127
|
Monday, February 29, 2016, 16:16 |
Laura Lambert | UC2 | 41077-1 | LP-SIS | Done | Conditioning UCx#15 |
John Wong wrote: |
Laura Lambert wrote: |
Thursday, February 18, 2016, 15:34
Target container was previously coated with TaC spray and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block - same method as for sintering TaC coating [new wrapping method-see elog112 eva2].
The target consists of 244 discs of UCx with 7.8cm in length.
A regular TaC coated endcap is inserted left, wrt the ionizer tube pointing down, so the right is open
The chamber is currently pumping down.
TGHT will be ramped up to 520A at 0.1A/min
Parameter setup: 5.0e-5 good vac, 6.0e-5 bad vac.
Friday, February 19, 2016, 08:28
IG1 = 4.7e-6 Torr
Tapped up manually to 35A.
Waited ~1hr, vacuum stable
IG1 = 3.8e-6 Torr.
Initiating auto-ramp.
|
Friday, February 26, 2016, 10:26
Target has been heated at 520A for 10 hrs.
Vacuum at 5.3e-6 Torr.
Initiated cool down at 1A/min.
Remember to vent with Ar.
|
Monday, February 29, 2016, 16:15
Vented in Ar.
Target removed from evap1 this morning.
Currently sitting in glovebox.
Weird red discharge on the end of the right side, inside the container [wrt ionizer tube into page] - same side with no endcap during carbonization.
Materials look good, both endcaps inserted.
Rh foil still needs to be implanted.
Wednesday, March 02, 2016, 10:13
The discoloration appears to be a simple change in the morphology of the TaC coating, future tests would need to be done to confirm this estimation.
This should not effect the container/ target.
See photo attached. |
Attachment 1: UCx_15.jpg
|
|
130
|
Tuesday, April 19, 2016, 10:48 |
Laura Lambert | UC2 | *** | | Done | ***ALL FUTURE UCx TARGETS*** | Tuesday, April 19, 2016, 09:47
Temperature measurements have been taken in evap2 on target containers.
Previously all UCx targets have been conditioned in evap1 at 520A. The respective target containers TaC coating was sintered in evap2 at a different current.
All future UCx targets will now be conditioned in evap1 at the same current required to reach 1900C in evap2 when sintering the TaC coating on the container to be used for the respective target.
ie. If a container is being sintered in evap2 at 450A [1900C], this same container is used for UCx - then that specific UCx target will be conditioned in evap1 at 450A.
Confirm full carbonization has been achieved by following with the vacuum on the strip tool and make sure the final vacuum comes down at the end of the whole process.
|
132
|
Wednesday, May 18, 2016, 15:15 |
Laura Lambert | UC2 | 40860-2 | LP-IG-LIS | Done | Conditioning UCx#16 | Wednesday, May 18, 2016, 15:05
Target container was previously coated with TaC spray and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block - new wrapping method-see elog112 evap2
The target consists of 200 discs of UCx with 7.4cm in length [4 packs of 5 + 180 single discs].
A regular TaC coated endcap is inserted left, wrt the ionizer tube pointing down.
The right side is open with a TaC coated spring to help hold materials in.
The chamber is currently pumping down.
TGHT will be ramped up to 460A at 0.1A/min [same current used to reach 1900C in evap2 when sintering TaC coating - elog291 evap2]
Parameter setup: 5.0e-5 good vac, 6.0e-5 bad vac.
Thursday, May 19, 2016, 09:25
IG1 = 3.4e-6 Torr
Tapped up manually to 35A
Vacuum stable.
IG1 = 3.5e-6 Torr.
Initiating auto-ramp.
Wednesday, May 25, 2016, 13:05
Target has been heated at 460A, 4.5V for 5 hrs.
Vacuum at 6.4e-6 Torr.
Initiated cool down at 1A/min.
Friday, May 27, 2016, 11:14
UCx done.
Vented in Ar and put in glove box yesterday.
Looked inside before inserting 2nd endcap - clean view all the way through the materials to the endcap/ not much visible shifting.
Ta coated spring helped hold materials in place.
Slightly darker markings on legs of container on side that was open in evap1.
2nd endcap put in.
Ready for assembly.
|
133
|
Monday, July 11, 2016, 16:00 |
Laura Lambert | UC2 | 41790-3 | LP-SIS | Done | Conditioning UCx#17 | Monday, July 11, 2016, 15:54
Target container was previously coated with TaC spray and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block - new wrapping method-see elog112 evap2
The target consists of 216 discs of UCx with 7.6cm in length [4 packs of 5 + 196 single discs].
A regular TaC coated endcap is inserted left, wrt the ionizer tube pointing down.
The right side is open with a TaC coated spring to help hold materials in.
The chamber is currently pumping down.
TGHT will be ramped up to 410A at 0.1A/min [same current used to reach 1900C in evap2 when sintering TaC coating - elog308 evap2]
Parameter setup: 5.0e-5 good vac, 6.0e-5 bad vac.
Tuesday, July 12, 2016, 08:50
IG1 = 5.3e-6 Torr
Tapped up manually to 35A
Vacuum stable.
IG1 = 5.25e-6 Torr.
Initiating auto-ramp.
Friday, July 15, 2016, 16:59
With evap2 not working, water was turned off to check valves...this tripped off evap1 since this also turned off the water to evap1.
TGHT was ~115A when evap1 tripped off.
Vacuum stable = 2.9e-6 Torr.
Tapped back up manually to 115A, 1.08V
Vacuum stable = 2.8e-6 Torr.
Restarting auto ramp at 0.1A/min.
Friday, July 22, 2016, 16:25
Target has remained at max setpoints for 4.5days.
TGHT = 410A, 3.99V
IG1 = 2.5e-6 Torr
Voltage has wavered a small amount, between 3,91V-4.02V; this can be seen in the photo attached of the screenshot of the striptool.
Conditioning process is now complete.
Initiating auto-cool at 1.0A/min
Tuesday, July 26, 2016, 16:48
Vented in Ar and currently transfering into glove box
will update elog tomorrow...
