoramp @4A/min to 300A
Friday, December 16, 2022, 11:15
TGHT=450 A, 7.6 V
OMEGA= 1863 C
IGP1= 7.2e-06 Torr
Will keep for 4 hours
Monday, December 19, 2022, 10:30
Sintering was perfect. Repeat same configuration next time. |
Thursday, March 09, 2023, 06:58, Darwin Ortiz Rosales, Endcaps, , TARGET BOAT, Done, TaC coated endcaps and spring sintering
|
Thursday, March 09, 2023, 06:53
2 TaC coated springs and 12 Tac coated caps loaded into a target boat (in packs of 4 wrapped in graphite foil).
Target boat wrapped in 4 Ta heatshields
Target boat type was with endcaps at both ends.
Left in Evap2 over previous night to depressurize.
Target temperature= 1850-1900C for 4 hours
Good vacuum = 5e-04 Torr
Bad vacuum = 5e-02 Torr
Start autoramp at 2A/min to 50A on TGHT
Thursday, March 09, 2023, 07:22
at 44A switched ramping rate to 1A/min to 120 A
Thursday, March 09, 2023, 09:53
ramping at 4A/min (2A/30s) to 400A
IGP1= 9.9e-07 Torr
Thursday, March 09, 2023, 11:26
1130 am reaching 425A on TGHT
1850 C OMEGA
Thursday, March 09, 2023, 15:37
TGHT 425 A, 7.1V
OMEGA = 1850 C
Starting rampdown @ -2A/min
endcaps and spring looked really good.
|
Friday, April 28, 2023, 11:31, Darwin Ortiz Rosales, TaC, Boat, TARGET BOAT, Done, TaC coated endcaps and spring sintering
|
Friday, April 28, 2023, 11:29
loaded 14 TaC coated end caps and 2 TaC coated springs.
OMEGA Slope 0.99
Will heat to 1850-1900 C and hold for 4 hours
Good Vac = 5.0e-4 Torr
Bad Vac= 5.0 e-02 Torr
2 end caps had slight damage and were disposed of. 12 good caps and 2 good springs. |
Monday, June 01, 2020, 12:03, Aaron Schmidt, Ta, 44139-13, LP-SIS, In progress, Ta#60 Conditioning
|
Ta#60 LP-SIS target description:
Total Ta foils = 470 [6x20 packs + 350 single discs]
Foil Thickness = 0.025mm
Target density = 14.081 g/cm3
Target length = 3.33 cm
Total Mass = 46.891 g [Incl foils + Ta wire on 6 packs]
Total mass w/ Target oven= 445g w/ end caps)
Discs in target are arranged as follows: 1pack / 75singles / 1pack / 100singles / 2packs / 100singles / 1pack / 75singles / 1pack
End caps installed (Expanded). No Ta heat shield added.
https://elog.triumf.ca/TIS/Target+Production/98
Monday, June 01, 2020, 11:38: Roughing.
Monday, June 01, 2020, 12:03: Turbo pump on.
TBHT will be ramped up to 230A at 1.0A/min.
TGHT will be ramped up to 600A + at 2.0A/min.
Final desired temperature = 1900C.
OMEGA slope = 0.98.
Tuesday, June 02, 2020, 07:13: Omega slope set to 0.98. Power supplies / sources on. vacuum@ 5.13e-07T.
Tuesday, June 02, 2020, 07:16: Manually tap up TGHT / TBHT to 40 / 5 A. Vacuum @ 5.08e-07T.
Tuesday, June 02, 2020, 07:19: Auto-ramping TGHT / TBHT @ 2 A per min to 350 / 150 A.
Tuesday, June 02, 2020, 10:02: Auto-ramping TGHT / TBHT @ 2 / 1 A per min to 450 / 200 A. Vacuum @ 1.39e-06T. TGHT Voltage= 5.955V. Omega: 1288 deg C.
Tuesday, June 02, 2020, 11:54: Auto-ramping TGHT / TBHT @ 2 / 1 A per min to 500 / 230 A. Vacuum @ 1.85e-06T. TGHT Voltage= 7.998V. Omega: 1528 deg C.
