Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Test-Stand, Page 48 of 49  Not logged in ELOG logo
Entry  Tuesday, February 28, 2012, 16:32, Brandon Humphries, , , , , , , , Initial settings for FEBIAD on Test Stand grab.V13332.pnggrab.m13336.png
ISAC Test Stand FEBIAD Ion Source and ISACT optics screen grabs before practicing tuning.  Tune saved as: data/febiaddata/tune/120228-1620_0.snap
and data/isactdata/tune/120228-1620_0.snap respectively.<br>
Seeing 1.93e-06 on TMS:FC0 and 3.30e-09 on TMS:FC6.
Entry  Tuesday, February 28, 2012, 11:04, Pierre Bricault, , , , , , , ,  
 Calibrating the gas valve
Entry  Tuesday, February 28, 2012, 10:29, Pierre Bricault, , LP-FEBIAD, , , , , In progress, Test FEBIAD at ISAC test statnd 
 
Entry  Monday, February 27, 2012, 17:39, Friedhelm Ames, , , , , , , In progress, target and tube heaters ramped up 
ramping up target to 300 A and tube to 270 A
Entry  Friday, February 17, 2012, 10:27, Aurelia Laxdal, , , , , , , Done, Started the Archivers 
Started both ISACT and SOURCES Archivers.
Entry  Thursday, February 16, 2012, 15:59, Anders Mjos, , , , , , , Problems/Solutions, He and Ne installed and gas lines leak checked 
New supply of He and Ne was installed yesterday and gas lines leak checked. The He bottle is currently closed.

UPDATE Monday, June 17, 2013, 15:17
Specifications for the currently installed Ne leak (SN: 11-231) can be found on DocuShare
Entry  Wednesday, February 08, 2012, 17:39, Friedhelm Ames, , , , , , , Failed, TSG:TP1B failure 
Both turbo pumps at the source box were found off. TSG:TP1A has been started normally. TSG:TP1B does not spin up above 3KRPM even after several attemps.
A fault report has been send to vacuum group.
 
    Reply  Wednesday, February 08, 2012, 18:16, Friedhelm Ames, , , , , , , Failed, TSG:TP1B and TSG:TP1A failure  


    
        
            Friedhelm Ames wrote:
        
        
            
            Both turbo pumps at the source box were found off. TSG:TP1A has been started normally. TSG:TP1B does not spin up above
Entry  Tuesday, January 24, 2012, 09:44, Friedhelm Ames, , , , , , , , turbo pumps restarted 
All turbo pumps have been restarted after cooling water is back and running.
 
Entry  Friday, January 20, 2012, 10:37, Friedhelm Ames, , , , , , , , vacuum pumps shut off 
turbo pumps shut off due to work on cooling water system
Entry  Monday, October 17, 2011, 10:22, Anders Mjos, FEBIAD, , , , , , Problems/Solutions, Variable leak valve replaced F3-649.PDF
Variable leak valve with serial number F3-592 has been replaced by F3-649 due to regulating problems described previously by Fridhelm Ames.
    Reply  Monday, November 14, 2011, 15:40, Anders Mjos, , , , , , , Problems/Solutions, Variable leak valve repaired F3-VCR-43_Repair_F3-592.PDF


    
        
            Anders Mjos wrote:
        
        
            
            Variable leak valve with serial number F3-592 has been replaced by F3-649 due to regulating problems
       Reply  Tuesday, December 20, 2011, 16:09, Anders Mjos, , , , , , , Problems/Solutions, Variable leak valve repaired 


    
        
            Anders Mjos wrote:
        
        
            
            
            
