Monday, January 05, 2015, 09:06, Anders Mjos, , , , , , , Problems/Solutions, TSG:TP1A found to be timed out after the Hollidays
|
Vacuum at 1.7E-7 T
Corrected title from off to timed out . It seems the controller lost contact with the pump when I touched the rack. The pump recovered right back
to 38 kRPM upon restart. |
Monday, January 05, 2015, 09:20, Anders Mjos, , , , , , , Problems/Solutions, IV4 did not get close signal before the Hollidays
|
The valve closes physically, but does not receive the closed signal.
Cycled the valve multiple times before finally showing closed state. |
Tuesday, January 20, 2015, 14:31, Anders Mjos, , , , , , , Problems/Solutions, Ne leak disconnected for recallibration
|
SN 11-231 from VIC |
Wednesday, January 21, 2015, 13:40, Anders Mjos, , , , , , , In progress, HV BIAS Test
|
Wednesday, January 21, 2015, 13:34: Opened water flow.
Wednesday, January 21, 2015, 13:42: 30 / 15 kV (BIAS / EZL)
Wednesday, January 21, 2015, 13:4: 40 / 20 kV |
Wednesday, January 28, 2015, 10:40, Anders Mjos, , , , , , , Problems/Solutions, Test Stand shut down for site wide power outage today
|
Friday, January 30, 2015, 10:50: Optics section accidentally vented during work on the ER
Monday, February 02, 2015, 13:24: Roughing TMS section
Monday, February 02, 2015, 13:39: Starting turbos |
Tuesday, February 03, 2015, 09:40, Anders Mjos, , , , , , , Problems/Solutions, RGA installation
|
Tuesday, February 03, 2015, 09:40: Venting
RGA installed on the 12" CF port below the Source Tray.
Wednesday, February 04, 2015, 13:45: RGA turned on and mass scan performed. |
Tuesday, February 03, 2015, 14:33, Anders Mjos, Empty, LP-SIS, , , , , In progress, Target with new center block and new EE insulator
|
Also with newly installed RGA
Tuesday, February 03, 2015, 14:33: Roughing
Tuesday, February 03, 2015, 15:05: Turbos started |
Tuesday, February 03, 2015, 16:10, Anders Mjos, , , , , , , Problems/Solutions, Current read back on TBHT has been corrected to 600 A
|
By controls group |
Friday, February 13, 2015, 13:59, Anders Mjos, , , , , , , Problems/Solutions, PLC failure
|
The PLC CPU came out of the socket around 11:50am today (Dave Morris). The CPU had not been properly attached. This resulted in full stop of all power
supplies and vacuum pumps.
Restarted vacuum pumps at 12:10pm (20 min later). |
Tuesday, February 17, 2015, 14:41, Anders Mjos, , , , , , , In progress, Pumping down empty chamber
|
Tuesday, February 17, 2015, 14:35: Roughing. Doors were difficult to get to seal.
Tuesday, February 17, 2015, 15:11: Started turbos
Tuesday, February 17, 2015, 15:34: Turbos at speed. Vacuum at 6.7E-6 T |
Wednesday, February 18, 2015, 13:32, Anders Mjos, , , , , , , Problems/Solutions, Switched off system in preparation for power outage
|
Thursday, February 19, 2015, 12:14: Starting system again after the power outage
Thursday, February 19, 2015, 13:27: The performance of RP1 has degraded. Edi flushed some air through, which helped a bit. It now takes longer
to start up. |
Thursday, February 26, 2015, 10:11, Anders Mjos, , , , , , , In progress, Installing FEBIAD test target for emittance rig tests
|
Thursday, February 26, 2015, 10:11: Stopped turbos
Thursday, February 26, 2015, 11:23: Venting
Thursday, February 26, 2015, 11:39: Stopped venting at 550 T. To be continued later |
Monday, March 16, 2015, 18:53, Anders Mjos, Ta#45, HP-SIS, ITE, TM4, 38817-5, , In progress, Conditioning Ta#45
|
Monday, March 16, 2015, 18:53: Started turbos
Monday, March 16, 2015, 19:00: Turbos at speed. Vacuum at 1.3E-5 T
Tuesday, March 17, 2015, 09:03: Opened cooling water. Vacuum stable at 1.9E-7 T |
Tuesday, March 24, 2015, 09:50, Anders Mjos, , , , , , , In progress, Empty chamber
|
Roughed down on Friday 20th
Tuesday, March 24, 2015, 09:49: Turbos started
Tuesday, March 24, 2015, 09:59: Turbos at speed. Vacuum at 2.8E-6 T |
Thursday, April 09, 2015, 11:21, Anders Mjos, , , , , , , Problems/Solutions, No RGA communcations
|
RGA stopped working. Likely after a spark yesterday. |
Monday, April 13, 2015, 13:07, Anders Mjos, , , , , , , Problems/Solutions, ISAC Test Stand Optical elements power supply drop out
|
See e-fault 8027
Monday, April 13, 2015
Kevin and Graham are working on it |
Wednesday, April 22, 2015, 13:17, Anders Mjos, , , , , , , , Source Tray Removed
|
by Mico, Dan and Anders |
Friday, April 24, 2015, 12:25, Anders Mjos, , , , , , , Problems/Solutions, Backing line pressure high
|
TSG:RP1 backing line pressure is >200 mT. An e-fault has been submitted to have the roughing pump replaced.
Friday, April 24, 2015, 13:13: Pump replaced by vacuum group. |
Monday, May 04, 2015, 09:51, Anders Mjos, , , , , , , Problems/Solutions, FEBIAD Coil power supply replaced
|
Power supply did not work after high voltage conditioning. On Friday May 1st John Chow replaced the power supply with a 12 V 100 A power supply temporary while the other supply is being repaired. EPICS controls have not been adjusted. |
Friday, May 08, 2015, 09:07, Anders Mjos, , , , , , , Problems/Solutions, EPICS lost contact with the PLC
|
Everything shut down, while EPICS showed everyhing to be on.
Controls group (Dave Morris) has reestablished contact. System is operations.
TSG section vented for Source Tray work |
|