Entry  Tuesday, October 22, 2013, 15:20, Rick Maharaj, , , , , , , Problems/Solutions, Target Heater Conductor Block Insulators Replaced Source_Tray_TGHT_and_COIL_insulators_replaced_2013-10.pdf
The Conductor insulating blocks - ITD053C and ITD054C - that secure the target heater and coil conductor blocks were replaced. The existing ones were
cracked and fell apart upon removal.
Entry  Tuesday, October 15, 2013, 16:17, Anders Mjos, , , , , , , Done, TGHT and TB HT test bar test 
HS line is looped. Cu-test bars installed on TGHT and TBHT. Torqued all bolts  to 120 in lbs.
Tuesday, October 15, 2013, 16:17: Roughing
Tuesday, October 15, 2013, 16:39: Turbos started.
Entry  Thursday, October 03, 2013, 14:15, Anders Mjos, , , , , , , Problems/Solutions, TMS:Q1 and Q6 tripped 
 
Entry  Thursday, October 03, 2013, 08:43, Anders Mjos, , , , , , , Problems/Solutions, TMS:TP2 tripped off - controller replaced. 
This morning the turbo was found tripped off. 
The controller was replaced by Edi on Friday.

Monday, October 07, 2013, 08:28: Starting Turbo
Entry  Monday, September 30, 2013, 15:19, Anders Mjos, , , , , , , Problems/Solutions, New purging valves installed on Heat Shield water circuit 
The Heat Shield circuit can now be separately purged for water. Use valves on heat shield circuit to purge the lines for target exchanges from now on.
All paddle wheels have been rotated to allow trapped air to escape the system more easily.
Entry  Friday, September 27, 2013, 11:41, Anders Mjos, Ta#41, HP-SIS, ITW, TM4, 39069-5, 38817-10, Done, Ta#41 Conditioning Ta#41_EE_After_Test_Stand.pdf
Friday, September 27, 2013, 11:41: Roughing
Friday, September 27, 2013, 12:08: Turbos started
Friday, September 27, 2013, 12:16: Turbos at speed.
Entry  Wednesday, September 18, 2013, 16:18, Anders Mjos, , HP-FEBIAD, , , Tube only, 38307-9, Done, Test Target - FEBIAD COIL 
Wednesday, September 18, 2013, 16:18: Starting turbos
Wednesday, September 18, 2013, 16:26 : Turbos at speed
Wednesday, September 18, 2013, 16:28 : Vacuum at 2.8 E-5 T
Entry  Wednesday, September 18, 2013, 14:54, Anders Mjos, , , , , , , Problems/Solutions, Hall probe calibration 2013-09-18_NiOcalibration.png
New calibration of the m/q based on the hall probe after exchanging the controller(MASSOVERQ2). Based on NiO#2-HP-FEBIAD with Ne supplied and ANODE
biased to 200V, 30kV Bias.
CONST11 = -16.3929
Entry  Tuesday, September 17, 2013, 10:06, Anders Mjos, , , , , , , Problems/Solutions, TGHT insulator cracked Photo_2013-09-16_3_53_19_PM.jpg
The coil insulator has been observed to have cracked earlier. 
Entry  Monday, September 16, 2013, 17:07, Anders Mjos, NiO#2, HP-FEBIAD, ITE, TM3, 39530-6, 39069-4, Done, Conditioning NiO#2 take 2 
The GE on the Source tray and EE on the target was cleaned. The target will be conditioned again to verify if sparking has been reduced. Torque 120 in
lbs
Monday, September 16, 2013, 17:05: Roughing. The roughing pump is somewhat noisy.
Entry  Monday, September 09, 2013, 09:14, Anders Mjos, , , , , , , Problems/Solutions, Ground Electrode cleaned Dirty_GE.pdf
Monday, September 16, 2013, 17:04: Cleaned GE. Copper shavings were removed from below the guide pins for the Heat Shield. The shavings were sitting
on top of the aluminum support.
Entry  Monday, September 09, 2013, 09:12, Anders Mjos, , , , , , , Problems/Solutions, Coil power supply back 
Ray D. installed the "standard" 6V 200A FEBIAD COIL P/S on Friday morning.It has not yet been tested as water supply was on.
Entry  Friday, August 30, 2013, 15:09, Anders Mjos, NiO#2, HP-FEBIAD, ITE, TM3, 39530-6, 39069-4, Done, Conditioning of NiO#2 2013-09-12_NiO#2_TBHT_jump.PNG
Friday, August 30, 2013, 15:09 : Turbos stopped in preparation for installation. 
Friday, August 30, 2013, 16:22: Venting
Friday, August 30, 2013, 17:08: Roughing with NiO#2
Entry  Wednesday, August 28, 2013, 11:28, Anders Mjos, , , , , , , Problems/Solutions, Hall probe controller for MB1 removed 
Jens Lassen provided a new controller for the Hall prove. With the help from Graham from controls it was reconfigured and is operational again. The magnet
must likely be calibrated again.
Entry  Monday, August 26, 2013, 13:49, Anders Mjos, , , , , , , Problems/Solutions, TP1A time out/fault sometime this weekend 
Monday, August 26, 2013, 14:07: The turbo could be restarted, but it does not sound happy (Dimo was consulted earlier today). The pump is drawing around
4 A. The current draw is fluctuating between 3.5 and 4.2 A at the same time as backing pressure is spiking from 0.015 to 0.045 T
Monday, August 26, 2013, 15:32:: The turbo failed again. Dimo had a quick look. It will have to be replaced. See e-fault: 6953
Entry  Friday, August 23, 2013, 11:16, Anders Mjos, , , , , , , Problems/Solutions, Possible leak between BV1A, BV1B and PV1 
CG1A is climbing from 0.016 to 0.130 in 30 seconds when isolated.
The leak was confirmed to be between BV1A and PV1 in the bellows. The bellows has been replaced and backing pressure is back to normal values.
Entry  Tuesday, August 20, 2013, 08:27, Anders Mjos, , , , , , , Problems/Solutions, TP1B noise - TP1B replacement 
TP1B high frequency noise is coming and going. Power is 22W , current 1.1A (other pumps are 11W and 14W, 0.7A)
Edi from vacuum group notified. He will replace the pump today.
Tuesday, August 20, 2013, 08:40: Turbos off. Vacuum 1.4E-7 T
Entry  Tuesday, August 20, 2013, 08:24, Anders Mjos, , , , , Tube only, 38307-9, In progress, FEBIAD Coil Test 
Tuesday, August 20, 2013, 08:13: Roughing gas lines
Tuesday, August 20, 2013, 08:22: Gas lines roughed. Valve closed
Entry  Monday, July 22, 2013, 14:08, Anders Mjos, , , , , , , Problems/Solutions, 20V 60A COIL PS installed for FEBIAD Coil Test 
By Ray. Note that controls have not been updated yet.
Entry  Friday, July 19, 2013, 14:14, Anders Mjos, , , , , Tube only, 38307-9, In progress, FEBIAD Coil Test 
Friday, July 19, 2013, 14:14 : Stopping Turbos. Vacuum at 1.3E-7 T 
Friday, July 19, 2013, 15:14:  Venting
Friday, July 19, 2013, 16:22: Target installed. Roughing.