Message ID: 328     Entry time: Monday, August 26, 2013, 13:49
Author: Anders Mjos 
Target/No.#:  
Source:  
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#:  
Status: Problems/Solutions 
Subject: TP1A time out/fault sometime this weekend 

Monday, August 26, 2013, 14:07: The turbo could be restarted, but it does not sound happy (Dimo was consulted earlier today). The pump is drawing around 4 A. The current draw is fluctuating between 3.5 and 4.2 A at the same time as backing pressure is spiking from 0.015 to 0.045 T

Monday, August 26, 2013, 15:32:: The turbo failed again. Dimo had a quick look. It will have to be replaced. See e-fault: 6953


Wednesday, August 28, 2013, 08:48: Stopping TP1B. Vacuum at 4.8 E-7 T

Wednesday, August 28, 2013, 10:59: Venting

Anthony has replaced the pump. There was no screen on the existing pump. A screen has been installed in front of the turbo.

Wednesday, August 28, 2013, 14:03: started roughing

Wednesday, August 28, 2013, 14:31: Starting turbos

Wednesday, August 28, 2013, 14:41Turbos at speed

Wednesday, August 28, 2013, 14:43: Vacuum at 2.0 E-5 T