236
|
Thursday, November 29, 2012, 16:21 |
Anders Mjos | | | | | | | | Pumping down | Thursday, November 29, 2012, 16:21: Roughing |
|
|
237
|
Friday, November 30, 2012, 10:42 |
Anders Mjos | | | | | | | | Venting | |
|
|
240
|
Tuesday, December 04, 2012, 11:05 |
Anders Mjos | | | | | | | | Vented | In preparation for RFQ target and leak
troubleshooting.
Tuesday, December 04, 2012, 11:04: |
|
|
243
|
Thursday, December 06, 2012, 08:41 |
Anders Mjos | | | | | | | | Opened cooling water | Vacuum stable at 2.8E-7 T |
|
|
244
|
Tuesday, December 11, 2012, 13:27 |
Sebastian Raeder | | | | | | | | 9 PIN connector | A Sub D 9 Pin connector on a HV insulator
was installed on Port Q of the target box
at the teststand. The insulator is leak tested |
|
|
247
|
Thursday, December 13, 2012, 14:38 |
Anders Mjos | | | | | | | | Pumping down empty chamber | Thursday, December 13, 2012, 14:36: Roughing
Thursday, December 13, 2012, 14:56
: Starting turbos |
|
|
248
|
Friday, December 14, 2012, 14:24 |
Sebastian Raeder | RFQ empty | | | | | | | Venting | Friday, December 14, 2012, 14:24 Stop Turbopumps
and prepare venting to insert RFQ target |
|
|
251
|
Monday, December 17, 2012, 22:35 |
Sebastian Raeder | RFQ empty | | | | | | | wire connection for RFQ test | Overview over the connections of the new
9Pin connector inside the vacuum and in the
HV cage |
|
|
252
|
Tuesday, December 18, 2012, 12:51 |
Sebastian Raeder | | | | | | | | Anode powersupply connected to HV-common | The anode PS is turned off and connected
to HV common.
the Target is connected to a -18V |
|
|
257
|
Thursday, December 20, 2012, 14:19 |
Anders Mjos | | | | | | | | Power down for holidays | |
|
|
262
|
Monday, January 07, 2013, 14:52 |
Sebastian Raeder | RFQ empty | | | | | | | heating target | heating target for RFQ tests. Now the wiring
is insulated with alumina beats and tubing
and the target has the standard Ta alkali |
|
|
264
|
Wednesday, January 09, 2013, 14:13 |
Anders Mjos | Empty | | | | | | | Rouging | Wednesday, January 09, 2013, 14:12: Roughing
empty chamber |
|
|
266
|
Friday, January 11, 2013, 11:02 |
Anders Mjos | RFQ empty | | | | | | | Target installed, pumping down | Target installed with 120 in lbs torque
on target legs and on central support.
Friday, January 11, 2013, 11:01: |
|
|
268
|
Monday, January 14, 2013, 18:18 |
Friedhelm Ames | | | | | | | | TMS:CBC1 not working | The optics at the teststand has been switched
on, but TMS:CBC1 is not working. A fault
report has been send to controls. |
|
|
269
|
Tuesday, January 15, 2013, 15:12 |
Sebastian Raeder | RFQ empty | | | | | | | Start cooling | Start cooling of Target RFQ empty |
|
|
270
|
Tuesday, January 15, 2013, 16:10 |
Anders Mjos | RFQ empty | | | | | | | Turbos off |
|
|
|
271
|
Wednesday, January 16, 2013, 01:06 |
Sebastian Raeder | RFQ empty | | | | | | | Target installed - pumping down | RFQ empty target installed
Wednesday, January 16, 2013, 01:05:
roughing started |
|
|
273
|
Friday, January 18, 2013, 11:28 |
Sebastian Raeder | RFQ empty | | | | | | | stop turbos | Friday, January 18, 2013, 11:28: turbos
stopped |
|
|
274
|
Friday, January 18, 2013, 15:34 |
Anders Mjos | empty | | | | | | | Pumping down empty chamber | Started roughing
Friday, January 18, 2013, 15:25:
Started turbos |
|
|
277
|
Monday, January 28, 2013, 12:56 |
Anders Mjos | Empty | | | | | | | Venting | For conductor bolt work
Monday, January 28, 2013, 12:56:
Turbos off |
|