Wednesday, July 27, 2016, 14:56
had a few problems with the transfer chamber in the glove box, but managed to get the target into the glove box okay last night.
was exposed to oxygen for minimal amount of time - transfer chamber wasnt flushing properly/ leak in james bond box
|
Attachment 1: trip-off.JPG
|
|
Attachment 2: snapshot_of_striptool.JPG
|
|
138
|
Wednesday, October 19, 2016, 16:52 |
Laura Lambert | UC2 | 41790-6 | LP-SIS | Done | Conditioning UCx#18 | Wednesday, October 19, 2016, 16:47
Target container was previously coated with TaC spray and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block using one single foil/ layer
The target consists of 165 discs of UCx with 5.4cm in length
Materials: 4 packs of 5 {all made with 'modified' UC2cast} + 145 single discs{20 from 'modified cast'}
A regular TaC coated endcap is inserted left, wrt the ionizer tube pointing down.
The right side is open with a TaC coated spring to help hold materials in.
The chamber is currently pumping down.
TGHT will be ramped up to 430A at 0.1A/min [same current used to reach 1900C in evap2 when sintering TaC coating - elog327 evap2]
Parameter setup: 5.0e-5 good vac, 6.0e-5 bad vac.
Thursday, October 20, 2016, 10:11
Tapped up manually to 40A
Vacuum stable.
IG1 = 4.45e-6 Torr.
Initiating auto-ramp.
Monday, October 24, 2016, 11:19
TGHT = 254A, 2.46V
Still ramping up...~half way to final setpoint
Vacuum dropped, looks good, IG1 = 6.77e-6 Torr
Wednesday, October 26, 2016, 09:38
Target has remained at max setpoints for ~16hrs.
TGHT = 430A, 4.25V
IG1 = 2.3e-6 Torr
Conditioning/ re-carbonization process is now complete.
Initiating auto-cool at 1.0A/min
Thursday, October 27, 2016, 15:35
UCx done.
Vented in Ar and transferred to glove box.
Looked inside before inserting 2nd endcap - clean view all the way through the materials to the endcap/ no visible shifting.
Ta coated spring helped hold materials in place, materials expanded minimally ~0.5cm
Pushed materials back to desired length.
Successfully removed a single disc for further analysis.
Second endcap now in with 2x graphite foils.
Both endcaps need expanding.
Ready for assembly.
Requires Rh foil - to be inserted during assembly.
|
144
|
Thursday, February 16, 2017, 15:09 |
Laura Lambert | UC2 | 42218-12 | LP-SIS | Done | Conditioning UCx#19 | Thursday, February 16, 2017, 15:04
Target container was previously coated with TaC spray and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block
The target consists of 200 discs of UCx with 7.3cm in length [6 packs of 5 + 170 single discs].
Discs in target are arranged as follows: 5singles / 1pack / 40singles / 1pack / 40singles / 2packs / 40singles / 1pack / 40singles / 1pack / 5singles
A regular TaC coated endcap is inserted left, wrt the ionizer tube pointing down.
The right side is open with a TaC coated spring to help hold materials in.
The chamber is currently pumping down.
TGHT will be ramped up to 475A at 0.1A/min [same current used to reach 1900C in evap2 when sintering TaC coating - elog340 evap2]
Parameter setup: 5.0e-5 good vac, 6.0e-5 bad vac.
NOTE: small bug in evap1 IOC. when current is tapped up 1A, it auto-taps back down 0.01A. should be OK, but will keep an eye on evaporator during conditioning process and acct for changes.
Friday, February 17, 2017, 09:56
IG1 = 1.56e-6 Torr
Tapped up manually to 35A
Vacuum stable.
IG1 = 1.56e-6 Torr.
Initiating auto-ramp.
Friday, February 24, 2017, 15:09
Local TGHT 473 A 4.63 V
Monday, February 27, 2017, 09:06
Target has remained at max setpoints for 20+hrs [epics problems and archives currently not working so unable to find out exact time]
TGHT = 475A, 4.67V
IG1 = 1.48e-6 Torr
Conditioning process is now complete.
Initiating auto-cool at 1.0A/min
Tuesday, February 28, 2017, 12:00
UCx conditioning process complete.
Vented in Ar and transferred to glove box this morning.
Tuesday, April 11, 2017, 09:44
A few photos taken of the target post-conditioning.
Note a few flakes came out from one end - end disc from 'open' side flaked off.
|
Attachment 1: IMG_1578.JPG
|
|
Attachment 2: IMG_1587.JPG
|
|
Attachment 3: IMG_1594.JPG
|
|
Attachment 4: IMG_1598.JPG
|
|
146
|
Thursday, April 20, 2017, 11:41 |
Laura Lambert | UC2 | 42218-1 | LP-IG-LIS | Done | Conditioning UCx#20 | Thursday, April 20, 2017, 11:31
Target container was previously coated with TaC spray and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block
The target consists of 220 discs of UCx with 7.55cm in length [6 packs of 5 + 190 single discs].
Discs in target are arranged as follows: 1pack / 45singles / 1pack / 50singles / 2packs / 50singles / 1pack / 45singles / 1pack
A regular TaC coated endcap is inserted left, wrt the ionizer tube pointing down.
The right side is open with a TaC coated spring to help hold materials in.
The chamber is currently pumping down.
TGHT will be ramped up to 490A at 0.1A/min [same current used to reach 1900C in evap2 when sintering TaC coating - elog350 evap2]
Parameter setup: 5.0e-5 good vac, 6.0e-5 bad vac.
Friday, April 21, 2017, 10:14
IG1 = 2.47e-6 Torr
Tapped up manually to 35A.
Waited ~1.5hrs, vacuum stable IG1 = 2.37e-6 Torr
Initiating auto-ramp.
Thursday, April 27, 2017, 09:19
IG1 = 4.611e-6 Torr
TGHT = 490A, 4.93V
Target has remained at max setpoints for ~9hrs.
