Wednesday, February 08, 2012, 17:39, Friedhelm Ames, , , , , , , Failed, TSG:TP1B failure
|
Wednesday, February 08, 2012, 18:16, Friedhelm Ames, , , , , , , Failed, TSG:TP1B and TSG:TP1A failure
|
|
Message ID: 32
Entry time: Wednesday, February 08, 2012, 18:16
In reply to: 31
|
Author: |
Friedhelm Ames |
Target/No.#: |
|
Source: |
|
Station: |
|
Module: |
|
Target Oven W.O#: |
|
Heat Shield W.O#: |
|
Status: |
Failed |
Subject: |
TSG:TP1B and TSG:TP1A failure |
|
|
Friedhelm Ames wrote: |
Both turbo pumps at the source box were found off. TSG:TP1A has been started normally. TSG:TP1B does not spin up above 3KRPM even after several attemps. A fault report has been send to vacuum group.
|