Tuesday, June 02, 2020, 13:16: Auto-ramping TGHT @ 2 A per min to 550 A. Vacuum @ 2.51e-06T. TGHT Voltage= 9.060V. Omega: 1625 deg C.
Tuesday, June 02, 2020, 13:58: Auto-ramping TGHT @ 2 A per min to 600 A. Vacuum @ 3.53e-06T. TGHT Voltage= 9.060V. Omega: 1728 deg C.
Tuesday, June 02, 2020, 14:23: Auto-ramping TGHT @ 2 A per min to 625 A. Vacuum @ 5.56e-06T. TGHT Voltage= 11.236V. Omega: 1821 deg C.
Tuesday, June 02, 2020, 14:36: TGHT / TBHT 625 / 230 A. Vacuum @ 6.65e-06T. TGHT Voltage= 11.724V. Omega: 1865 deg C.
Tap up TGHT manually.
Tuesday, June 02, 2020, 14:48: TGHT / TBHT 643 / 230 A. Vacuum @ 7.24e-06T. TGHT Voltage= 12.129V. Omega: 1901-1903 deg C.
Desired temperature = 1900C reached.
Tuesday, June 02, 2020, 22:20: TGHT / TBHT 643 / 230 A. Vacuum @ 2.05e-06T. TGHT Voltage= 12.212V. Omega: 1901-1903 deg C.
Tuesday, June 02, 2020, 22:22: Auto-Cooling @ 1 A per min.
Wednesday, June 03, 2020, 06:08: TBHT @ 0. TGHT set for Auto-Cooling @ 2 A per min.
Wednesday, June 03, 2020, 11:38: PS off. Turbo pump off.
Wednesday, June 03, 2020, 12:40: Venting. |
Sunday, March 13, 2016, 14:58, Aurelia Laxdal, Ta, 41790-1, LP-SIS, In progress, Ta#47 LP-SIS (with new center block) conditioning
|
Started Ta#47 heating at Evap2 using the autoramp program. The TGHT current is setup to go to 300A (for now) and the TBHT to 230A (final value). |
Monday, March 14, 2016, 09:22, Laura Lambert, Ta, 41790-1, LP-SIS, In progress, Ta#47 LP-SIS (with new center block) conditioning
|
Aurelia Laxdal wrote: |
Started Ta#47 heating at Evap2 using the autoramp program. The TGHT current is setup to go to 300A (for now) and the TBHT to 230A (final value).
|
Monday, March 14, 2016, 09:20
One thermocouple was not welded on correctly and is not working.
Cooling evap2 back down, to remove target and re-weld thermocouple.
Once thermocouple replaced, will ramp back up and continue with tests/ conditioning of target.
|
Monday, March 14, 2016, 13:12, Anders Mjos, Ta, 41790-1, LP-SIS, In progress, Ta#47 LP-SIS (with new center block) conditioning
|
Laura Lambert wrote: |
Aurelia Laxdal wrote: |
Started Ta#47 heating at Evap2 using the autoramp program. The TGHT current is setup to go to 300A (for now) and the TBHT to 230A (final value).
|
Monday, March 14, 2016, 09:20
One thermocouple was not welded on correctly and is not working.
Cooling evap2 back down, to remove target and re-weld thermocouple.
Once thermocouple replaced, will ramp back up and continue with tests/ conditioning of target.
|
Monday, March 14, 2016, 13:12: Stopped turbo pump |
Monday, March 14, 2016, 19:22, Aurelia Laxdal, Ta, 41790-1, LP-SIS, In progress, Ta#47 LP-SIS (with new center block) conditioning
|
Anders Mjos wrote: |
Laura Lambert wrote: |
Aurelia Laxdal wrote: |
Started Ta#47 heating at Evap2 using the autoramp program. The TGHT current is setup to go to 300A (for now) and the TBHT to 230A (final value).
|
Monday, March 14, 2016, 09:20
One thermocouple was not welded on correctly and is not working.
Cooling evap2 back down, to remove target and re-weld thermocouple.