Initiating auto-cool at 1.0A/min
Tuesday, May 16, 2017, 13:21
Update:
Target looks good, see photos attached post sintering.
Gold tint on container commonly seen with the Uranium targets.
Orange colouring on inside of container end - also common.
Both endcaps in and handed off to assembly yesterday.
|
Attachment 1: 20170420_103410.jpg
|
|
Attachment 2: 20170420_103516.jpg
|
|
Attachment 3: 20170420_103154_Richtone(HDR).jpg
|
|
Attachment 4: 20170508_150816_Richtone(HDR).jpg
|
|
Attachment 5: 20170512_101150_Richtone(HDR).jpg
|
|
Attachment 6: 20170512_101348_Richtone(HDR).jpg
|
|
155
|
Wednesday, July 12, 2017, 17:07 |
Laura Lambert | UC2 | 42218-15 | LP-SIS | In progress | Conditioning UCx#21 | Wednesday, July 12, 2017, 17:06
Target container was previously coated with TaC and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block
The target consists of 400 discs of UCx with 13.60cm in length [8 packs of 5 + 360 single discs/ 2.6cm on left side, 2.8cm on right side wrt ionizer into page].
Discs in target are arranged as follows: 1pack / 60singles / 1pack / 60singles / 1pack / 60singles / 2packs / 60singles / 1pack / 60singles / 1pack / 60singles / 1pack
A regular TaC coated endcap is inserted left, wrt the ionizer tube pointing down.
The right side is open with a TaC coated spring to help hold materials in.
The chamber is currently pumping down.
TGHT will be ramped up to 450A at 0.1A/min [same current used to reach 1900C in evap2 when sintering TaC coating - elog373 evap2]
Parameter setup: 5.0e-5 good vac, 6.0e-5 bad vac.
Thursday, July 13, 2017, 12:49
Tapped up manually to 35A.
Waited ~2hrs, vacuum stable: IG1 = 2.64e-6 Torr
Initiating auto-ramp.
|
157
|
Thursday, July 13, 2017, 14:50 |
Laura Lambert | UC2 | 42218-15 | LP-SIS | Problems | Conditioning UCx#21 |
Laura Lambert wrote: |
Wednesday, July 12, 2017, 17:06
Target container was previously coated with TaC and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block
The target consists of 400 discs of UCx with 13.60cm in length [8 packs of 5 + 360 single discs/ 2.6cm on left side, 2.8cm on right side wrt ionizer into page].
Discs in target are arranged as follows: 1pack / 60singles / 1pack / 60singles / 1pack / 60singles / 2packs / 60singles / 1pack / 60singles / 1pack / 60singles / 1pack
A regular TaC coated endcap is inserted left, wrt the ionizer tube pointing down.
The right side is open with a TaC coated spring to help hold materials in.
The chamber is currently pumping down.
TGHT will be ramped up to 450A at 0.1A/min [same current used to reach 1900C in evap2 when sintering TaC coating - elog373 evap2]
Parameter setup: 5.0e-5 good vac, 6.0e-5 bad vac.
Thursday, July 13, 2017, 12:49
Tapped up manually to 35A.
Waited ~2hrs, vacuum stable: IG1 = 2.64e-6 Torr
Initiating auto-ramp.
|
Thursday, July 13, 2017, 14:48
Update: auto-ramp not started.
With recent updates to evap1 epics, not everything was uploaded correctly.
TGHT auto-ramp system not working: parameter boxes have white outline indicating locked.
No parameters can be inputed and therefore unable to start auto-ramp.
Friday, July 14, 2017, 15:56
Problems still not fixed.
Have tapped up manually to 50A, 0.59V
Vacuum stable; IG1 = 5.26e-6 Torr.
Will remain at setpoints over weekend before continuing to ramp up manually...
Monday, July 17, 2017, 15:10
New problems:
Paddle wheels for evap2 need replacing asap [see elog evap2 i.d.378]
In order to replace, supply/ return need to be turned off and a full purge; therefore, evap1 must be off otherwise it will trip off from no water.
Evap2 needs to be fixed asap and cannot wait for this process to be complete.
Evap1 had been tapped up manually to 60A.
Tapping down manually to 0A so one can start the paddle wheel replacement work tomorrow.
Tuesday, July 18, 2017, 15:31
Paddle wheels for evap2 replaced and up and running again.
IG1 = 1.2e-6 Torr.
Starting to tap back-up manually...
|
158
|
Wednesday, July 19, 2017, 14:15 |
Laura Lambert | UC2 | 42218-15 | LP-SIS | Problems resolved | Conditioning UCx#21 |
Laura Lambert wrote: |
Laura Lambert wrote: |
Wednesday, July 12, 2017, 17:06
Target container was previously coated with TaC and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block
The target consists of 400 discs of UCx with 13.60cm in length [8 packs of 5 + 360 single discs/ 2.6cm on left side, 2.8cm on right side wrt ionizer into page].
Discs in target are arranged as follows: 1pack / 60singles / 1pack / 60singles / 1pack / 60singles / 2packs / 60singles / 1pack / 60singles / 1pack / 60singles / 1pack
A regular TaC coated endcap is inserted left, wrt the ionizer tube pointing down.
The right side is open with a TaC coated spring to help hold materials in.
The chamber is currently pumping down.
TGHT will be ramped up to 450A at 0.1A/min [same current used to reach 1900C in evap2 when sintering TaC coating - elog373 evap2]
Parameter setup: 5.0e-5 good vac, 6.0e-5 bad vac.
Thursday, July 13, 2017, 12:49
Tapped up manually to 35A.
Waited ~2hrs, vacuum stable: IG1 = 2.64e-6 Torr
Initiating auto-ramp.
|
Thursday, July 13, 2017, 14:48
Update: auto-ramp not started.
With recent updates to evap1 epics, not everything was uploaded correctly.
TGHT auto-ramp system not working: parameter boxes have white outline indicating locked.
No parameters can be inputed and therefore unable to start auto-ramp.
Friday, July 14, 2017, 15:56
Problems still not fixed.
