Logbooks Lab Maintenance Evaporator_1 Evaporator_2 Laser cutter Target Production Test-Stand RH-ISAC RH-Cyclotron RH-Meson Hall RH-Beamlines RH-ARIEL
  Test-Stand, Page 32 of 53  Not logged in ELOG logo
Entry  Monday, January 18, 2016, 08:41, Anders Mjos, , , , , , , Problems/Solutions, TSG:RP1 nor performing 

The pump failed to pump down below 2 Torr. on Friday 15th E-fault 8680 submitted. Vacuum group will replace the pump today

    Reply  Monday, January 18, 2016, 15:38, Aurelia Laxdal, , , , , , , Problems/Solutions, TSG:RP1 nor performing 2016-01-18_Pumping_on_Ta46Clone_(leak_at_Lid-Base_HS).png

Anders Mjos wrote:

The pump failed to pump down below 2 Torr. on Friday 15th E-fault 8680 submitted. Vacuum group will replace the pump today

Edi Dalla Valle from vacuum group replaced the roughing pump TSG:RP1 in the morning. However, the pumping curve showed a leak: see attachment. It was suspected the VCR water line connection between the lid and the base of the target Heat Shield. After venting the chamber found the VCR connection between the lid and the base forgotten finger tight. Tighten it with wrenches and restarted pumping.

    Reply  Tuesday, January 19, 2016, 18:34, Aurelia Laxdal, , , , , , , Problems/Solutions, TSG:RP1 nor performing 

Aurelia Laxdal wrote:

Anders Mjos wrote:

The pump failed to pump down below 2 Torr. on Friday 15th E-fault 8680 submitted. Vacuum group will replace the pump today

Edi Dalla Valle from vacuum group replaced the roughing pump TSG:RP1 in the morning. However, the pumping curve showed a leak: see attachment. It was suspected the VCR water line connection between the lid and the base of the target Heat Shield. After venting the chamber found the VCR connection between the lid and the base forgotten finger tight. Tighten it with wrenches and restarted pumping.

 Turned ON the water for the heat shield cooling circuit. Put a lockout padlock on the transformer breaker since Controls work still seems to be underway.

    Reply  Wednesday, January 20, 2016, 14:26, Aurelia Laxdal, , , , , , , Problems/Solutions, TSG:RP1 nor performing 

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Anders Mjos wrote:

The pump failed to pump down below 2 Torr. on Friday 15th E-fault 8680 submitted. Vacuum group will replace the pump today

Edi Dalla Valle from vacuum group replaced the roughing pump TSG:RP1 in the morning. However, the pumping curve showed a leak: see attachment. It was suspected the VCR water line connection between the lid and the base of the target Heat Shield. After venting the chamber found the VCR connection between the lid and the base forgotten finger tight. Tighten it with wrenches and restarted pumping.

 Turned ON the water for the heat shield cooling circuit. Put a lockout padlock on the transformer breaker since Controls work still seems to be underway.

Turned ON the TGHT and ramping it up at a rate of 1A/30sec. Currently it's at 108A.

    Reply  Wednesday, January 20, 2016, 19:11, Aurelia Laxdal, , , , , , , Problems/Solutions, TSG:RP1 nor performing 

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Anders Mjos wrote:

The pump failed to pump down below 2 Torr. on Friday 15th E-fault 8680 submitted. Vacuum group will replace the pump today

Edi Dalla Valle from vacuum group replaced the roughing pump TSG:RP1 in the morning. However, the pumping curve showed a leak: see attachment. It was suspected the VCR water line connection between the lid and the base of the target Heat Shield. After venting the chamber found the VCR connection between the lid and the base forgotten finger tight. Tighten it with wrenches and restarted pumping.

 Turned ON the water for the heat shield cooling circuit. Put a lockout padlock on the transformer breaker since Controls work still seems to be underway.

Turned ON the TGHT and ramping it up at a rate of 1A/30sec. Currently it's at 108A.

Temperature measurements in progress for Ta46clone HP-SIS target, wrapped with 3 Ta foil heat-shields . Stopped for today at 360A for the TGHT and TBHT kept OFF.

