Entry  Thursday, January 19, 2023, 10:02, Darwin Ortiz Rosales, UO2/C, , LP TUBE, Done, C230105 Reduction 
Thursday, January 19, 2023, 09:57
Cartridge #8 loaded with 198 discs
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields.
Entry  Wednesday, March 22, 2023, 22:29, Darwin Ortiz Rosales, UO2/C, , LP TUBE, Done, 230316 Reduction 
Wednesday, March 22, 2023, 22:29
Cartridge #9 loaded with 213 plus 3 analysi discs
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields.
Entry  Wednesday, October 11, 2023, 10:06, Darwin Ortiz Rosales, UO2/C, , LP TUBE, Done, TUCx-231005 reduction & conditioning 
Wednesday, October 11, 2023, 9:36
Cartridge #10 loaded with 213 plus 3 analysi discs
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields.
Entry  Thursday, September 12, 2024, 06:23, Darwin Ortiz Rosales, UO2/C, , LP TUBE, Done, UCx240904 reduction 

Thursday, September 12, 2024, 06:19
Cartridge #19 loaded with 232 discs including 5 analysis discs
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields.
Entry  Tuesday, September 17, 2024, 06:49, Darwin Ortiz Rosales, UO2/C, , LP TUBE, Done, UCx240916 reduction 
Tuesday, September 17, 2024, 06:45
Cartridge #20 loaded with 224 discs plus 3 analysis discs
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields.
Entry  Thursday, September 19, 2024, 22:48, Darwin Ortiz Rosales, UO2/C, conditioning oven#3, LP TUBE, Done, UCx240917 reduction 
Thursday, September 19, 2024, 22:44
 
Cartridge #21 loaded with 211 discs including 3 analysis discs
Entry  Tuesday, January 14, 2025, 16:28, Darwin Ortiz Rosales, UO2/C, conditioning oven#3, LP TUBE, In progress, UCx250113 reduction 
Tuesday, January 14, 2025, 16:26
 
Cartridge #22 loaded with 211 discs including 3 analysis discs
Entry  Tuesday, February 14, 2012, 21:56, John Wong, UO2, 38481-9, LP-FEBIAD, Done, UO2/Nb sintering process Screen_shot_2012-02-14_at_9.00.04_PM.pngUO2_Nb_1_striptool.jpg
 Tuesday, February 14, 2012, 20:58
Evaporator is setup for UO2/Nb sintering process.  
Target oven filled with 402 discs of UO2/Nb, 5.0cm in length with tot mass of 61.49g. 
Entry  Tuesday, April 09, 2024, 14:43, Darwin Ortiz Rosales, UO2, , LP TUBE, Done, UCx240408 reduction 
 Tuesday, April 09, 2024, 14:42
Cartridge #16 loaded with 213 plus 3 analysi discs
To be reduced inside a Ta container tube.  Tube wrapped in 3 Ta foil heatshields.
Entry  Wednesday, July 27, 2011, 13:02, John Wong, UC2, 38634-3, LP-SIS, Problems, UCx#2 conditioning  striptool_july31.pngTarget_with_3_heat_shields.jpgstriptool_july31_600A.jpgUCx#2-conditioning.jpg
Wednesday, July 27, 2011, 12:58: 
Target length = 11.2cm
Total UC2/C foils = 245 discs
Entry  Thursday, August 04, 2011, 17:46, John Wong, UC2, 38634-8, LP-SIS, Problems resolved, Repacking UCx in new target oven 200A.jpgreconditioning.jpg
Thursday, August 04, 2011, 17:44:  All the UCx material from target oven  38634-3 was recovered and repacked in this new oven.  Total mass
recovered = 45.911g and packed in 10.7cm length.  Target is currently being pumped down. 
Thursday, August 04, 2011, 20:23:  Current vac 5.6e-6 Torr.  Stepping up TGHT to 104A, vac increasing slowly.  Being auto heating
Entry  Thursday, November 03, 2011, 09:24, John Wong, UC2, 38634-10, LP-SIS, Done, UCx#3: Final conditioning auto_heating_failed.jpgEvap1_TGHT_problem.jpgEvpr_org_burnout_01.jpgEvpr_org_burnout.jpgarchive_overall_process.JPG
 Thursday, November 03, 2011, 08:59
Target was previously coated/sintered with TaC & wrapped with 3 Ta-heat shields, including the back-block. 
Target was loaded with 365 UC2 discs + 3 samples for analysis. 
Entry  Monday, November 14, 2011, 11:56, Peter Kunz , UC2, 38634-10, LP-SIS, Done, UCx03: Conditioning up to 175A 0--0009.jpg0--0011.jpg
Evaporator was cleaned Nov 11 from after target was conditioned up to 175A. There was significant condensation of oily fluid on the left side where the
target container was open (D-shaped end cap). There were also deposits in the hole for the ionizer, but the ionizer itself seemed to be clean.
Entry  Tuesday, July 10, 2012, 12:54, John Wong, UC2, 38634-9, LP-SIS, Done, UCx#4 final conditioning completed TGHT_0-175_orgburnoff.GIFUCx#4_final_conditioning_0-520A.PNG
Tuesday, July 10, 2012, 12:44
Target contains 230 discs of UCx (material from UC2 flakes, batch#01-04062012). 
Total UCx mass (UC2 + C-grv extra + C-foil + Org.) = 38.564g
Entry  Friday, August 24, 2012, 16:44, John Wong, UC2, 39165-5, LP-SIS, In progress, Conditioning UCx#5 
Friday, August 24, 2012, 16:40
Target is loaded with 245 discs of UCx (material from batch#02-13062012),
Tot length = 9.1 cm. 
Entry  Monday, September 03, 2012, 02:56, Peter Kunz , UC2, 39165-5, LP-SIS, In progress, Conditioning UCx05 
Organic/volatile burnoff complete at TGHT = 190A. Rampdown initiated.
Entry  Tuesday, September 04, 2012, 17:26, Peter Kunz , UC2, 39165-5, LP-SIS, In progress, Conditioning UCx05 
Organic gunk cleaned out. Beginning 2nd phase of conditioning.
Entry  Friday, September 07, 2012, 17:21, Peter Kunz , UC2, 39165-5, LP-SIS, In progress, Conditioning UCx05 
Target 6h at 520A. IEVAP:IG1 8.4e-6 Torr. Cool down sequence initiated.
Entry  Monday, September 10, 2012, 11:00, Peter Kunz , UC2, 39165-5, LP-SIS, In progress, Conditioning UCx05 UC2_05_conditioning.png
Plot of conditioning run: IEVAP:IG1, TGHT
Entry  Thursday, May 30, 2013, 16:25, John Wong, UC2, 39165-6, LP-SIS, Done, Conditioning UCx#06 UCx#6_conditioning_stage1.PNG
Thursday, May 30, 2013, 16:16
The target container was previously coated with TaC and sintered in Evap 2.
The target is loaded with 250 discs of UCx (material from batch#03_02042013)