Have tapped up manually to 50A, 0.59V
Vacuum stable; IG1 = 5.26e-6 Torr.
Will remain at setpoints over weekend before continuing to ramp up manually...
Monday, July 17, 2017, 15:10
New problems:
Paddle wheels for evap2 need replacing asap [see elog evap2 i.d.378]
In order to replace, supply/ return need to be turned off and a full purge; therefore, evap1 must be off otherwise it will trip off from no water.
Evap2 needs to be fixed asap and cannot wait for this process to be complete.
Evap1 had been tapped up manually to 60A.
Tapping down manually to 0A so one can start the paddle wheel replacement work tomorrow.
Tuesday, July 18, 2017, 15:31
Paddle wheels for evap2 replaced and up and running again.
IG1 = 1.2e-6 Torr.
Starting to tap back-up manually...
|
Wednesday, July 19, 2017, 14:12
TGHT auto-ramp fixed.
Since TBHT isn't hooked up yet, epics thinks TBHT has tripped off.
Currently during auto-ramp, every time steps up: states TBHT tripped off.
This is not the case but not a big deal as we will soon have TBHT hooked up and this won't be an issue.
Also it only states it, doesn't stop auto-ramp and therefore technically works fine/ will go with this for now...
Note: Might be a few spikes on striptool from past hour when IOC was rebooted.
|
159
|
Wednesday, July 19, 2017, 14:17 |
Laura Lambert | UC2 | 42218-15 | LP-SIS | In progress | Conditioning UCx#21 |
Laura Lambert wrote: |
Laura Lambert wrote: |
Laura Lambert wrote: |
Wednesday, July 12, 2017, 17:06
Target container was previously coated with TaC and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block
The target consists of 400 discs of UCx with 13.60cm in length [8 packs of 5 + 360 single discs/ 2.6cm on left side, 2.8cm on right side wrt ionizer into page].
Discs in target are arranged as follows: 1pack / 60singles / 1pack / 60singles / 1pack / 60singles / 2packs / 60singles / 1pack / 60singles / 1pack / 60singles / 1pack
A regular TaC coated endcap is inserted left, wrt the ionizer tube pointing down.
The right side is open with a TaC coated spring to help hold materials in.
The chamber is currently pumping down.
TGHT will be ramped up to 450A at 0.1A/min [same current used to reach 1900C in evap2 when sintering TaC coating - elog373 evap2]
Parameter setup: 5.0e-5 good vac, 6.0e-5 bad vac.
Thursday, July 13, 2017, 12:49
Tapped up manually to 35A.
Waited ~2hrs, vacuum stable: IG1 = 2.64e-6 Torr
Initiating auto-ramp.
|
Thursday, July 13, 2017, 14:48
Update: auto-ramp not started.
With recent updates to evap1 epics, not everything was uploaded correctly.
TGHT auto-ramp system not working: parameter boxes have white outline indicating locked.
No parameters can be inputed and therefore unable to start auto-ramp.
Friday, July 14, 2017, 15:56
Problems still not fixed.
Have tapped up manually to 50A, 0.59V
Vacuum stable; IG1 = 5.26e-6 Torr.
Will remain at setpoints over weekend before continuing to ramp up manually...
Monday, July 17, 2017, 15:10
New problems:
Paddle wheels for evap2 need replacing asap [see elog evap2 i.d.378]
In order to replace, supply/ return need to be turned off and a full purge; therefore, evap1 must be off otherwise it will trip off from no water.
Evap2 needs to be fixed asap and cannot wait for this process to be complete.
Evap1 had been tapped up manually to 60A.
Tapping down manually to 0A so one can start the paddle wheel replacement work tomorrow.
Tuesday, July 18, 2017, 15:31
Paddle wheels for evap2 replaced and up and running again.
IG1 = 1.2e-6 Torr.
Starting to tap back-up manually...
|
Wednesday, July 19, 2017, 14:12
TGHT auto-ramp fixed.
Since TBHT isn't hooked up yet, epics thinks TBHT has tripped off.
Currently during auto-ramp, every time steps up: states TBHT tripped off.
This is not the case but not a big deal as we will soon have TBHT hooked up and this won't be an issue.
Also it only states it, doesn't stop auto-ramp and therefore technically works fine/ will go with this for now...
Note: Might be a few spikes on striptool from past hour when IOC was rebooted.
|
Wednesday, July 19, 2017, 14:16
Tapped up manually to 30A yesterday.
Continued manual tap up today and reached 60A.
Initiated auto-ramp.
IG1 = 4.4e-6 Torr
|
160
|
Thursday, July 20, 2017, 15:00 |
Laura Lambert | UC2 | 42218-15 | LP-SIS | Problems | Conditioning UCx#21 |
Laura Lambert wrote: |
Laura Lambert wrote: |
Laura Lambert wrote: |
Laura Lambert wrote: |
Wednesday, July 12, 2017, 17:06
Target container was previously coated with TaC and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block
The target consists of 400 discs of UCx with 13.60cm in length [8 packs of 5 + 360 single discs/ 2.6cm on left side, 2.8cm on right side wrt ionizer into page].
Discs in target are arranged as follows: 1pack / 60singles / 1pack / 60singles / 1pack / 60singles / 2packs / 60singles / 1pack / 60singles / 1pack / 60singles / 1pack
A regular TaC coated endcap is inserted left, wrt the ionizer tube pointing down.
The right side is open with a TaC coated spring to help hold materials in.
The chamber is currently pumping down.
TGHT will be ramped up to 450A at 0.1A/min [same current used to reach 1900C in evap2 when sintering TaC coating - elog373 evap2]
Parameter setup: 5.0e-5 good vac, 6.0e-5 bad vac.
Thursday, July 13, 2017, 12:49
Tapped up manually to 35A.
Waited ~2hrs, vacuum stable: IG1 = 2.64e-6 Torr
Initiating auto-ramp.
|
Thursday, July 13, 2017, 14:48
Update: auto-ramp not started.