Once thermocouple replaced, will ramp back up and continue with tests/ conditioning of target.
|
Monday, March 14, 2016, 13:12: Stopped turbo pump
|
After EVAP2 was vented the thermocouple problem was fixed: it was the wire at on connector inside the box not making proper contact. The lid of the heat shield was also replaced since the one initially mounted had no holes, so one couldn't see the center block. Restarted pumping down at 4:30pm. Just started again the autoramp program: TGHT set to 300A (for the time being) and TBHT to 230A. Temperature measurements will resume tomorrow morning. |
Friday, March 18, 2016, 17:13, Aurelia Laxdal, Ta, 41790-1, LP-SIS, In progress, Ta#47 LP-SIS (with new center block) conditioning
|
Aurelia Laxdal wrote: |
Anders Mjos wrote: |
Laura Lambert wrote: |
Aurelia Laxdal wrote: |
Started Ta#47 heating at Evap2 using the autoramp program. The TGHT current is setup to go to 300A (for now) and the TBHT to 230A (final value).
|
Monday, March 14, 2016, 09:20
One thermocouple was not welded on correctly and is not working.
Cooling evap2 back down, to remove target and re-weld thermocouple.
Once thermocouple replaced, will ramp back up and continue with tests/ conditioning of target.
|
Monday, March 14, 2016, 13:12: Stopped turbo pump
|
After EVAP2 was vented the thermocouple problem was fixed: it was the wire at on connector inside the box not making proper contact. The lid of the heat shield was also replaced since the one initially mounted had no holes, so one couldn't see the center block. Restarted pumping down at 4:30pm. Just started again the autoramp program: TGHT set to 300A (for the time being) and TBHT to 230A. Temperature measurements will resume tomorrow morning.
|
Raised the TGHT at 620A. The TBHT was already set at 230A. The temperature is at 1902 deg C. As per John's instructions the target will condition at these setpoints over the week-end. |
Monday, March 21, 2016, 18:57, Aurelia Laxdal, Ta, 41790-1, LP-SIS, In progress, Ta#47 LP-SIS (with new center block) conditioning
|
Aurelia Laxdal wrote: |
Aurelia Laxdal wrote: |
Anders Mjos wrote: |
Laura Lambert wrote: |
Aurelia Laxdal wrote: |
Started Ta#47 heating at Evap2 using the autoramp program. The TGHT current is setup to go to 300A (for now) and the TBHT to 230A (final value).
|
Monday, March 14, 2016, 09:20
One thermocouple was not welded on correctly and is not working.
Cooling evap2 back down, to remove target and re-weld thermocouple.
Once thermocouple replaced, will ramp back up and continue with tests/ conditioning of target.
|
Monday, March 14, 2016, 13:12: Stopped turbo pump
|
After EVAP2 was vented the thermocouple problem was fixed: it was the wire at on connector inside the box not making proper contact. The lid of the heat shield was also replaced since the one initially mounted had no holes, so one couldn't see the center block. Restarted pumping down at 4:30pm. Just started again the autoramp program: TGHT set to 300A (for the time being) and TBHT to 230A. Temperature measurements will resume tomorrow morning.
|
Raised the TGHT at 620A. The TBHT was already set at 230A. The temperature is at 1902 deg C. As per John's instructions the target will condition at these setpoints over the week-end.
|
Today, lowered the TGHT from 620A (at 1894 deg C) to 300A. TBHT is still at 230A. |
Tuesday, March 22, 2016, 11:31, Aurelia Laxdal, Ta, 41790-1, LP-SIS, In progress, Ta#47 LP-SIS (with new center block) conditioning
|
Aurelia Laxdal wrote: |
Aurelia Laxdal wrote: |
Aurelia Laxdal wrote: |
Anders Mjos wrote: |
Laura Lambert wrote: |
Aurelia Laxdal wrote: |
Started Ta#47 heating at Evap2 using the autoramp program. The TGHT current is setup to go to 300A (for now) and the TBHT to 230A (final value).
|
Monday, March 14, 2016, 09:20
One thermocouple was not welded on correctly and is not working.
Cooling evap2 back down, to remove target and re-weld thermocouple.
