  929   Friday, May 27, 2022, 07:19 Fernando Maldonado      DoneFEBIAD parameter scan web-app and brief description (with links)A web-app for systematic FEBIAD parametrizations
has been develop and  now includes the
ISAC Test Stand (ITS) :
  
  980   Monday, September 25, 2023, 16:31 Aaron SchmidtTa#66LP-SISITWTM245220-545235-9DoneConditioning Ta#66 & HV Tests.Thermocouples installed on the left end
plate x 2.
Monday, September 25, 2023, 16:23:
 Ta#66_HV_Test_1.docxTa#66_HV_test_2.docxTa#66_Conditioning.docx 
  987   Tuesday, December 12, 2023, 12:41 Aaron Schmidt      DoneSource Tray / TS inspectionTuesday, December 12, 2023, 12:39: Visual
inspection.
Source tray: OK. Minor cracks on
  
  989   Thursday, January 18, 2024, 10:44 Aaron Schmidt      DoneThermal tests 2December 18 - January 15. Were not logged.
Placed holder. Aurelia's tests. Included
thermocouples in the oven & ionizer.
  
  1000   Thursday, April 04, 2024, 10:38 Dave Neilson LP-SIS  44691-845235-26DoneMass marker testing Thursday, April 04, 2024, 09:49:
Target inserted yesterday, April 3. mass
marker tube connections carefully confirmed.
  
  1012   Tuesday, July 23, 2024, 09:43 Dave Neilson LP-SIS  44691-845235-26Donemass marker - reservoir testingWednesday, July 22, 2024, 11:41  -
target installed
Wednesday, July 22, 2024, 13:31 -
  
  1020   Friday, September 06, 2024, 12:08 Dave Neilson      DoneTest Stand repair/updateFriday, September 06, 2024:  New TSH:TGHT
power supply has been installed and is now
functional. Magna-Power TSD-900/208. The
  
  1033   Tuesday, December 03, 2024, 14:55 Dave Neilson      DonePower supply changed to CATHODE mode (-)Tuesday, December 03, 2024, 14:55  ANODE/CATHODE
power supply switched to cathode mode, NEGATIVE
  
  1042   Tuesday, December 17, 2024, 16:09 Dave Neilson      DoneAnode,TGHT, TBHT power supply investigation. Resolved Note, ground and HVC (high voltage
common) are used interchangeably here.
 
  
  1   Wednesday, June 29, 2011, 15:30 John Wong       Testing Yield station elogABC 123 blah blah blah...   
  4   Thursday, September 15, 2011, 09:20 Anders Mjos       ISAC TestStand old e-loglink
to old e-log
  
  9   Friday, September 23, 2011, 15:38 Rick Maharaj       test stand ventedTest stand vented   
  14   Wednesday, September 28, 2011, 14:11 Friedhelm AmesSiC#26 ITETM4   gas system checked and pumpedThe gas system has been checked. The variable
valve opens at about 7.55 very fast. Please
be careful when using it. Stepsize for opening
  
  22   Thursday, October 13, 2011, 12:33 Rick MaharajTraining       Test stand ventedtest stand vented   
  26   Tuesday, December 13, 2011, 14:10 Aurelia Laxdal       Test Stand IOC rebootEvgeniy rebooted the ISAC Test Stand IOC.
Re-started EPICS at the Test Stand.
Found all 4 turbo pumps off and their
  
  27   Monday, December 19, 2011, 13:09 Aurelia Laxdal       Test Stand updatesIn January Controls will install a new
firewall for ISAC Test Stand. Until then
ISAC Test Stand can be used, but it may require
  
  29   Friday, January 20, 2012, 10:37 Friedhelm Ames       vacuum pumps shut offturbo pumps shut off due to work on
cooling water system
  
  30   Tuesday, January 24, 2012, 09:44 Friedhelm Ames       turbo pumps restartedAll turbo pumps have been restarted after
cooling water is back and running.
 
  
  37   Tuesday, February 28, 2012, 11:04 Pierre Bricault         Calibrating the gas valve   
  40   Tuesday, February 28, 2012, 16:32 Brandon Humphries       Initial settings for FEBIAD on Test StandISAC Test Stand FEBIAD Ion Source and ISACT
optics screen grabs before practicing tuning. 
Tune saved as: data/febiaddata/tune/120228-1620_0.snap
 grab.V13332.pnggrab.m13336.png 