  ID Date Author Target/No.# Source Station Module Target Oven W.O# Heat Shield W.O# Status Subjectdown Text Attachments
  670   Thursday, June 21, 2018, 16:32 Anders Mjos LP-FEBIAD  41790-942752-5In progressHeating targetThursday, June 21, 2018, 16:30: Short between
ANODE and EE. Do not use until repaired.
Thursday, June 21, 2018, 16:32: Ramping
 TS-2018-06-19-10-30.rgaTS_Source_tray_2018_-_Check_2.docx 
  351   Wednesday, December 18, 2013, 12:04 Anders Mjos    40282-539230-1DoneHeating Test Wednesday, December 18, 2013, 12:04:
Turbos stopped
Wednesday, December 18, 2013, 13:19:
  
  354   Tuesday, January 14, 2014, 08:58 Anders Mjos    40282-539230-1DoneHeating TestTuesday, January 14, 2014, 08:57: Stopping
turbos. Vacuum at 1.2E-7 T
Tuesday, January 14, 2014, 13:32:
  
  1031   Thursday, November 28, 2024, 11:47 Isaiah Rabuka      In progressHeating Stage Pellet Testing and DevelopmentOpened the ATTS, placed what I will call
“Cast Alumina Sample #1” into
the ATTS and activated the roughing then
  
  16   Thursday, September 29, 2011, 09:27 Aurelia LaxdalSiC#26HP-FEBIADITETM438295-938307-8In progressHeaters conditioningStarted the heaters conditioning: TGHT
up to 580A and TBHT up to 230A.
  
  158   Friday, August 10, 2012, 13:48 Anders Mjos      Problems/SolutionsHe line leak checked - leak fixedA major leak was found on the connection
to the regulation valve on the He bottle.
Ferrule replaced. System leak checked.
  
  33   Thursday, February 16, 2012, 15:59 Anders Mjos      Problems/SolutionsHe and Ne installed and gas lines leak checkedNew supply of He and Ne was installed yesterday
and gas lines leak checked. The He bottle
is currently closed.
  
  95   Wednesday, May 16, 2012, 19:55 Friedhelm Ames      Problems/SolutionsHall probe reading wrongDuring the mass scan today it was discovered,
that the mass calibration was off. Further
investigation showed, that the Hall probe
  
  329   Wednesday, August 28, 2013, 11:28 Anders Mjos      Problems/SolutionsHall probe controller for MB1 removedJens Lassen provided a new controller for
the Hall prove. With the help from Graham
from controls it was reconfigured and is
  
  335   Wednesday, September 18, 2013, 14:54 Anders Mjos      Problems/SolutionsHall probe calibrationNew calibration of the m/q based on
the hall probe after exchanging the controller(MASSOVERQ2).
Based on NiO#2-HP-FEBIAD with Ne supplied
 2013-09-18_NiOcalibration.png 
  642   Thursday, March 01, 2018, 10:05 Carla Babcock       HV tests with corona discharge problems solvedTurning up bias, no corona discharge at
60kV but a spark at 61.5kV bias, 31kV EZL,
-800V EE
 01032018_10am_61kVspark.PNG 
  645   Friday, March 09, 2018, 08:57 Carla Babcock       HV test with electronics moved to rackFirst attachment: BIAS/EE/EZL = 63.25/-1.5/31
So far no issues.
Second attachment: BIAS/EE/EZL =
 09032018_830.PNG09032018_835.PNG09032018_850.PNG09032018_855.PNG 
  627   Wednesday, January 31, 2018, 12:58 Aaron Schmidt LP-SIS  (Blank)42752-3In progressHV test 4Wednesday, January 31, 2018, 12:53: Power/sources
on.
Wednesday, January 31, 2018, 12:58:
 2018_HV_test_4.docx 
  625   Tuesday, January 30, 2018, 06:51 Aaron Schmidt LP-SIS  (Blank)42752-3DoneHV test 3Tuesday, January 30, 2018, 06:50: BIAS
/ EZL / EE @ 30 / 13 / 1.5
Tuesday, January 30, 2018, 06:52:
 2018_HV_test_3.docx 
  623   Friday, January 26, 2018, 13:59 Aaron Schmidt LP-SIS  (Blank)42752-3DoneHV test 1Friday, January 26, 2018, 14:00: BIAS/EZL/EE
ramp up.
Friday, January 26, 2018, 14:06:
 2018_HV_test_1.docx 
  984   Monday, October 30, 2023, 16:01 Aaron Schmidt LP-SIS  45220-245235-13In progressHV power surge test plus mass scans Monday, October 30, 2023, 16:00 
Roughing

Tuesday, October 31, 2023,
  
  986   Monday, November 27, 2023, 16:09 Ferran Boix Pamies LP-SIS  45220-245235-13In progressHV power surge test plus mass scansMonday, November 27, 2023, 16:09 
Roughing
Monday, November 27, 2023, 17:22
  
  411   Friday, December 12, 2014, 13:11 Anders Mjos      Problems/SolutionsHV inspection and cleaningby Ray D and Anders in preparation for
60kV test. Rack insulators and f/t insulators
cleaned with windex
  
  412   Friday, December 12, 2014, 13:11 Anders Mjos      Problems/SolutionsHV inspection and cleaningby Ray D and Anders in preparation for
60kV test. Rack insulators and f/t insulators
cleaned with windex
  
  58   Wednesday, March 07, 2012, 10:36 Paul Mocock       HV conditioning begins.HV conditioning has begins. Vacuum chamber
pressure is currently 3.2e-07 Torr on TSG:IG1.
  