304
|
Tuesday, May 21, 2013, 19:38 |
Friedhelm Ames | | | | | | | Problems/Solutions | magnet power supply water leak |
The cyclotron operators discovered a water leak in the magnet power supply. The water is valved off and the power is off. A fault report has been issued to the power supplies group. |
59
|
Wednesday, March 07, 2012, 13:48 |
Friedhelm Ames | Nb#6 | | | | | | | high voltage conditioning |
High voltage conditioning has been started by ISAC ops. Einzel lens is unstable below 5 kV., o.k. above this. |
262
|
Monday, January 07, 2013, 14:52 |
Sebastian Raeder | RFQ empty | | | | | | | heating target |
heating target for RFQ tests. Now the wiring is insulated with alumina beats and tubing and the target has the standard Ta alkali element mixture
Unfortunately I deleted some entries, so here a short summary in combination with a screenshot of the striptool
heated to 580A, vacuum increased over time from 4.8 to 5.6E-7T
HV up to 30kV - current of 37 uA - seems fine
Mass scan not possible, ops found a water leak in the magnet PS, optics around the magnet are thereofre also not available and red in EPICS
NOTE: all FC values are in reversed bias!!
source +4.5V, 2nd Rep 0V: RFQ offs =0V, RFQ Ampl = 20V, 1 MHz (current 0.26A), locked up
about 2E-9A at FC0
one spark observed
source -5.5V, 2nd Rep 0V: RFQ offs =0V, RFQ Ampl = 20V, 1 MHz (current 0.26A), locked up
about 4E-11A at FC0
source -12V, 2nd Rep 0V: RFQ offs =0V, RFQ Ampl = 20V, 1 MHz (current 0.26A), locked up
about 5E-11A at FC0
two sparks observed
source +4.5V, 2nd Rep 0V: RFQ offs =0V, RFQ Ampl = 20V, 1 MHz (current 0.26A), locked up
about 3E-10A at FC0
source -5.5V, 2nd Rep 0V: RFQ offs =0V, RFQ Ampl = 20V, 1 MHz (current 0.26A), locked up - done again since not sure if the restore of the tune was done properly for this
about 4E-11A at FC0
done, source +4.5V, 2nd Rep +12V: RFQ offs =0V, RFQ Ampl = 20V, 1 MHz (current 0.26A), locked up
about 3E-10A at FC0
1 spark during HV ramping
done, source +4.5V, 2nd Rep&exit +12V: RFQ offs =+12V, RFQ Ampl = 20V, 1 MHz (current 0.26A), locked up
there is something visible <~ 2E-12A at FC0
reduced current to 550A and leave it over night.
Short summary:
suppression possible but RFQ has to be shifted, the "only source shift" mode yielded a worse suppression than expected - unfortunately no mass scans have been possible, which would help to get some information on possible effects
|
Attachment 1: RFQ_with_signal_total.PNG
|
|
Attachment 2: RFQ_with_signal.PNG
|
|
267
|
Monday, January 14, 2013, 13:51 |
Sebastian Raeder | RFQ empty | | | | | | In progress | heating |
Started heating the target, now Silica sleevings are installed for wire insulation and the gap target -- repeller is now 0.6mm (was 0.25mm) |
272
|
Thursday, January 17, 2013, 08:16 |
Sebastian Raeder | RFQ empty | | | | | | In progress | heating |
Thursday, January 17, 2013, 08:16: started heating of the target, vacuum at 2.6E-7T
Thursday, January 17, 2013, 14:55: current at 572A/6.95V (panel reading), vacuum at 6.7E-7T
Thursday, January 17, 2013, 18:40: measurements done, vacuum at 5.3E-7T, current 572V/6.94V, start cooling down |
276
|
Friday, January 18, 2013, 16:17 |
Anders Mjos | RFQ empty | | | | | | In progress | heating |
Sebastian Raeder wrote: |
Thursday, January 17, 2013, 08:16: started heating of the target, vacuum at 2.6E-7T
Thursday, January 17, 2013, 14:55: current at 572A/6.95V (panel reading), vacuum at 6.7E-7T
Thursday, January 17, 2013, 18:40: measurements done, vacuum at 5.3E-7T, current 572V/6.94V, start cooling down
|
The temperature of the cooling water was logged during this test. See attachments for details. Note that current and voltage read back is not available due to trouble with the power supply. One thermocouple (Heat Shield circuit) came loose before the end of the test (not shown in plot). |