    Reply  Thursday, January 21, 2016, 13:04, Aurelia Laxdal, , , , , , , Problems/Solutions, TSG:RP1 nor performing 

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Anders Mjos wrote:

The pump failed to pump down below 2 Torr. on Friday 15th E-fault 8680 submitted. Vacuum group will replace the pump today

Edi Dalla Valle from vacuum group replaced the roughing pump TSG:RP1 in the morning. However, the pumping curve showed a leak: see attachment. It was suspected the VCR water line connection between the lid and the base of the target Heat Shield. After venting the chamber found the VCR connection between the lid and the base forgotten finger tight. Tighten it with wrenches and restarted pumping.

 Turned ON the water for the heat shield cooling circuit. Put a lockout padlock on the transformer breaker since Controls work still seems to be underway.

Turned ON the TGHT and ramping it up at a rate of 1A/30sec. Currently it's at 108A.

Temperature measurements in progress for Ta46clone HP-SIS target, wrapped with 3 Ta foil heat-shields . Stopped for today at 360A for the TGHT and TBHT kept OFF.

 Temperature measurements in progress for Ta46clone HP-SIS target, wrapped with 3 Ta foil heat-shields. currently at 496A and the window is OK.

Entry  Friday, January 22, 2016, 11:07, Anders Mjos, , , , , , , In progress, Venting 

 Friday, January 22, 2016, 11:07: Stopped turbos

    Reply  Friday, January 22, 2016, 13:35, Aurelia Laxdal, , , , , , , Problems/Solutions, TSG:RP1 nor performing 

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Aurelia Laxdal wrote:

Anders Mjos wrote:

The pump failed to pump down below 2 Torr. on Friday 15th E-fault 8680 submitted. Vacuum group will replace the pump today

Edi Dalla Valle from vacuum group replaced the roughing pump TSG:RP1 in the morning. However, the pumping curve showed a leak: see attachment. It was suspected the VCR water line connection between the lid and the base of the target Heat Shield. After venting the chamber found the VCR connection between the lid and the base forgotten finger tight. Tighten it with wrenches and restarted pumping.

 Turned ON the water for the heat shield cooling circuit. Put a lockout padlock on the transformer breaker since Controls work still seems to be underway.

Turned ON the TGHT and ramping it up at a rate of 1A/30sec. Currently it's at 108A.

Temperature measurements in progress for Ta46clone HP-SIS target, wrapped with 3 Ta foil heat-shields . Stopped for today at 360A for the TGHT and TBHT kept OFF.

 Temperature measurements in progress for Ta46clone HP-SIS target, wrapped with 3 Ta foil heat-shields. currently at 496A and the window is OK.

 Temperature measurements ended on Thursday, January 21, followed by cool down over night.

Entry  Wednesday, March 02, 2016, 12:08, Anders Mjos, , , , , , , Problems/Solutions, TGHT insulator broken 

 The insulator for the TGHT terminals cracked during an attempt to remove a seized bolt.The right TGHT block was removed with the target and the bolt cut to remove the target. The single stand-off insulator on the target assembly cracked in the process.


Friday, March 04, 2016

Re-installed the TGHT terminal with new Keensert.

Entry  Friday, March 11, 2016, 15:46, Anders Mjos, , , , , , , In progress, Testing end cap leak tightness 

Two Ta-tubes sealed with 2 end caps each placed in the vacuum chamber. 

Friday, March 11, 2016, 15:03: Rouging


Monday, March 14, 2016, 09:43: Caps still on the tube. Vacuum on CG1 5 mT


Wednesday, March 16, 2016, 08:37: Venting

Entry  Tuesday, March 29, 2016, 14:44, Aaron Schmidt, , , , , , , , Pumping down empty chamber. 

Tuesday, March 29, 2016, 14:43: Roughing.


 Wednesday, March 30, 2016, 14:33: Venting   -AM

Entry  Monday, April 04, 2016, 11:33, Aaron Schmidt, , LP-SIS, , , 41790-2, 39956-8, In progress, Testing restraint insulator prototype Anode_Voltage_VS_Current.xlsxTS-2016-04-05_Restraint_Test.rgaTS-2016-04-13_Restraint_Test.rgaRP#1.docx

Monday, April 04, 2016, 11:31: Begin roughing. (No plasma electrode)

Monday, April 04, 2016, 12:47: Started Turbos and Ion gauge


Tuesday, April 05, 2016, 09:09: Open water, Vacuum increased from 3.7E-07 to 2.2E-06 (roughly). Leak detected, Confirmed via RGA, Water increased from 7.0E-7T to 5.8E-6T.

