23
|
Wednesday, May 25, 2011, 14:42 |
John Wong | UO2/C | UCx-heatboat#1 | LP-SIS | Done | Batch#1: UO2/C mixing & carbonization | Before began the carbonization process,
two cameras were setup in the hotlab for
monitoring the evaporator and the power supply. |
|
|
24
|
Thursday, June 30, 2011, 12:42 |
John Wong | UO2/C | UCx-heatboat#1 | LP-SIS | Done | Batch#2: UO2/C for carbonization | Before began the
carbonization process, two cameras were setup |
|
|
41
|
Thursday, September 29, 2011, 10:58 |
John Wong | UO2/C | UCx-heatboat#2 | | Done | UCx#3: Batch#1 - UO2/C mixture of carbonization | Thursday, September 29, 2011, 10:54
UO2/C mixture was made on Tuesday
Sept 27, casted on a piece of glass and let |
6x |
|
42
|
Thursday, October 06, 2011, 12:22 |
John Wong | UO2/C | UCx-heatboat#2 | | Done | UCx#3: Batch#2 - UO2/C mixture of carbonization | Thursday, October 06, 2011, 12:19
|
|
|
49
|
Wednesday, June 06, 2012, 16:58 |
John Wong | UO2/C | UCx-heatboat#2 | | Done | UC2 flakes for UCx#4: batch#01-04062012 | Wednesday, June 06, 2012, 16:55
The UO2/C green was prepared on June
04, 2012. |
7x |
|
50
|
Monday, June 11, 2012, 10:48 |
John Wong | UO2/C | UCx-heatboat#2 | | Problems | UC2 flakes - batch#01-04062012: broken seal & TGHT power supply |
|
|
|
51
|
Tuesday, June 12, 2012, 11:38 |
John Wong | UO2/C | UCx-heatboat#2 | | Problems resolved | UC2 flakes - batch#01-04062012: broken seal & TGHT power supply |
|
|
|
53
|
Sunday, June 24, 2012, 22:52 |
John Wong | UO2/C | UCx-heatboat#2 | | Problems | UC2 flakes - batch#01-04062012: IOC problems |
|
|
|
54
|
Monday, June 25, 2012, 16:00 |
John Wong | UO2/C | UCx-heatboat#2 | | Problems resolved | UC2 flakes - batch#01-04062012: Fiber converters failed |
|
|
|
56
|
Thursday, July 19, 2012, 17:14 |
John Wong | UO2/C | Target boat #2 | | Done | Processing UC2 flakes for UCx#5 - (batch#02-13062012) | Thursday, July 19, 2012, 17:09
UO2/C green was prepared on June
13, 2012. |
|
|
63
|
Tuesday, April 02, 2013, 17:46 |
John Wong | UO2/C | Target boat #2 | | Done | Processing UC2 flakes for UCx#6 (batch#03 - 02042013) | Tuesday, April 02, 2013, 17:25
UO2/C green was prepared on Mar 11,
2013. |
|
|
64
|
Monday, May 06, 2013, 14:34 |
John Wong | UO2/C | Target boat #2 | | Done | Processing UC2 flakes (batch#04 - 05032013) | Monday, May 06, 2013, 14:29
UO2/C green was prepared on May 2,
2013 and let dry over the weekend. |
|
|
68
|
Tuesday, June 25, 2013, 14:49 |
Laura Lambert | UO2/C | Target boat #2 | | Done | Processing UC2 flakes (batch#05 - 18062013) | Tuesday, June 25, 2013, 14:35
UO2/C green was prepared on June
18, 2013 and let dry over the weekend. |
|
|
69
|
Tuesday, June 25, 2013, 16:28 |
John Wong | UO2/C | Target boat #2 | | Done | Processing UC2 flakes (batch#05 - 18062013) |
|
|
|
70
|
Tuesday, July 02, 2013, 11:13 |
Peter Kunz | UO2/C | Target boat #2 | | Done | Processing UC2 flakes (batch#05 - 18062013) |
1. stage - burning off organics complete
2. stage - carbonization began 1-8 |
|
|
71
|
Thursday, July 11, 2013, 16:22 |
John Wong | UO2/C | Target boat #2 | | Done | Processing UC2 flakes (batch#05 - 18062013) |
|
|
|
72
|
Monday, July 15, 2013, 09:45 |
John Wong | UO2/C | Target boat #2 | | Done | Processing UC2 flakes (batch#05 - 18062013) |
|
|
|
75
|
Thursday, August 22, 2013, 18:00 |
John Wong | UO2/C | Target Boat #2 | | Done | Processing UC2 flaskes (batch#06 - 08222013 | Thursday, August 22, 2013, 17:31
1st attempt:
UO2/C green was prepared on Aug 14, |
|
|
76
|
Friday, August 23, 2013, 16:11 |
John Wong | UO2/C | Target Boat #2 | | Problems resolved | Processing UC2 flaskes (batch#06 - 08222013 |
|
|
|
77
|
Tuesday, September 10, 2013, 12:20 |
Laura Lambert | UO2/C | Target Boat #2 | | Done | Processing UC2 flaskes (batch#06 - 08222013 |
|
|