Attachment 1: Test_Stand_cooling_temp_data_2013-01-16.pdf
|
|
Attachment 2: Test_Stand_strip_tool_TGHT_CUR_2013-01-16.PNG
|
|
69
|
Friday, March 09, 2012, 17:25 |
Friedhelm Ames | | | | | | | | heaters and HV power supplies off |
heaters and HV power supplies have been switched off
IG1 5.1e-9 T. |
203
|
Thursday, September 13, 2012, 13:05 |
Friedhelm Ames | Nb#7 | LP-SIS | | | | | | heater ramping up started |
|
68
|
Friday, March 09, 2012, 13:30 |
Friedhelm Ames | NB#6 | | | | | | | heater ramping down |
Fc0 23 nA
IG1 9.9e-7 T
start automatic heater ramping down |
62
|
Thursday, March 08, 2012, 14:08 |
Friedhelm Ames | Nb#6 | | | | | | | heater ramped up |
heaters have reached final values TGHT 580 A, TBHT 230 A, some sparking during ramp up. see strip tool image attached |
Attachment 1: grab.Z27253.png
|
|
14
|
Wednesday, September 28, 2011, 14:11 |
Friedhelm Ames | SiC#26 | | ITE | TM4 | | | | gas system checked and pumped |
The gas system has been checked. The variable valve opens at about 7.55 very fast. Please be careful when using it. Stepsize for opening around this value should be 0.01. Gas lines have been pumped with pump in the high voltage rack. Ne leak was opened to release pressure. |
44
|
Wednesday, February 29, 2012, 17:26 |
Friedhelm Ames | | | | | | | | gas inlet valves closed |
|
220
|
Wednesday, October 10, 2012, 10:47 |
Friedhelm Ames | | | | | | | Failed | found teststand tripped off |
turbo pumps in source section and all ion gauges off all optics and heaters tripped. Reason unknown. |
221
|
Wednesday, October 10, 2012, 17:35 |
Aurelia Laxdal | | | | | | | Failed | found teststand tripped off |
Friedhelm Ames wrote: |
turbo pumps in source section and all ion gauges off all optics and heaters tripped. Reason unknown.
|
Checked the Archiver and the striptool: TSG:TP1A & TP1B tripped on Oct. 10, at 7:53am. Both pumps showed timeout, but the AC breakers were not tripped. Also, checked with MCR: they were no power bumps or cooling water problems around that time.
Discussed it with Kazuya Negishi from Controls: there were no PLC problems. Kazuya and I would monitor the trips. |
130
|
Thursday, July 05, 2012, 18:02 |
Friedhelm Ames | | | | | | | Problems/Solutions | fluctuations in magnet current |
The current at the magnet power supply TMS:MB1 shows fluctuations every 1-2 minutes. The same can be seen in the Hall probe read back and in the beam current at Fc6. |
Attachment 1: TMSMB1_2012_07_05.PNG
|
|
131
|
Thursday, July 05, 2012, 18:10 |
Friedhelm Ames | | | | | | | Problems/Solutions | fluctuations in magnet current |
Friedhelm Ames wrote: |
The current at the magnet power supply TMS:MB1 shows fluctuations every 1-2 minutes. The same can be seen in the Hall probe read back and in the beam current at Fc6.
|
a fault report has been issued to power supplies group. Dan Louie will look into it. |
160
|
Friday, August 10, 2012, 15:29 |
Pierre Bricault | NA | LP-FEBIAD | | | NA | NA | | finishing the gas installation and its pump |
1524H Start small pump.
1529H stop the pump.
|
199
|
Tuesday, September 11, 2012, 19:48 |
Friedhelm Ames | NB#7 | HP-SIS | | | | | Done | cool down finished, all source power supplies off. |
|
61
|
Thursday, March 08, 2012, 09:14 |
Friedhelm Ames | Nb#6 | | | | | | | continue target heating |
continue target heating up to 580 A. Strip tool for the heating up to 300A from yesyerday see below |
Attachment 1: grab.K26109.png
|
|
42
|
Wednesday, February 29, 2012, 15:08 |
Friedhelm Ames | | | | | | | | connected Al(CH3)3 |
connected A(CH3)3 instead of He, pumped line and valve with pump on the high voltage rack.. Opened regulating valve first response at mass 27 with valve set point at 7.0. |