With recent updates to evap1 epics, not everything was uploaded correctly.
TGHT auto-ramp system not working: parameter boxes have white outline indicating locked.
No parameters can be inputed and therefore unable to start auto-ramp.
Friday, July 14, 2017, 15:56
Problems still not fixed.
Have tapped up manually to 50A, 0.59V
Vacuum stable; IG1 = 5.26e-6 Torr.
Will remain at setpoints over weekend before continuing to ramp up manually...
Monday, July 17, 2017, 15:10
New problems:
Paddle wheels for evap2 need replacing asap [see elog evap2 i.d.378]
In order to replace, supply/ return need to be turned off and a full purge; therefore, evap1 must be off otherwise it will trip off from no water.
Evap2 needs to be fixed asap and cannot wait for this process to be complete.
Evap1 had been tapped up manually to 60A.
Tapping down manually to 0A so one can start the paddle wheel replacement work tomorrow.
Tuesday, July 18, 2017, 15:31
Paddle wheels for evap2 replaced and up and running again.
IG1 = 1.2e-6 Torr.
Starting to tap back-up manually...
|
Wednesday, July 19, 2017, 14:12
TGHT auto-ramp fixed.
Since TBHT isn't hooked up yet, epics thinks TBHT has tripped off.
Currently during auto-ramp, every time steps up: states TBHT tripped off.
This is not the case but not a big deal as we will soon have TBHT hooked up and this won't be an issue.
Also it only states it, doesn't stop auto-ramp and therefore technically works fine/ will go with this for now...
Note: Might be a few spikes on striptool from past hour when IOC was rebooted.
|
Wednesday, July 19, 2017, 14:16
Tapped up manually to 30A yesterday.
Continued manual tap up today and reached 60A.
Initiated auto-ramp.
IG1 = 4.4e-6 Torr
|
Thursday, July 20, 2017, 14:48
TGHT tripped off yesterday evening
Auto-ramping was fixed but a few more glitches in the system caused the TGHT to trip.
Please refer to photos.
When auto-ramp is running and vacuum reaches the parameter set for 'Good Vacuum', the auto-ramp should stop until the vacuum drops below the good vacuum at which point it can then continue to auto-ramp.
When auto-ramp is running and vacuum reaches the parameter set for 'Bad Vacuum', the auto-ramp should initiate auto-cool/ramp-down until the vacuum drops to the good vacuum parameter at which point it can then proceed with the 'Good Vacuum' requirement.
With this scenario, the auto-ramp system ignored the parameters set for good and bad vacuum, proceeded past both points and continued to ramp until the vacuum eventually reached it's trip off vacuum causing the TGHT to trip.
The TGHT current was at ~90A when it tripped off, so the target should be OK.
|
Attachment 1: Capture.JPG
|
|
Attachment 2: Capture3.JPG
|
|
161
|
Thursday, July 20, 2017, 15:35 |
Laura Lambert | UC2 | 42218-15 | LP-SIS | Problems resolved | Conditioning UCx#21 |
Laura Lambert wrote: |
Laura Lambert wrote: |
Laura Lambert wrote: |
Laura Lambert wrote: |
Laura Lambert wrote: |
Wednesday, July 12, 2017, 17:06
Target container was previously coated with TaC and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block
The target consists of 400 discs of UCx with 13.60cm in length [8 packs of 5 + 360 single discs/ 2.6cm on left side, 2.8cm on right side wrt ionizer into page].
Discs in target are arranged as follows: 1pack / 60singles / 1pack / 60singles / 1pack / 60singles / 2packs / 60singles / 1pack / 60singles / 1pack / 60singles / 1pack
A regular TaC coated endcap is inserted left, wrt the ionizer tube pointing down.
The right side is open with a TaC coated spring to help hold materials in.
The chamber is currently pumping down.
TGHT will be ramped up to 450A at 0.1A/min [same current used to reach 1900C in evap2 when sintering TaC coating - elog373 evap2]
Parameter setup: 5.0e-5 good vac, 6.0e-5 bad vac.
Thursday, July 13, 2017, 12:49
Tapped up manually to 35A.
Waited ~2hrs, vacuum stable: IG1 = 2.64e-6 Torr
Initiating auto-ramp.
|
Thursday, July 13, 2017, 14:48
Update: auto-ramp not started.
With recent updates to evap1 epics, not everything was uploaded correctly.
TGHT auto-ramp system not working: parameter boxes have white outline indicating locked.
No parameters can be inputed and therefore unable to start auto-ramp.
Friday, July 14, 2017, 15:56
Problems still not fixed.
Have tapped up manually to 50A, 0.59V
Vacuum stable; IG1 = 5.26e-6 Torr.
Will remain at setpoints over weekend before continuing to ramp up manually...
Monday, July 17, 2017, 15:10
New problems:
Paddle wheels for evap2 need replacing asap [see elog evap2 i.d.378]
In order to replace, supply/ return need to be turned off and a full purge; therefore, evap1 must be off otherwise it will trip off from no water.
Evap2 needs to be fixed asap and cannot wait for this process to be complete.
Evap1 had been tapped up manually to 60A.
Tapping down manually to 0A so one can start the paddle wheel replacement work tomorrow.
Tuesday, July 18, 2017, 15:31
Paddle wheels for evap2 replaced and up and running again.
IG1 = 1.2e-6 Torr.
Starting to tap back-up manually...
|
Wednesday, July 19, 2017, 14:12
TGHT auto-ramp fixed.
Since TBHT isn't hooked up yet, epics thinks TBHT has tripped off.
Currently during auto-ramp, every time steps up: states TBHT tripped off.
This is not the case but not a big deal as we will soon have TBHT hooked up and this won't be an issue.
Also it only states it, doesn't stop auto-ramp and therefore technically works fine/ will go with this for now...
Note: Might be a few spikes on striptool from past hour when IOC was rebooted.
|
Wednesday, July 19, 2017, 14:16
Tapped up manually to 30A yesterday.
Continued manual tap up today and reached 60A.
