ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Statusdown Subject Text Attachments
  800   Monday, July 13, 2020, 14:52 Aaron Schmidt LP-FEBIAD  41790-943515-2 UCx HS conditioning. Broken LP-FEBIAD used to out gas.
Monday, July 13, 2020, 14:52: Roughing.
Monday, July 13, 2020, 15:29: Turbo
  
  807   Tuesday, August 18, 2020, 10:00 Aaron Schmidt       IDP15 Scroll pump installed - RP1 replacedPN: X3815-64000
SN: MY2005SA02
Description: IDP15 Scroll pump, Std.
  
  809   Wednesday, August 19, 2020, 08:52 Aaron Schmidt       Leak check / TroubleshootWednesday, August 19, 2020, 08:52: Purging
all lines, except FS#5, It was already purged
/ closed.
 Aug_19_-_2020_Leak_Check..docx 
  824   Wednesday, December 02, 2020, 08:32 Carla Babcock       Modifications to test stand for TM3 testsWednesday, December 02, 2020, 08:31 :
Added copper wire connection to multipin
screw terminals in HV cage to make sure they
  
  826   Thursday, December 03, 2020, 15:55 Carla Babcock, Alexander Shkuratoff       Modifications to ISAC test stand for TM3 testsThursday, December 03, 2020, 15:54 :
Got sign off from John Chow to run
the system, though the nylon insulator was
 20201203_150458.jpg20201203_173725.jpg 
  827   Friday, December 04, 2020, 08:53 Carla Babcock       Modifications to test stand for TM3 testsFriday, December 04, 2020, 08:52 :
Test stand roughed down to 29mT overnight.
Started turbos for testing later.
  
  829   Tuesday, December 08, 2020, 11:54 Carla Babcock       Modifications to test stand for TM3 testsThe copper tubes to be used in the TM3
test piece may have flux inside them from
soldering the end caps on. There are holes
 20201207_135011.jpg20201207_134951.jpgScreenshot_from_2020-12-09_19-41-36.png 
  830   Friday, December 11, 2020, 15:02 Carla Babcock, Sam McEwen, Aaron Schmidt       Modifications to test stand for TM3 testsTest piece installed with Sam, Aaron and
Alexander. Ended up shimming the support
stand (middle foot) since it seemed to be
 20201211_140703.jpg20201211_140639.jpg20201211_140605.jpg 
  832   Tuesday, December 15, 2020, 11:24 Alexander Shkuratoff       TM3 service tray prototype HV testsTuesday, December 15, 2020, 11:15
Vacuum at 1.0e-6 Torr. Turned bias
power supply on, starting HV ramp at 500
  
  833   Wednesday, December 16, 2020, 10:32 Carla Babcock, Alexander Shkuratoff       TM3 service tray prototype HV testsWednesday, December 16, 2020, 10:30 (Carla)
:
Started ramping up about 45 mins
  
  834   Thursday, December 17, 2020, 08:16 Carla Babcock, Alexander Shkuratoff        Ramping up to 75kV. Started drawing current
at 63.5kV this time.
Now at 75kV, drawing 5uA of current.
  
  835   Monday, December 21, 2020, 07:58 Aaron Schmidt       Shutdown TS Shutting down the ISAC TS for the planned
outage on Dec 22.
Monday, December 21, 2020, 07:50:
  
  836   Monday, January 04, 2021, 08:17 Aaron Schmidt       Restart TSRestarting TS after holidays & planned
power outage.
Monday, January 04, 2021, 08:17:
  
  837   Monday, January 11, 2021, 14:20 Carla Babcock       Test stand wiring reverted to anode bias modeI have rewired the test stand (service
cap wiring only, not power supply wiring)
to anode bias mode as shown in the diagram.
  
  852   Thursday, February 18, 2021, 10:47 Aaron Schmidt       Optics loss / CANBUS failure.Thursday, February 18, 2021, 10:45: TPS:Q3
& the TSB CBC CANBUS controllers had
failed yesterday, as well as a cable was
  
  860   Tuesday, March 02, 2021, 11:42 Aaron Schmidt       TS Tripped.    
  861   Wednesday, March 10, 2021, 11:10 Carla Babcock       Venting for installation of emittance metersWednesday, March 10, 2021, 10:48 
: Venting beamline section only for installation
of emittance meters.
  
  864   Monday, March 15, 2021, 16:10 Carla Babcock       TISA emittance meter testing with new FEBIAD sourceMonday, March 15, 2021, 16:09 Target and
ion source ramped to 400A/330A this afternoon
Monday, March 15, 2021, 18:53 : Tune
 Carla_tune_tracking.docx 
  865   Thursday, March 25, 2021, 08:11 Aaron Schmidt       Test Stand Tripped. (Water leak)   Mar_2021_-_FS#3_leak..docx 
  866   Friday, March 26, 2021, 17:04 Carla Babcock       Beam line vented for emittance meter exchangeVented beamline and removed ARIEL emittance
meter. In the process of swapping components,
beamline left vented until Monday when we
  