Once thermocouple replaced, will ramp back up and continue with tests/ conditioning of target.
|
Monday, March 14, 2016, 13:12: Stopped turbo pump
|
After EVAP2 was vented the thermocouple problem was fixed: it was the wire at on connector inside the box not making proper contact. The lid of the heat shield was also replaced since the one initially mounted had no holes, so one couldn't see the center block. Restarted pumping down at 4:30pm. Just started again the autoramp program: TGHT set to 300A (for the time being) and TBHT to 230A. Temperature measurements will resume tomorrow morning.
|
Raised the TGHT at 620A. The TBHT was already set at 230A. The temperature is at 1902 deg C. As per John's instructions the target will condition at these setpoints over the week-end.
|
Today, lowered the TGHT from 620A (at 1894 deg C) to 300A. TBHT is still at 230A.
|
Cooling down the target.
|
Thursday, March 24, 2016, 11:32, John Wong, Ta, 41790-1, LP-SIS, Done, Ta#47 LP-SIS (with new center block) conditioning
|
Aurelia Laxdal wrote: |
Aurelia Laxdal wrote: |
Aurelia Laxdal wrote: |
Aurelia Laxdal wrote: |
Anders Mjos wrote: |
Laura Lambert wrote: |
Aurelia Laxdal wrote: |
Started Ta#47 heating at Evap2 using the autoramp program. The TGHT current is setup to go to 300A (for now) and the TBHT to 230A (final value).
|
Monday, March 14, 2016, 09:20
One thermocouple was not welded on correctly and is not working.
Cooling evap2 back down, to remove target and re-weld thermocouple.
Once thermocouple replaced, will ramp back up and continue with tests/ conditioning of target.
|
Monday, March 14, 2016, 13:12: Stopped turbo pump
|
After EVAP2 was vented the thermocouple problem was fixed: it was the wire at on connector inside the box not making proper contact. The lid of the heat shield was also replaced since the one initially mounted had no holes, so one couldn't see the center block. Restarted pumping down at 4:30pm. Just started again the autoramp program: TGHT set to 300A (for the time being) and TBHT to 230A. Temperature measurements will resume tomorrow morning.
|
Raised the TGHT at 620A. The TBHT was already set at 230A. The temperature is at 1902 deg C. As per John's instructions the target will condition at these setpoints over the week-end.
|
Today, lowered the TGHT from 620A (at 1894 deg C) to 300A. TBHT is still at 230A.
|
Cooling down the target.
|
Thursday, March 24, 2016, 11:29
Target was removed from the Evaporator.
The thermocouples broke off.
Need to insert Re foil prior to installing
|
Tuesday, April 19, 2016, 09:28, Anders Mjos, Ta, 41790-1, LP-SIS, Done, Ta#47 LP-SIS (with new center block) conditioning 
|
John Wong wrote: |
Aurelia Laxdal wrote: |
Aurelia Laxdal wrote: |
Aurelia Laxdal wrote: |
Aurelia Laxdal wrote: |
Anders Mjos wrote: |
Laura Lambert wrote: |
Aurelia Laxdal wrote: |
Started Ta#47 heating at Evap2 using the autoramp program. The TGHT current is setup to go to 300A (for now) and the TBHT to 230A (final value).
|
Monday, March 14, 2016, 09:20
One thermocouple was not welded on correctly and is not working.
Cooling evap2 back down, to remove target and re-weld thermocouple.
Once thermocouple replaced, will ramp back up and continue with tests/ conditioning of target.
|
Monday, March 14, 2016, 13:12: Stopped turbo pump
|
After EVAP2 was vented the thermocouple problem was fixed: it was the wire at on connector inside the box not making proper contact. The lid of the heat shield was also replaced since the one initially mounted had no holes, so one couldn't see the center block. Restarted pumping down at 4:30pm. Just started again the autoramp program: TGHT set to 300A (for the time being) and TBHT to 230A. Temperature measurements will resume tomorrow morning.
|
Raised the TGHT at 620A. The TBHT was already set at 230A. The temperature is at 1902 deg C. As per John's instructions the target will condition at these setpoints over the week-end.
|
Today, lowered the TGHT from 620A (at 1894 deg C) to 300A. TBHT is still at 230A.
|
Cooling down the target.
|
Thursday, March 24, 2016, 11:29
Target was removed from the Evaporator.
