Friday, September 11, 2015, 11:43, Anders Mjos, Ta#46, HP-SIS, ITE, TM4, , , Done, Ta#46 conditioning
|
EE is ST-200 material (AlN)
Friday, September 11, 2015, 11:0: Roughing
Friday, September 11, 2015, 12:12: Turbos started. |
Monday, September 14, 2015, 08:38, Anders Mjos, , , , , , , Problems/Solutions, RP2 increased pressure
|
e-fault submitted and vacuum group (Edi) notified.
Monday, September 14, 2015, 09:33: RP2 replaced by vacuum group |
Thursday, September 17, 2015, 14:05, Anders Mjos, Test Target, LP-SIS, , , , , In progress, New centre block test
|
T1
Probe Inside Target
Left
T2
Centre block attached outside
|
Friday, September 18, 2015, 11:35, Anders Mjos, , , , , , , Problems/Solutions, TMS:TP6 nor working
|
found in fault state this morning. Edi consulted and fault report submitted. |
Wednesday, September 30, 2015, 16:28, Anders Mjos, Test Target wrapped with heat shields, LP-SIS, , , , , In progress, New centre block test
|
T1
Probe Inside Target Left
T2
|
Friday, October 02, 2015, 08:35, Anders Mjos, , , , , , , Problems/Solutions, Venting beam line for TP exchange
|
Friday, October 02, 2015, 08:35: Turbo stopped |
Wednesday, October 07, 2015, 11:16, Anders Mjos, SiC#32, HP-FEBIAD, ITW, TM2, , , In progress, Conditioning SiC#32
|
Wednesday, October 07, 2015, 11:15: roughing
Wednesday, October 07, 2015, 12:09 Turbos started
Wednesday, October 07, 2015, 12:18: Turbos at speed. Vacuum at 1.7E-5 T |
Tuesday, October 13, 2015, 07:47, Anders Mjos, SiC#32, HP-FEBIAD, ITW, TM2, , , In progress, Conditioning SiC#32
|
Target was pumped down on Friday.
Tuesday, October 13, 2015, 07:47: Opened water for HS. No response on RGA. Vacuum stable at 2.2E-7 T
Tuesday, October 13, 2015, 07:59: Gas lines open. |
Tuesday, October 13, 2015, 16:04, Anders Mjos, , , , , , , Problems/Solutions, IV4 timed out
|
Contacted Graham W. (controls) to have a look. It turned out to be a limit switch problem. Removed and reinstalled limit switch solved the time out issue. |
Tuesday, October 13, 2015, 17:23, Anders Mjos, SiC#32, HP-FEBIAD, ITW, TM2, , , In progress, Conditioning SiC#32
|
Tuesday, October 13, 2015, 17:22: Roughing
Tuesday, October 13, 2015, 18:07: Started turbos.
Tuesday, October 13, 2015, 18:15: Turbos at speed. Vacuum at 1.9E-5 T |
Wednesday, October 14, 2015, 16:13, Anders Mjos, , , , , , , Problems/Solutions, TMS:RP2 replaced
|
by vacuum group. The pump was making more noise than usual. |
Thursday, October 15, 2015, 11:19, Anders Mjos, , , , , , , Problems/Solutions, Right side TGHT connector block removed
|
The keensert has been worn out and will be replaced.
The keensert was re-tapped and the block re-installed. New bolts used for TGHT connection (2x). Swagelok T connections shortened (pluged). |
Monday, October 19, 2015, 09:45, Anders Mjos, , , , , , , Problems/Solutions, IG1 filament dead
|
Will went chamber to replace the filament.
See e-fault 8501
Monday, October 19, 2015, 09:43: turbos stopped |
Monday, October 19, 2015, 15:39, Anders Mjos, , , , , , , Problems/Solutions, Exhaust came off the new RP2
|
Anders Mjos wrote:
by vacuum group. The pump was making more noise than usual. |
Monday, November 02, 2015, 12:47, Anders Mjos, , , , , , , Problems/Solutions, Removed Swagelok T from rioght TGHT water lines
|
Mico replaced the T's with copper tube and leak checked.
Monday, November 02, 2015, 12:46: Roughing
Monday, November 02, 2015, 13:19: Starting turbos |
Monday, November 16, 2015, 14:52, Anders Mjos, , , , , , , In progress, Current measurement
|
Installed Cu-shunts on TGHT and TBHT terminals. HS water looped.
Monday, November 16, 2015, 14:43: Roughing
Monday, November 16, 2015, 15:21: Turbos started. |
Tuesday, November 17, 2015, 11:27, Anders Mjos, , , , , , , Problems/Solutions, Ran RP2 with gas ballast for 15 min
|
To recover performance |
Wednesday, December 02, 2015, 14:50, Anders Mjos, , , , , , , Problems/Solutions, Nitrogen supply for venting temporarely from bottle
|
No supply of N through the piping due to work on the N tanks. Confirmed with Geoff Hodgson. ISIS supply is shut off. Using a bottle until the supply
is returned.
Monday, January 11, 2016 |
Wednesday, December 02, 2015, 15:30, Anders Mjos, , LP-SIS, , , , , , New centre block test
|
New 2x 9-pin connector grounding tool with gripper installed.
Wednesday, December 02, 2015, 15:30: Roughing
Wednesday, December 02, 2015, 17:14: Starting turbos |
Friday, December 18, 2015, 11:44, Anders Mjos, , , , , , , Problems/Solutions, IG6 not reading correctly
|
The new controller (XGS-600) installed for IG6 use a different voltage to pressure conversion than the previous models. This causes a discrepancy between
values in EPICS and the value displayed on the controller. An e-fault has been submitted.
Friday, December 18, 2015, 14:40: EPICS updated and restarted. |
|