ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Statusdown Subject Text Attachments
  639   Friday, February 23, 2018, 08:50 Aaron Schmidt       New Al Corona Friday, February 23, 2018, 08:50    
  640   Monday, February 26, 2018, 09:13 Carla Babcock       Running list of changes to the ISAC test stand for >60kV operation1. Al corona shield installed over end
of the HV duct to suppress discharges from
the sharp edge of the duct.
 6x 
  641   Wednesday, February 28, 2018, 11:50 Aaron Schmidt       HV Test NpNew parts installed. Corona Shield, brackets,
and board/spark gap orientation.
Wednesday, February 28, 2018, 11:48:
 2018_HV_test_Np.docx 
  642   Thursday, March 01, 2018, 10:05 Carla Babcock       HV tests with corona discharge problems solvedTurning up bias, no corona discharge at
60kV but a spark at 61.5kV bias, 31kV EZL,
-800V EE
 01032018_10am_61kVspark.PNG 
  643   Tuesday, March 06, 2018, 10:55 Carla Babcock       Trying HV without electronicsI have removed the resistor/varistor combinations
that go between the poles of the target and
tube heaters, and between those two supplies.
 spark_06032018.PNGnospark_06032018_1410.PNG 
  644   Thursday, March 08, 2018, 17:47 Carla Babcock       Change of electronics on target and tube power suppliesThe resistor/varistor combinations across
the target + / -, tube + / - and target-
/ tube + have been remade and moved to the
 IMG_20180308_152637.jpgIMG_20180308_152645.jpgTargetNeg.jpgTubeNegPos.jpg 
  645   Friday, March 09, 2018, 08:57 Carla Babcock       HV test with electronics moved to rackFirst attachment: BIAS/EE/EZL = 63.25/-1.5/31
So far no issues.
Second attachment: BIAS/EE/EZL =
 09032018_830.PNG09032018_835.PNG09032018_850.PNG09032018_855.PNG 
  646   Monday, March 12, 2018, 10:07 Aaron Schmidt       HV Test w-gasMonday, March 12, 2018, 09:45: Gas lines
opened. Leak rate set. Vacuum @ 1.16e-06T
Monday, March 12, 2018, 10:00: RGA
  
  647   Monday, March 12, 2018, 10:44 Carla Babcock       Bringing up HV with gas onPressure:
Previous HV tests done at 2e-7
pressure.
Current pressure 1.1e-6
 8x 
  652   Thursday, March 29, 2018, 10:58 Carla Babcock        Started with Anode at 25V and coil at 0A,
bias at 30kV. (attachment 1)
Ramped coil to 60A (0.4V) (attachment
 6x 
  653   Wednesday, April 11, 2018, 10:19 Aaron Schmidt       Pump down empty chamberWednesday, April 11, 2018, 10:19: Roughing   
  654   Tuesday, April 17, 2018, 09:59 Aaron Schmidt LP-FEBIAD  41790-9  Test FEBIADNew assembly & target. Same silver
bolts.
Tuesday, April 17, 2018, 09:56: Roughing.
  
  678   Tuesday, August 14, 2018, 11:03 Aaron Schmidt LP-SIS  41177-342752-6 Voltage Tests (Ta target)Tuesday, August 14, 2018, 10:55: Auto ramping
TGHT @ 6 A per min to 40 A.
Tuesday, August 14, 2018, 11:03:
  
  680   Wednesday, August 22, 2018, 15:20 Aaron Schmidt LP-SIS  41177-3  Voltage Tests (Ta Target)  Wires reconfigured / set 
Wednesday, August 22, 2018, 13:10:
Roughing. 
  
  681   Wednesday, August 29, 2018, 11:36 Aaron Schmidt       Epics / putty crash.Wednesday, August 29, 2018, 11:35: EPIC's
crashed.... epically.
Unable to restart Putty or TS controls.
  
  690   Monday, October 22, 2018, 07:18 Aaron Schmidt       TS restart after power outageFriday, October 19, 2018, 10:00 (Approx):
Site wide power outage. TS completely shut
down. 
  
  696   Thursday, November 08, 2018, 14:13 Aaron Schmidt       Ar & Ne gas bottle replacement.Thursday, November 08, 2018, 14:05: Fresh
/ recently calibrated Neon & Argon bottles
installed.
 GasLeak_Datasheet.pdf 
  701   Monday, December 17, 2018, 12:03 Aaron Schmidt LP-FEBIAD  395530-342752-5 Anode leak current check.Monday, December 17, 2018, 12:01: Connected
Multimeter through feedthroughs J & L.
Blue wire removed.
  
  702   Thursday, December 20, 2018, 13:55 Aaron Schmidt LP-FEBIAD  395530-342752-5 Holiday shut down.High winds caused a brief power outage
that completely shutoff the ISAC test stand.
Locked out the power.
  
  704   Wednesday, January 09, 2019, 09:10 Aaron Schmidt       Cathode to Anode. PS to PositiveWednesday, January 09, 2019, 09:09: Upper
HV cage set to Anode / Positive as per dwg
ISK4523D Rev 6.
  