The thermocouples broke off.
Need to insert Re foil prior to installing
|
Tuesday, April 19, 2016, 09:28: Uploaded thermoucouple data. |
Tuesday, February 09, 2021, 06:48, Aaron Schmidt, , NA, , Done, Ta coating test
|
Monday, February 08, 2021, 17:00: Installed brackets w/ Ta wire and a small piece of Re to test voltage drop.
Rough down, TP on. Waterlines open.
Tuesday, February 09, 2021, 06:44: Vacuum @ 8.63e-07T.
Tuesday, February 09, 2021, 06:45: Shut TP & roughing pump ff. Valves are close. Ready for power outage.
Tuesday, February 09, 2021, 11:30: BP1 & TP1 back on.
Tuesday, February 09, 2021, 11:37: PS on. Vacuum @ 9.7e-06T & continuing down.
micron slope 0.98
Tuesday, February 09, 2021, 16:01 Pressure 7.26e-7 Torr
aiming at a temperature of 2000 degC on the wire; wire is not in the visual range of pycnometer; simulations of the system indicate that wire will be at 2000 degC at 60 W, hence current will be increased slowly.
Rate: 0.1 A/60 s to 10 A
Tuesday, February 09, 2021, 16:47 Tendence showed that at 5 A the power will be ~10 W, final ramping step was updated accordingly.
Tuesday, February 09, 2021, 16:49 Pressure dropping a bit: Current reading 7e-7 Torr
Tuesday, February 09, 2021, 17:09Pressure going down, curent will be ramped down at 0.2 A/min
Pressure: 6.958e-7 Torr, TGHT: 5 A, 2.748 V, omega is reading 1625 degC somewhere somehow, wire will stay at this conditions for 10 min to see if there is a pressure or voltage change.
Tuesday, February 09, 2021, 17:16 voltage and temperature are slowly increasing 2.789 V, and 1688 degC respectively.
Tuesday, February 09, 2021, 17:32 Voltage signal is noisy but it seems like the voltage is not increasing anymore, preassure has remained constant, wire is glowing, 1100 degC with manual pyrometer.
Tuesday, February 09, 2021, 17:44 TGHT: 2.81 V, 4.95 A, IGP1 6.63e-7 Torr. current will be increased manually at 0.2 A steps. At first step voltage is stable.
Tuesday, February 09, 2021, 18:13 TGHT: 6.6A, 3.981V (~26W), Omega 1741 degC and manual pyrometer ~1300 degC
Tuesday, February 09, 2021, 18:28 TGHT: 8A, 5.121V (~40W), omega 1816 degc, 1390 degC with manual pyrometer, step changed to 0.4A.
Tuesday, February 09, 2021, 18:34 TGHT: 8.8A, 5.88V (50W), omega 2008 degC, 1500 manual pyrometer
Tuesday, February 09, 2021, 18:56 TGHT: 9.6A, 6.64V, manual pyrometer 1800 degC, omega 2042 degC, wire is shinny enough for micron 2092 degC.
Tuesday, February 09, 2021, 19:01TGHT: 10A, 7V, ~1800 degC manual pyrometer, omega 2123 degC, micron 2152 degC
Tuesday, February 09, 2021, 19:15 TGHT: 10.5A, 7.47V, 2150 degC Omega, 2165 degC, ~1800 degC manual
Tuesday, February 09, 2021, 19:23 TGHT: 11A, 7.93 V, 2188 omega, 2210 deC micron
Tuesday, February 09, 2021, 19:29 TGHT: 11.5A, 8.37V, 2188 omega, 2210 deC micron
Tuesday, February 09, 2021, 19:33 TGHT: 12A, 9V, 2325 degC, 1900 degC manual, the wire changed shape and the preassure increase a bit , micron was readjusted to read, micron 2454 degC. Wire might be touching tube, only one more amper will be imputed.
