ID Date Author Target/No.# Source Stationdown Module Target Oven W.O# Heat Shield W.O# Status Subject Text Attachments
  2   Wednesday, September 14, 2011, 15:33 John WongTest#1HP-SISITWTM1testtestIn progresstesting elog for test standWednesday, September 14, 2011, 15:33
blah blah blah...
  
  72   Monday, April 16, 2012, 11:16 Anders MjosNb#6LP-SISITWTM1  In progressVenting, purging cooling linesVenting chamber and purging cooling lines
in preparation for target removal
  
  73   Monday, April 16, 2012, 11:56 Anders MjosNb#6LP-SISITWTM1  In progressVenting, purging cooling lines

    

       
            
  
  77   Friday, April 20, 2012, 08:56 Anders MjosNb#6LP-SISITWTM1  Problems/SolutionsInsulator stand-off failure When the target was removed from
the test stand it was discovered that the
custom designed insulator stand-off (ITD0400
 ITW-TM1-Nb#6-LP-SIS_-_TestStand.pdf 
  101   Thursday, May 31, 2012, 15:43 Anders MjosTa#38LP-SISITWTM1  In progressTarget ready to be heatedThursday, May 31, 2012, 15:42: Roughing
Thursday, May 31, 2012, 16:01 : Starting
turbos
  
  102   Friday, June 01, 2012, 12:23 Aurelia LaxdalTa#38LP-SISITWTM1  In progressHV & Heaters conditioning.Did the HV conditioning.
Heaters conditioning in progress.
The Hall probe is not working: couldn't
  
  103   Monday, June 04, 2012, 10:51 Anders MjosTa#38LP-SISITWTM1  DoneVenting chamber

    

       
            
  
  192   Friday, August 31, 2012, 13:59 Anders MjosNb#7LP-SISITWTM1  In progressNb#7 installedFriday, August 31, 2012, 15:19: roughing
Friday, August 31, 2012, 15:39 :
starting turbos
  
  193   Tuesday, September 04, 2012, 08:11 Anders MjosNb#7LP-SISITWTM1  DoneNb#7 installed

    

       
            
  
  197   Friday, September 07, 2012, 14:34 Anders MjosNb#7LP-SISITWTM1  Problems/SolutionsInsulator ITD0342 overheated - swelling See attached photo  Nb#7_swelling_insulator.pdf 
  200   Wednesday, September 12, 2012, 08:02 Anders MjosNb#7LP-SISITWTM1  In progressVentingWednesday, September 12, 2012, 08:01: Turbos
off
Wednesday, September 12, 2012, 13:35:
  
  201   Wednesday, September 12, 2012, 17:04 Anders MjosNb#7LP-SISITWTM1  In progressPumping down - w/replaced insulatorsReplaced swollen insulator and added Ta
heat shield on insulator.
 
  
  202   Thursday, September 13, 2012, 08:24 Anders MjosNb#7LP-SISITWTM1  In progressWater onThursday, September 13, 2012, 08:16: Opened
up cooling water. Vacuum (IG1) increased
from 5.9E-7 to 6.2E-7 before returning to
  
  204   Friday, September 14, 2012, 15:27 Anders MjosNb#7LP-SISITWTM1  DoneVentingTarget cooled down. Power supplies off.
Friday, September 14, 2012, 15:27:
Turbos off.
  
  223   Thursday, October 25, 2012, 13:02 Anders MjosTiC#3LP-SISITWTM1  In progressPumping downThursday, October 25, 2012, 13:00: Roughing
Thursday, October 25, 2012, 13:19
: Turbos on
  
  224   Friday, October 26, 2012, 08:29 Anders MjosTiC#3LP-SISITWTM1  DoneTarget ready for conditioning

    

       
            
  
  225   Thursday, November 01, 2012, 11:16 Aurelia LaxdalTiC#3LP-SISITWTM1   TiC#3-LP-SIS StartupDid the HV conditioning for the TiC#3 up
to 30kV.
Heaters ramp up in progress.
  
  226   Thursday, November 01, 2012, 14:57 Aurelia LaxdalTiC#3LP-SISITWTM1   TSH:TGHT readback stopped at 264.5A (for a higher setpoint)The TSH:TGHT stopped at 263.7A, but the
setpoint is still ramping (now  at 421A).
The voltage is set correctly: have 6.238V
  
  227   Friday, November 02, 2012, 14:20 Aurelia Laxdal LP-SISITWTM1   Mass scan done

Normal
0




false
false
false
  
  228   Friday, November 02, 2012, 15:40 Aurelia Laxdal LP-SISITWTM1  DoneSiC#3 cooldown startedStarted the cooldown for SiC#3.   