  288   Thursday, January 19, 2023, 10:02 Darwin Ortiz RosalesUO2/C LP TUBEDoneC230105 ReductionThursday, January 19, 2023, 09:57
Cartridge #8 loaded with 198 discs
To be reduced inside a Ta container
  
  289   Wednesday, March 22, 2023, 22:29 Darwin Ortiz RosalesUO2/C LP TUBEDone230316 ReductionWednesday, March 22, 2023, 22:29
Cartridge #9 loaded with 213 plus
3 analysi discs
  
  290   Wednesday, October 11, 2023, 10:06 Darwin Ortiz RosalesUO2/C LP TUBEDoneTUCx-231005 reduction & conditioningWednesday, October 11, 2023, 9:36
Cartridge #10 loaded with 213 plus
3 analysi discs
  
  292   Thursday, September 12, 2024, 06:23 Darwin Ortiz RosalesUO2/C LP TUBEDoneUCx240904 reduction
Thursday, September 12, 2024, 06:19
Cartridge #19 loaded with 232 discs
including 5 analysis discs
  
  293   Tuesday, September 17, 2024, 06:49 Darwin Ortiz RosalesUO2/C LP TUBEDoneUCx240916 reductionTuesday, September 17, 2024, 06:45
Cartridge #20 loaded with 224 discs
plus 3 analysis discs
  
  294   Thursday, September 19, 2024, 22:48 Darwin Ortiz RosalesUO2/Cconditioning oven#3LP TUBEDoneUCx240917 reductionThursday, September 19, 2024, 22:44
 
Cartridge #21 loaded with 211 discs
  
  295   Tuesday, January 14, 2025, 16:28 Darwin Ortiz RosalesUO2/Cconditioning oven#3LP TUBEIn progressUCx250113 reductionTuesday, January 14, 2025, 16:26
 
Cartridge #22 loaded with 211 discs
  
  45   Tuesday, February 14, 2012, 21:56 John WongUO238481-9LP-FEBIADDoneUO2/Nb sintering process Tuesday, February 14, 2012, 20:58
Evaporator is setup for UO2/Nb sintering
process.  
 Screen_shot_2012-02-14_at_9.00.04_PM.pngUO2_Nb_1_striptool.jpg 
  291   Tuesday, April 09, 2024, 14:43 Darwin Ortiz RosalesUO2 LP TUBEDoneUCx240408 reduction Tuesday, April 09, 2024, 14:42
Cartridge #16 loaded with 213 plus
3 analysi discs
  
  26   Wednesday, July 27, 2011, 13:02 John WongUC238634-3LP-SISProblemsUCx#2 conditioning Wednesday, July 27, 2011, 12:58: 
Target length = 11.2cm
Total UC2/C foils = 245 discs
 striptool_july31.pngTarget_with_3_heat_shields.jpgstriptool_july31_600A.jpgUCx#2-conditioning.jpg 
  28   Thursday, August 04, 2011, 17:46 John WongUC238634-8LP-SISProblems resolvedRepacking UCx in new target ovenThursday, August 04, 2011, 17:44: 
All the UCx material from target oven  38634-3
was recovered and repacked in this new oven. 
 200A.jpgreconditioning.jpg 
  43   Thursday, November 03, 2011, 09:24 John WongUC238634-10LP-SISDoneUCx#3: Final conditioning Thursday, November 03, 2011, 08:59
Target was previously coated/sintered
with TaC & wrapped with 3 Ta-heat shields,
 auto_heating_failed.jpgEvap1_TGHT_problem.jpgEvpr_org_burnout_01.jpgEvpr_org_burnout.jpgarchive_overall_process.JPG 
  44   Monday, November 14, 2011, 11:56 Peter Kunz UC238634-10LP-SISDoneUCx03: Conditioning up to 175AEvaporator was cleaned Nov 11 from after
target was conditioned up to 175A. There
was significant condensation of oily fluid
 0--0009.jpg0--0011.jpg 
  55   Tuesday, July 10, 2012, 12:54 John WongUC238634-9LP-SISDoneUCx#4 final conditioning completedTuesday, July 10, 2012, 12:44
Target contains 230 discs of UCx
(material from UC2 flakes, batch#01-04062012). 
 TGHT_0-175_orgburnoff.GIFUCx#4_final_conditioning_0-520A.PNG 
  57   Friday, August 24, 2012, 16:44 John WongUC239165-5LP-SISIn progressConditioning UCx#5Friday, August 24, 2012, 16:40
Target is loaded with 245 discs of
UCx (material from batch#02-13062012),
  
  58   Monday, September 03, 2012, 02:56 Peter Kunz UC239165-5LP-SISIn progressConditioning UCx05Organic/volatile burnoff complete at TGHT
= 190A. Rampdown initiated.
  
  59   Tuesday, September 04, 2012, 17:26 Peter Kunz UC239165-5LP-SISIn progressConditioning UCx05Organic gunk cleaned out. Beginning 2nd phase
of conditioning.
  
  60   Friday, September 07, 2012, 17:21 Peter Kunz UC239165-5LP-SISIn progressConditioning UCx05Target 6h at 520A. IEVAP:IG1 8.4e-6 Torr.
Cool down sequence initiated.
  
  61   Monday, September 10, 2012, 11:00 Peter Kunz UC239165-5LP-SISIn progressConditioning UCx05Plot of conditioning run: IEVAP:IG1, TGHT  UC2_05_conditioning.png 
  65   Thursday, May 30, 2013, 16:25 John WongUC239165-6LP-SISDoneConditioning UCx#06Thursday, May 30, 2013, 16:16
The target container was previously
coated with TaC and sintered in Evap 2.
 UCx#6_conditioning_stage1.PNG 