Tuesday, February 09, 2021, 19:55 TGHT 13A, 9.865 V, 2404 degC omega , 2558 degC micron, manual pyrometer still reads 1800 degC, pressure increased with the power increment, bbut it seems like the wire touching the tube so no more current will be imputed.
Tuesday, February 09, 2021, 20:08 started ramping at -0.2A/min
Wednesday, February 10th , 20211, 10:00 System unloaded from EVAP2, wire has straightened, it has not sintered to the copper brackets, system is clean there is no evidence of coating. |
Friday, March 07, 2014, 10:34, Anders Mjos, , , , Problems resolved, TGHT2 water flow signal
|
There was no signal going from the coils to the PLC. After manipulating the connection points on the coil a signal could again be established. Frequency is ~ 40Hz. |
Tuesday, November 04, 2014, 16:20, John Wong, SiC, , TARGET BOAT, In progress, TEST: Fabrication of SiC & Determine phase transformation 3C vs 6H
|
Tuesday, November 04, 2014, 16:08
The purpose of this experiment is to improve the fabrication of SiC. Previously, the SiC target was heated to 2000c and yellow crystals were observed.
In this experiment, 10g of SiC powder (7um size) was previously milled down (actual size to be determined under SEM). The powder was mixed with 5% PVA and the slurry was pour onto a glass and let dry. The semi-dry slurry was rolled up into balls. The SiC balls were let dry in over (115C) over night. Taken out 2.903g SiC + 5% PVA, it's rolled up with a small sheet of graphite foil. Then the targer boat is filled with the sample and wrapped with 3-layers of Ta-heat shield.
The sample will be heated up to 2000C to see if the yellow crystals are reproducible. It is suspected that there might be a phase transformation from 6H alpha-SiC to 3C beta-SiC.
Chamber is currently being pumped down...
Wednesday, November 05, 2014, 14:04
TGHT was ramped up over night, currently at 485A = 1800 C.
Will do manual step up to get to 2000C.
|
Wednesday, August 10, 2022, 09:31, Ivan Bao, Empty, , TARGET BOAT, In progress, TC tests
|
1st test polarity 1
10:12 am Begin pumping down to rough vacuum
12:50 pm begin ramping up towards 2000C. Ta tube only, welded thermocouple mount
3:08 Ta tube reached 2000C, began ramping down. The ramping up process was smooth and no hiccups happened
4:57 ramp down complete, began shutting down the evap2, will let the turbopump to slow down spin overnight.
2nd test polarity 2(swapped)
Tuesday, Aug 09 2022, 4pm begin pumping to vacuum after switching the polarity of the power supply
Wednesday, August 10, 2022, 13:09 begin ramping up
3:18 ramped to 671A. 2000C, no hiccups, everything is nominal. The thermocouple reads higher than before, about 20-30 deg C colder than pyro at high temperatures (1400C and above)
No bad connections, short circuits or unexpected overheating.
begin ramping down
ramping down was smooth, with error being the TC about 40 deg C colder than pyro at temp above 1500C
ramping done completed at Wednesday, August 10, 2022, 16:46 , shutting down evap 2 roughing and turbopump |
Tuesday, June 28, 2022, 09:31, Ferran Boix Pamies, Empty, 41882-2, TARGET BOAT, In progress, TC test on Ta tube
|
Tuesday, June 27, 2022, early afternoon: We assembled the setup in evap2 and started the pumps leaving it running over night.
Tuesday, June 28, 2022, 09:31 Turbo pump stopped for unknown reasons a few hours after we left. Restarting the pump.
Tuesday, June 28, 2022, 10:23 Vacuum down to 1e-5T start to ramp up TGHT 1A/10s to 200A.
Tuesday, June 28, 2022, 1:20 pm, Ramped from 0-500A. thermocouple reading 900C while pyrometer reads 1600C. begin ramping down to 0A. |
Thursday, August 04, 2022, 09:31, Ferran Boix Pamies, Empty, , TARGET BOAT, In progress, TC on Ta boat test.
|
11am: Setting up new target tube thermocouple test
Thursday, August 04, 2022, 09:31 Test finished August 3rd afternoon. Venting now.
|
|