Initiated auto-ramp.
IG1 = 4.4e-6 Torr
|
Thursday, July 20, 2017, 14:48
TGHT tripped off yesterday evening
Auto-ramping was fixed but a few more glitches in the system caused the TGHT to trip.
Please refer to photos.
When auto-ramp is running and vacuum reaches the parameter set for 'Good Vacuum', the auto-ramp should stop until the vacuum drops below the good vacuum at which point it can then continue to auto-ramp.
When auto-ramp is running and vacuum reaches the parameter set for 'Bad Vacuum', the auto-ramp should initiate auto-cool/ramp-down until the vacuum drops to the good vacuum parameter at which point it can then proceed with the 'Good Vacuum' requirement.
With this scenario, the auto-ramp system ignored the parameters set for good and bad vacuum, proceeded past both points and continued to ramp until the vacuum eventually reached it's trip off vacuum causing the TGHT to trip.
The TGHT current was at ~90A when it tripped off, so the target should be OK.
|
Thursday, July 20, 2017, 15:14
Turns out the auto-ramp was reading the vacuum of 'IGP1' which is what the old ion gauge used to be called for evap1 and is currently one on evap2
AKA attempting to take a vacuum reading from one that doesn't exist for evap1
This ion gauge is now labelled 'IGP' and the auto-ramp system now uses 'IGP' for the vacuum parameter confirmations.
Changed a few things in the auto-ramp system:
-Updated messages.
-Auto-ramp aborts when TGHT/TBHT trips off.
-Displays setpoint it is ramping up to for next step
-Confirms which ion gauge it is reading
-Displays final setpoint and increment on message board
-No longer displays TBHT as 'tripped off' when not running.
System updated.
|
162
|
Thursday, July 20, 2017, 15:57 |
Laura Lambert | UC2 | 42218-15 | LP-SIS | Done | Conditioning UCx#21 |
Laura Lambert wrote: |
Laura Lambert wrote: |
Laura Lambert wrote: |
Laura Lambert wrote: |
Laura Lambert wrote: |
Laura Lambert wrote: |
Wednesday, July 12, 2017, 17:06
Target container was previously coated with TaC and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block
The target consists of 400 discs of UCx with 13.60cm in length [8 packs of 5 + 360 single discs/ 2.6cm on left side, 2.8cm on right side wrt ionizer into page].
Discs in target are arranged as follows: 1pack / 60singles / 1pack / 60singles / 1pack / 60singles / 2packs / 60singles / 1pack / 60singles / 1pack / 60singles / 1pack
A regular TaC coated endcap is inserted left, wrt the ionizer tube pointing down.
The right side is open with a TaC coated spring to help hold materials in.
The chamber is currently pumping down.
TGHT will be ramped up to 450A at 0.1A/min [same current used to reach 1900C in evap2 when sintering TaC coating - elog373 evap2]
Parameter setup: 5.0e-5 good vac, 6.0e-5 bad vac.
Thursday, July 13, 2017, 12:49
Tapped up manually to 35A.
Waited ~2hrs, vacuum stable: IG1 = 2.64e-6 Torr
Initiating auto-ramp.
|
Thursday, July 13, 2017, 14:48
Update: auto-ramp not started.
With recent updates to evap1 epics, not everything was uploaded correctly.
TGHT auto-ramp system not working: parameter boxes have white outline indicating locked.
No parameters can be inputed and therefore unable to start auto-ramp.
Friday, July 14, 2017, 15:56
Problems still not fixed.
Have tapped up manually to 50A, 0.59V
Vacuum stable; IG1 = 5.26e-6 Torr.
Will remain at setpoints over weekend before continuing to ramp up manually...
Monday, July 17, 2017, 15:10
New problems:
Paddle wheels for evap2 need replacing asap [see elog evap2 i.d.378]
In order to replace, supply/ return need to be turned off and a full purge; therefore, evap1 must be off otherwise it will trip off from no water.
Evap2 needs to be fixed asap and cannot wait for this process to be complete.
Evap1 had been tapped up manually to 60A.
Tapping down manually to 0A so one can start the paddle wheel replacement work tomorrow.
Tuesday, July 18, 2017, 15:31
Paddle wheels for evap2 replaced and up and running again.
IG1 = 1.2e-6 Torr.
Starting to tap back-up manually...
|
Wednesday, July 19, 2017, 14:12
TGHT auto-ramp fixed.
Since TBHT isn't hooked up yet, epics thinks TBHT has tripped off.
Currently during auto-ramp, every time steps up: states TBHT tripped off.
This is not the case but not a big deal as we will soon have TBHT hooked up and this won't be an issue.
Also it only states it, doesn't stop auto-ramp and therefore technically works fine/ will go with this for now...
Note: Might be a few spikes on striptool from past hour when IOC was rebooted.
|
Wednesday, July 19, 2017, 14:16
Tapped up manually to 30A yesterday.
Continued manual tap up today and reached 60A.
Initiated auto-ramp.
IG1 = 4.4e-6 Torr
|
Thursday, July 20, 2017, 14:48
TGHT tripped off yesterday evening
Auto-ramping was fixed but a few more glitches in the system caused the TGHT to trip.
Please refer to photos.
When auto-ramp is running and vacuum reaches the parameter set for 'Good Vacuum', the auto-ramp should stop until the vacuum drops below the good vacuum at which point it can then continue to auto-ramp.
When auto-ramp is running and vacuum reaches the parameter set for 'Bad Vacuum', the auto-ramp should initiate auto-cool/ramp-down until the vacuum drops to the good vacuum parameter at which point it can then proceed with the 'Good Vacuum' requirement.
With this scenario, the auto-ramp system ignored the parameters set for good and bad vacuum, proceeded past both points and continued to ramp until the vacuum eventually reached it's trip off vacuum causing the TGHT to trip.
