Entry  Wednesday, February 29, 2012, 15:08, Friedhelm Ames, , , , , , , , connected Al(CH3)3 
    Reply  Thursday, April 26, 2012, 09:14, Anders Mjos, , , , , , , , removed Al(CH3)3 
Message ID: 42     Entry time: Wednesday, February 29, 2012, 15:08     Reply to this: 78
Author: Friedhelm Ames 
Target/No.#:  
Source:  
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#:  
Status:  
Subject: connected Al(CH3)3 

connected A(CH3)3 instead of He, pumped line and valve with pump on the high voltage rack.. Opened regulating valve first response at mass 27 with valve set point at 7.0.