  304   Tuesday, May 21, 2013, 19:38 Friedhelm Ames      Problems/Solutionsmagnet power supply water leak

The cyclotron operators discovered a water leak in the magnet power supply. The water is valved off and the power is off. A fault report has been issued to the power supplies group.

  59   Wednesday, March 07, 2012, 13:48 Friedhelm AmesNb#6      high voltage conditioning

High voltage conditioning has been started by ISAC ops. Einzel lens is unstable below 5 kV., o.k. above this.

  262   Monday, January 07, 2013, 14:52 Sebastian RaederRFQ empty      heating target

heating target for RFQ tests. Now the wiring is insulated with alumina beats and tubing and the target has the standard Ta alkali element mixture

 

Unfortunately I deleted some entries, so here a short summary in combination with a screenshot of the striptool

heated to 580A, vacuum increased over time from 4.8 to 5.6E-7T

HV up to 30kV - current of 37 uA - seems fine

Mass scan not possible, ops found a water leak in the magnet PS, optics around the magnet are thereofre also not available and red in EPICS

NOTE: all FC values are in reversed bias!!

 

source +4.5V, 2nd Rep 0V:  RFQ offs =0V, RFQ Ampl = 20V, 1 MHz (current 0.26A), locked up

 about 2E-9A at FC0

one spark observed

 

source -5.5V, 2nd Rep 0V:  RFQ offs =0V, RFQ Ampl = 20V, 1 MHz (current 0.26A), locked up

  about 4E-11A at FC0

 

source -12V, 2nd Rep 0V:  RFQ offs =0V, RFQ Ampl = 20V, 1 MHz (current 0.26A), locked up

  about 5E-11A at FC0

  two sparks observed

 

source +4.5V, 2nd Rep 0V:  RFQ offs =0V, RFQ Ampl = 20V, 1 MHz (current 0.26A), locked up

  about 3E-10A at FC0

 

source -5.5V, 2nd Rep 0V:  RFQ offs =0V, RFQ Ampl = 20V, 1 MHz (current 0.26A), locked up - done again since not sure if the restore of the tune was done properly for this

  about 4E-11A at FC0

 

done, source +4.5V, 2nd Rep +12V:  RFQ offs =0V, RFQ Ampl = 20V, 1 MHz (current 0.26A), locked up

   about 3E-10A at FC0

 1 spark during HV ramping

 

done, source +4.5V, 2nd Rep&exit +12V:  RFQ offs =+12V, RFQ Ampl = 20V, 1 MHz (current 0.26A), locked up

there is something visible <~ 2E-12A at FC0

 

reduced current to 550A and leave it over night.

 

Short summary:

suppression possible but RFQ has to be shifted, the "only source shift" mode yielded a worse suppression than expected - unfortunately no mass scans have been possible, which would help to get some information on possible effects

 

Attachment 1: RFQ_with_signal_total.PNG
RFQ_with_signal_total.PNG
Attachment 2: RFQ_with_signal.PNG
RFQ_with_signal.PNG
  267   Monday, January 14, 2013, 13:51 Sebastian RaederRFQ empty     In progressheating

Started heating the target, now Silica sleevings are installed for wire insulation and the gap target -- repeller is now 0.6mm (was 0.25mm)

  272   Thursday, January 17, 2013, 08:16 Sebastian RaederRFQ empty     In progressheating

Thursday, January 17, 2013, 08:16: started heating of the target, vacuum at 2.6E-7T

 Thursday, January 17, 2013, 14:55: current at 572A/6.95V (panel reading), vacuum at 6.7E-7T

Thursday, January 17, 2013, 18:40: measurements done, vacuum at 5.3E-7T, current 572V/6.94V, start cooling down

  276   Friday, January 18, 2013, 16:17 Anders MjosRFQ empty     In progressheating

 

Sebastian Raeder wrote:

Thursday, January 17, 2013, 08:16: started heating of the target, vacuum at 2.6E-7T

 Thursday, January 17, 2013, 14:55: current at 572A/6.95V (panel reading), vacuum at 6.7E-7T

Thursday, January 17, 2013, 18:40: measurements done, vacuum at 5.3E-7T, current 572V/6.94V, start cooling down

 

 The temperature of the cooling water was logged during this test. See attachments for details. Note that current and voltage read back is not available due to trouble with the power supply. One thermocouple (Heat Shield circuit) came loose before the end of the test (not shown in plot).

