  29   Friday, January 20, 2012, 10:37 Friedhelm Ames       vacuum pumps shut offturbo pumps shut off due to work on
cooling water system
  
  254   Wednesday, December 19, 2012, 09:44 Sebastian Raeder      In progressventingventing and inspect the target
Wednesday, December 19, 2012, 09:43:
vqacuum at 1.9E-7T, stop turbos
  
  57   Wednesday, March 07, 2012, 09:27 Friedhelm AmesNb#6     Donewater cooling startedwater cooling line valves opened. No response
on vacuum TSG:IG1 3.5e-7 T
  
  124   Wednesday, July 04, 2012, 13:07 Anders Mjos      Problems/Solutionswater lines purged

    

       
            
  
  128   Thursday, July 05, 2012, 10:59 Friedhelm Ames      Problems/Solutionswater tripping in front of HV power suppliesFound some water tripping in front of the
high voltage power supplies rack from the
water lines at the ceiling. Plastic sheets
  
  251   Monday, December 17, 2012, 22:35 Sebastian RaederRFQ empty      wire connection for RFQ testOverview over the connections of the new
9Pin connector inside the vacuum and in the
HV cage
  
  915   Monday, April 04, 2022, 20:56 Carla Babcock       wiring reverted for cathode-bias FEBIADWiring which was changed to run the mass
marker tests has been reverted:

    anode bias cable connected
  
ELOG V2.9.2-2455