The TGHT current was at ~90A when it tripped off, so the target should be OK.
|
Thursday, July 20, 2017, 15:14
Turns out the auto-ramp was reading the vacuum of 'IGP1' which is what the old ion gauge used to be called for evap1 and is currently one on evap2
AKA attempting to take a vacuum reading from one that doesn't exist for evap1
This ion gauge is now labelled 'IGP' and the auto-ramp system now uses 'IGP' for the vacuum parameter confirmations.
Changed a few things in the auto-ramp system:
-Updated messages.
-Auto-ramp aborts when TGHT/TBHT trips off.
-Displays setpoint it is ramping up to for next step
-Confirms which ion gauge it is reading
-Displays final setpoint and increment on message board
-No longer displays TBHT as 'tripped off' when not running.
System updated.
|
Thursday, July 20, 2017, 15:57
Tapped up manually to 35A, 0.45V
IG1 = 5.26e-6 Torr
Re-initiated auto-ramp at 0.1A/min.
Friday, July 21, 2017, 13:50
TGHT = 81A, 0.92V
IG1 = 5.2e-5 Torr
Vacuum currently yo-yo-ing, but stable.
Changing vacuum limits.
Vacuum limit stop at 1.0e-4 Torr, backing off at 5.0e-4 Torr.
TP = 28.4C, RT = 27.3C
Thursday, July 27, 2017, 09:02
TGHT = 431A, 4.37V
IG1 = 1.32e-5 Torr
Vacuum stable.
Increasing ramping rate to 0.2A/min
TP = 26.7C, RT = 22.0C
Friday, July 28, 2017, 09:35
TGHT = 450A, 4.59V
IG1 = 5.4e-6 Torr
Target has remained at max setpoint for 23hrs.
TP = 25.9C, RT = 19.5C
Initiating auto-cool at 1.0A/min
Friday, August 04, 2017, 13:59
Evap1 was vented in Ar and transferred to the glove box on monday.
A few discs on opened end had slightly shifted [see photo], discs moved back in place - can see down into target.
Discoloration of Ta container to gold in some spots - this is normal as seen with most UCx targets
Target looks good.
Still requires 2nd endcap to be inserted.
Monday, August 21, 2017, 11:13
Both endcaps in.
No Rh foil inserted.
Endcaps require expanding.
|
Attachment 1: IMG_3249.JPG
|
|
Attachment 2: IMG_3251.JPG
|
|
Attachment 3: IMG_3257.JPG
|
|
Attachment 4: IMG_3258.JPG
|
|
Attachment 5: IMG_3260.JPG
|
|
198
|
Tuesday, March 20, 2018, 14:52 |
Laura Lambert | UC2 | 42218-13 | LP-SIS | Done | Conditioning UCx#22 | Tuesday, March 20, 2018, 14:43
Target container was previously coated with TaC and sintered.
Container is wrapped with 3 layers of Ta-heat shield, including the center block
The target consists of 230 discs of UCx with 7.28cm in length [6 packs of 5 + 200 single discs].
Discs in target are arranged as follows: 1pack / 55singles / 1pack / 50singles / 2packs / 50singles / 1pack / 45singles / 1pack
A regular TaC coated endcap is inserted left, wrt the ionizer tube pointing down.
The right side is open with a TaC coated spring to help hold materials in.
An extra 5 single discs are loaded on the right side on top of the last pack, these discs will be removed after conditioning and analysed using SEM and XRD
The chamber is currently pumping down.
TGHT will be ramped up to 445A and TBHT will be ramped up to 230A [same parameters used to reach 1900C in evap2 when sintering TaC coating - elog402 evap2]
NOTE: This will be the first UCx target to go online using the TBHT in evap1 after the target is loaded with materials.
Wednesday, March 21, 2018, 09:37
IGP1 = 2.47e-6 Torr
Tapped up manually to 40A.
TGHT = 40A, 0.61V
TBHT = 40A, 0.78V
Waited ~1hr, vacuum stable IG1 = 9.3e-6 Torr
Initiating auto-ramp for TGHT at a rate of 0.2A/min
Initiating auto-ramp for TBHT at a rate of 0.1A/min
Parameter setup: 5.0e-5 good vac, 8.0e-5 bad vac.
Wednesday, March 21, 2018, 13:02
TGHT = 57A, 0.72V
TBHT = 48A, 0.85V
IG1 = 5.8e-5 Torr
Vacuum stable.
Changing vacuum limits.
Vacuum limit stop at 3.0e-4 Torr, backing off at 6.0e-4 Torr.
Monday, March 26, 2018, 09:32
TGHT = 450A, 4.54V
TBHT = 230A, 2.75V
IGP1 = 8.99e-7 Torr
Target has remained at max setpoint over weekend.
Initiating auto-cool at 1.0A/min for the TGHT and 0.5A/min for the TBHT.
Wednesday, March 28, 2018, 11:31
Evap1 was vented in Ar and transferred to the glove box yesterday.
Inspection of target still required as well as 2nd endcap to be inserted.
|
204
|
Friday, May 11, 2018, 12:36 |
Marla Cervantes | UC2 | 41369-2 | LP-SIS | Done | UCx Fully loaded graphite insert thermal test - FL#1 | Thursday, May 10, 2018, 16:00
Graphite insert fully loaded with UCx was loaded into previously TaC coated target container.
No end caps on Ta target container.
Weight of graphite tube + UCx discs = 27 g
Currently pumping down in evap1.
Friday, May 11, 2018, 11:41
IGP1 = 1.13e-6 Torr
Good vac at 3.0e-4, bad vac at 6.0e-4 Torr.
Tapped up manually to 100A.
Pressure increased to ~2e-5 Torr
Vacuum stabilized after 40 min
IGP1 = 1e-5 Torr
Initiating auto ramp for TGHT @ 20 A/min to a max setpoint of 520 A
Initiating auto ramp for TBHT @ 10 A/min to a max setpoint of 245 A
Preassure increased o 1e-4 Torr and the auto ramp was aborted
After 8 min IGP1 = 3e-5 Torr
Initiating auto ramp for TGHT @ 10 A/min to a max setpoint of 520 A
Initiating auto ramp for TBHT @ 5 A/min to a max setpoint of 245 A
The vacuum is more stable.