Entry  Monday, December 19, 2011, 13:09, Aurelia Laxdal, , , , , , , , Test Stand updates 
In January Controls will install a new firewall for ISAC Test Stand. Until then ISAC Test Stand can be used, but it may require an IOC reboot once in
while.
Entry  Tuesday, December 13, 2011, 14:10, Aurelia Laxdal, , , , , , , , Test Stand IOC reboot 
Evgeniy rebooted the ISAC Test Stand IOC. Re-started EPICS at the Test Stand.
Found all 4 turbo pumps off and their backing valves closed. Re-started the pumps.
Entry  Thursday, October 13, 2011, 12:33, Rick Maharaj, Training , , , , , , , Test stand vented 
test stand vented
    Reply  Thursday, October 13, 2011, 15:42, Anders Mjos, Training , HP-FEBIAD, , , , , Problems/Solutions, Target ready to be heated 


    
        
            Rick Maharaj wrote:
        
        
            
            test stand vented
Entry  Monday, October 03, 2011, 10:53, Aurelia Laxdal, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Target is ready to be removed.  
Turned off the HV and locked up the transformer. Isolated the ion source box. The target is under vacuum and the water is still on.
    Reply  Monday, October 03, 2011, 13:56, Anders Mjos, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Venting 


    
        
            Aurelia Laxdal wrote:
        
        
            
            Turned off the HV and locked up the transformer. Isolated the ion source box. The target is under vacuum
       Reply  Monday, October 03, 2011, 14:46, Anders Mjos, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Target stored under vacuum 


    
        
            Anders Mjos wrote:
        
        
            
            
            
              
          Reply  Wednesday, October 12, 2011, 13:14, Anders Mjos, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Target removed 


    
        
            Anders Mjos wrote:
        
        
            
            
            
Entry  Friday, September 30, 2011, 18:03, Aurelia Laxdal, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, Done, Finished testing SiC#26 at the Test Stand 
Today, did a did a mass scan: plotdump-local-clean.txt Sep30 11 12-20-08.txt
Optimized a bit the tune with Friedhelm, then started the Target Cooldown.
Entry  Thursday, September 29, 2011, 09:27, Aurelia Laxdal, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, In progress, Heaters conditioning 
Started the heaters conditioning: TGHT up to 580A and TBHT up to 230A.
Entry  Wednesday, September 28, 2011, 16:33, Aurelia Laxdal, SiC#26, HP-FEBIAD, ITE, TM4, 38295-9, 38307-8, In progress, HV conditioning 
Started the HV conditioning: TSG:BIAS=30kV
Entry  Wednesday, September 28, 2011, 14:11, Friedhelm Ames, SiC#26, , ITE, TM4, , , , gas system checked and pumped 
The gas system has been checked. The variable valve opens at about 7.55 very fast. Please be careful when using it. Stepsize for opening around this
value should be 0.01. Gas lines have been pumped with pump in the high voltage rack. Ne leak was opened to release pressure.
Entry  Monday, September 26, 2011, 16:14, Anders Mjos, , , , , , , Problems/Solutions, Fixed leak on water line for HS, added Kapton insulation Water_Leak.pdfKapton.pdf

    While testing SiC#26 a leak was discovered on the water line to the heat shield. The leak was in the right joint (see attachment). The heat
shield water lines were removed from the test stand and repaired in the Machine Shop. 
    Kapton was added to the FEBIAD coil line to prevent
it from shorting to the target heater line (see attachment).
Entry  Friday, September 23, 2011, 16:40, Anders Mjos, , , , , , , Problems/Solutions, 9-pin connectors swapped on source tray 
Friday, September 23, 2011, 16:3: The connection on the 9-pin connector for FEBIAD targets showed burn marks from the previous FEBIAD tests. Corresponding
mark was found on the connector on the target side. Because of this the upper and lower 9-pin connectors were swapped to have a clean connector for the
next FEBIAD target.
    Reply  Monday, September 26, 2011, 14:56, John Wong, , , , , , , Problems/Solutions, 9-pin connectors swapped on source tray 9-pin-connector.jpg


    
        
            Anders Mjos wrote:
        
        
            
            Friday, September 23, 2011, 16:3: The connection on the 9-pin connector for FEBIAD targets showed burn
ELOG V2.9.2-2455