Attachment 1: Test_Stand_cooling_temp_data_2013-01-16.pdf
Test_Stand_cooling_temp_data_2013-01-16.pdf
Attachment 2: Test_Stand_strip_tool_TGHT_CUR_2013-01-16.PNG
Test_Stand_strip_tool_TGHT_CUR_2013-01-16.PNG
  69   Friday, March 09, 2012, 17:25 Friedhelm Ames       heaters and HV power supplies off

heaters and HV power supplies have been switched off

IG1 5.1e-9 T.

  203   Thursday, September 13, 2012, 13:05 Friedhelm AmesNb#7LP-SIS     heater ramping up started
  68   Friday, March 09, 2012, 13:30 Friedhelm AmesNB#6      heater ramping down

Fc0 23 nA

IG1 9.9e-7 T

start automatic heater ramping down

  62   Thursday, March 08, 2012, 14:08 Friedhelm AmesNb#6      heater ramped up

heaters have reached final values TGHT 580 A, TBHT 230 A, some sparking during ramp up. see strip tool image attached

Attachment 1: grab.Z27253.png
grab.Z27253.png
  14   Wednesday, September 28, 2011, 14:11 Friedhelm AmesSiC#26 ITETM4   gas system checked and pumped

The gas system has been checked. The variable valve opens at about 7.55 very fast. Please be careful when using it. Stepsize for opening around this value should be 0.01. Gas lines have been pumped with pump in the high voltage rack. Ne leak was opened to release pressure.

  44   Wednesday, February 29, 2012, 17:26 Friedhelm Ames       gas inlet valves closed
  220   Wednesday, October 10, 2012, 10:47 Friedhelm Ames      Failedfound teststand tripped off

turbo pumps in source section and all ion gauges off all optics and heaters tripped. Reason unknown.

  221   Wednesday, October 10, 2012, 17:35 Aurelia Laxdal      Failedfound teststand tripped off

Friedhelm Ames wrote:

turbo pumps in source section and all ion gauges off all optics and heaters tripped. Reason unknown.

 Checked the Archiver and the striptool: TSG:TP1A & TP1B tripped on Oct. 10, at 7:53am. Both pumps showed timeout, but the AC breakers were not tripped. Also, checked with MCR: they were no power bumps or cooling water problems around that time. 

Discussed it with Kazuya Negishi from Controls: there were no PLC problems. Kazuya and I would monitor the trips. 

  130   Thursday, July 05, 2012, 18:02 Friedhelm Ames      Problems/Solutionsfluctuations in magnet current

The current at the magnet power supply TMS:MB1 shows fluctuations every 1-2 minutes. The same can be seen in the Hall probe read back and in the beam current at Fc6.

Attachment 1: TMSMB1_2012_07_05.PNG
TMSMB1_2012_07_05.PNG
  131   Thursday, July 05, 2012, 18:10 Friedhelm Ames      Problems/Solutionsfluctuations in magnet current

Friedhelm Ames wrote:

The current at the magnet power supply TMS:MB1 shows fluctuations every 1-2 minutes. The same can be seen in the Hall probe read back and in the beam current at Fc6.

 a fault report has been issued to power supplies group. Dan Louie will look into it.

  160   Friday, August 10, 2012, 15:29 Pierre BricaultNALP-FEBIAD  NANA finishing the gas installation and its pump

1524H Start small pump.

1529H stop the pump.

 

  199   Tuesday, September 11, 2012, 19:48 Friedhelm AmesNB#7HP-SIS    Donecool down finished, all source power supplies off.
  61   Thursday, March 08, 2012, 09:14 Friedhelm AmesNb#6      continue target heating

continue target heating up to 580 A. Strip tool for the heating up to 300A from yesyerday see below

Attachment 1: grab.K26109.png
grab.K26109.png
  42   Wednesday, February 29, 2012, 15:08 Friedhelm Ames       connected Al(CH3)3

connected A(CH3)3 instead of He, pumped line and valve with pump on the high voltage rack.. Opened regulating valve first response at mass 27 with valve set point at 7.0.