TBHT reached 230 A at 13:00
TGHT reached 520 A at 13:24
Final pressure 1.15e-4 Torr
Target will stay at max current point for a week.
Friday, May 18, 2018, 13:01
IGP1 = 8.03e-7 Torr
TGHT 5.67 V, 519.3 A
TBHT 2.59 V, 228.3 A
Initiation auto cool at TGHT -5 A/min
Initiation auto cool at TBHT -2 A/min
Friday, May 18, 2018, 13:58
Accelerating auto cool TGHT -10 A/min
Accelerating auto cool at TBHT -5 A/min
Friday, May 18, 2018, 18:31
Evap1 was vented in Ar and UCx target was transferred to the glove box |
Attachment 1: 180511-FL1_520A.png
|
|
207
|
Monday, June 04, 2018, 11:29 |
Marla Cervantes | UC2 | 40282-1 | TARGET BOAT | Done | Conditioning B13 and 2sc | Friday, June 01, 2018, 11:20
Target boat was previously coated with TaC and sintered.
Two small C-inserts of ~2cm length were placed on Ta boat
Sample 1-sc: 15 discs of cast 3 made with 1-step cast method (UCx+foil 1.437 g)
Sample 2-sc: 24 discs from rejected discs of 2-step casting (UCx+foil 1.585 g)
Ta boat was wrapped with 3 layers of Ta-heat shield
The chamber is currently pumping down.
TGHT will be ramped up to 495A [same parameters used to reach 1910C in evap2 when sintering TaC coating - elog410 evap2]
Monday, June 04, 2018, 11:27
IG1 = 4e-7 Torr
Tapped up manually to 35A
Waited 1hr
Vacuum stable.
IG1 = 8.02e-7 Torr.
Initiating auto-ramp (0.1 A/min) up to 80 A
Tuesday, June 07, 2018, 15:47
Vacuum stable
IG1 = 7.02e-7 Torr.
Changing auto-ramp to 0.02 A/min up to 140 A
Thursday, June 07, 2018, 15:49
Vacuum stable 5.5e-7 Torr
Current 139 A, voltage 1.25 V
Changing auto-ramp to 0.1 A/min up to 495
Saturday, June 9, 2018, 10:41
The material stayed 4 hours at 495 A
Auto-ramp set to -1 A/min down to 0 A
Monday, June 11, 2018, 17:43
EVAPI was vented with Ar and UCx was transferred to glove box
|
213
|
Thursday, July 05, 2018, 13:43 |
John Wong | UC2 | | HP-FEBIAD-CTL | Done | Conditioning UCx#23 | Thursday, July 05, 2018, 13:24
Target container was previously coated and sintered with TaC, also wrapped with Ta heat shields (see Evap2 elog# 410).
Loaded 201 discs of UCx with 7.27 cm in length + 5 extra discs for QC samples.
One end-cap (coated/sintered TaC) inserted right, wrt the ionizer tube pointing down.
Left side is OPEN; a spring is inserted to hold the discs in place.
Chamber is currently being pumped down.
TGHT will be ramped up to 495A/8.85V and TBHT to 230A/3.26V (same parameters used for sintering the container, evap2 elog#410).
Vacuum initial setting:
Good Vac = 5.0 e-5 Torr, Bad vac = 8.0 e-5 Torr.
pressure level will be monitored accordingly...
Auto-ramping setting
TGHT: 60 wait time, 0.2A/min, final 495A
TGHT: 60 wait time, 0.2A/min, final 230A.
Thursday, July 05, 2018, 16:50
Tapping up TGHT to 40 A/0.49 V and TGHT to 40A/0.64V.
Vac slowly increasing from 5.0 e-6 Torr.
Initiate auto-heating
Tuesday, July 10, 2018, 10:46
Holding TGHT at 495A/5.3V for over 25 hours. Pressure at 2.9e-6 Torr.
Initiate autocooling TGHT at 2A/min, TBHT 1.0A/min
Wednesday, July 11, 2018, 17:12
Target was removed from the Evap; it is now in the Ar glovebox. End cap is inserted.
Target is ready for installation.
|
215
|
Friday, August 03, 2018, 17:49 |
John Wong | UC2 | | LP-SIS | In progress | Conditioning UCx#24 | Friday, August 03, 2018, 17:44
Target consists of 230 UCx discs, total packing length of 7.1cm.
Container was previously coated/sintered with TaC (see elog #415) in Evap#2 with TGHT set to 450A/7.5V and TBHT 230A/4.2
Vacuum initial setting:
Good Vac = 5.0 e-5 Torr, Bad vac = 8.0 e-5 Torr.
pressure level will be monitored accordingly...
Auto-ramping setting
TGHT: 60 wait time, 0.2A/min, final 450A
TGHT: 60 wait time, 0.2A/min, final 230A.
Chamber is currently being pumped down.Good
Monday, August 06, 2018, 00:04
Pressure at 3.6e-6 Torr.
Initiate autoramping.
Friday, August 10, 2018, 11:02
TGHT/TBHT have been at 450A(4.5V)/230A(2.9) for over 15 hours.
Pressure is stabilized at 5.2e-6 Torr.
Initiated auto-cooling at 2A/min for TGHT and 1A/min for TBHT.
|
216
|
Friday, August 17, 2018, 11:23 |
Marla Cervantes | UC2 | NA | | Done | UCx 1-step casting -Oxidation test | Friday, August 17, 2018, 11:17
Four discs of UCx produced with the 1-step casting method were placed in a glass jar.
The mass of the discs was 0.400 g.
The glass jar with the discs were placed in the heating chamber of the IEVAP.
Currently IEVAP is pumping down until vacuum is in the order of ~10^-6 Torr.
Friday, August 17, 2018, 16:28
Final vacuum: 9.5x10^-6 Torr
IEVAP's heating chamber will be vented with air and the materials will be taken out.
Friday, August 17, 2018, 17:27
Material was transferred to the glove box
|
|