64
|
Thursday, March 08, 2012, 17:39 |
Friedhelm Ames | | | | | | | Problems/Solutions | TPS:Q2 amd TMS:MB1 failed |
TPS:Q2 and TMS:MB1 failed during the scan. -> restarted. |
63
|
Thursday, March 08, 2012, 17:16 |
Friedhelm Ames | Nb#6 | | | | | | | mass scan started |
|
62
|
Thursday, March 08, 2012, 14:08 |
Friedhelm Ames | Nb#6 | | | | | | | heater ramped up |
heaters have reached final values TGHT 580 A, TBHT 230 A, some sparking during ramp up. see strip tool image attached |
61
|
Thursday, March 08, 2012, 09:14 |
Friedhelm Ames | Nb#6 | | | | | | | continue target heating |
continue target heating up to 580 A. Strip tool for the heating up to 300A from yesyerday see below |
60
|
Wednesday, March 07, 2012, 17:44 |
Friedhelm Ames | Nb#6 | | | | | | | ramping up heaters |
ramping up heaters has been started by ISAC ops. |
59
|
Wednesday, March 07, 2012, 13:48 |
Friedhelm Ames | Nb#6 | | | | | | | high voltage conditioning |
High voltage conditioning has been started by ISAC ops. Einzel lens is unstable below 5 kV., o.k. above this. |
58
|
Wednesday, March 07, 2012, 10:36 |
Paul Mocock | | | | | | | | HV conditioning begins. |
HV conditioning has begins. Vacuum chamber pressure is currently 3.2e-07 Torr on TSG:IG1. |
57
|
Wednesday, March 07, 2012, 09:27 |
Friedhelm Ames | Nb#6 | | | | | | Done | water cooling started |
water cooling line valves opened. No response on vacuum TSG:IG1 3.5e-7 T |
56
|
Tuesday, March 06, 2012, 15:51 |
Friedhelm Ames | | | | | | | | turbopumps in mass separator section started |
|
55
|
Tuesday, March 06, 2012, 15:25 |
Pierre Bricault | | | | | | | | ISAC test stand |
Turbos at full speed. P = 1.5E-05 T |
54
|
Tuesday, March 06, 2012, 15:17 |
Pierre Bricault | | | | | | | | ISAC test stand |
Start turbo pumps at 1514H |
53
|
Tuesday, March 06, 2012, 15:15 |
Pierre Bricault | | HP-SIS | | | | | | ISAC test stand two turbos replaced |
Vac group has replaced the two turbo pumps. |
52
|
Monday, March 05, 2012, 19:31 |
Friedhelm Ames | | | | | | | Failed | turbo pumps failed |
Both turbo pumps at the source box cannot be started. A fault report has been issued. |
51
|
Monday, March 05, 2012, 14:41 |
Friedhelm Ames | | | | | | | | vacuum and optics switched off |
vacuum and optics at teststand switched off to allow work on the water cooling system. |
50
|
Friday, March 02, 2012, 13:28 |
Anders Mjos | FEBIAD test | | | | | | | Venting test stand |
Venting for target exchange |
49
|
Friday, March 02, 2012, 08:53 |
Anders Mjos | FEBIAD test | | | | | | Problems/Solutions | Tube heater insulator glowing |
The insulator for the tube heater was observed to be glowing with a blue shine when the target was on high voltage. The insulator was glowing on the side closest to the 9-pin connector. See attached photo. |
48
|
Thursday, March 01, 2012, 17:10 |
Friedhelm Ames | | | | | | | | start ramping down of heaters |
|
47
|
Thursday, March 01, 2012, 17:09 |
Friedhelm Ames | | | | | | | | new mass scan |
Friedhelm Ames wrote: |
bigger mass scan after separator optimization and with finer step size
|
total curren on Fc0 183 nA gas valves SV2/5 open leak valve at 7.2 SV1 closed |
46
|
Thursday, March 01, 2012, 17:05 |
Friedhelm Ames | | | | | | | | start heater ramping down |
|
45
|
Thursday, March 01, 2012, 17:04 |
Friedhelm Ames | | | | | | | | new mass scan |
bigger mass scan after separator optimization and with finer step size
|