Tuesday, April 05, 2016, 09:17: Turbo Pumps stopped. Ion gauge shut off. RGA off.

Tuesday, April 05, 2016, 10:28: Venting for inspection.

Tuesday, April 05, 2016, 11:31: Inspect, re-tighten with new seals.. Begin roughing.

Tuesday, April 05, 2016, 11:54: Turbo pumps started.

Tuesday, April 05, 2016, 11:59: Ion gauge turned on.

Tuesday, April 05, 2016, 15:45: Opened water for heat shield. Vacuum stable @ 6.4E-7T - 6.8E-7T.

 Tuesday, April 05, 2016, 16:07: Vacuum stable @6.4E-7T.


Wednesday, April 06, 2016, 09:09: Started auto ramping up to 500A and 200A at 2A/min BIAS/EZL/EE to 30/13/1.5 KV

Wednesday, April 06, 2016, 09:22: Opened IV4. Switched on optics.

Wednesday, April 06, 2016, 14:29: Continue auto ramp up to 580A and 230A at 2A/min.


Thursday, April 07, 2016, 13:30: Most of the salts have evaporated FC0: at 3E-10A

Thursday, April 07, 2016, 14:10: Ramp down 2A/min.


Friday, April 08, 2016, 08:57: Ramp up 2A/min to 100A and 50A. ANODE to 200V.

Friday, April 08, 2016, 13:50: Ramp up 2A/min to 500A and 200A.


Monday, April 11, 2016, 08:29: Ramp up 2A/min to 580A and 230A. Vacuum stable @ 2.9E-7T

Monday, April 11, 2016, 09:44: ANODE current increased from 0 to 16 mA during the ramp up. -AM

Monday, April 11, 2016, 11:36: Increased TGHT voltage limit to 7.35 V. ANODE current now at 18 mA -AM

Monday, April 11, 2016, 16:00: BIAS / EZL / EE to 30 / 13 / 1.5 kV -AM


Tuesday, April 12, 2016, 08:47: Ramp Down 2A/min 230A to 200A TBHT only.

Tuesday, April 12, 2016, 09:31: Ramp Down 2A/min 580A to 500A TGHT only.

Tuesday, April 12, 2016, 13:55: Ramp up 2A/min 500A to 580A TGHT only.

 Tuesday, April 12, 2016, 15:43: Ramp up 2A/min 580A to 590A, Voltage limit increased to 7.50 TGHT only.

Tuesday, April 12, 2016, 15:59: Ramp down 2A/min and 1A/min.


Wednesday, April 13, 2016, 08:04 : RGA off.

Wednesday, April 13, 2016, 08:20: Source off. IV4 closed. Turbo pumps off.

Wednesday, April 13, 2016, 09:38: Venting.

Wednesday, April 13, 2016, 10:59: Venting paused.

Wednesday, April 13, 2016, 11:03: Venting Continued.

Wednesday, April 13, 2016, 11:24: Venting complete. RP#1 removed. (No plasma electrode).

Entry  Wednesday, April 13, 2016, 13:03, Aaron Schmidt, , LP-SIS, , , 41790-2, 39956-8, , Testing restraint insulator prototype (2) Anode_Voltage_and_EE_(neg_bias).xlsxAnode_Voltage_and_EE_(pos_bias).xlsxRP#1_(2).docx

Wednesday, April 13, 2016, 13:03: Begin roughing. (Plasma electrode in. Salts in)

Wednesday, April 13, 2016, 13:34: Turbo pumps started.

Wednesday, April 13, 2016, 13:39: Ion Gauge on.


Thursday, April 14, 2016, 08:13: Open water to heat shield. Vacuum stable at 3.3E-7T.

Thursday, April 14, 2016, 08:19: Isolation valve opened. Auto ramping TGHT/TBHT to 300A/200A @ 2A/min.

Thursday, April 14, 2016, 08:33: Turned on optics. BIAS/EZL/EE to 30/13/1.5kV.

Thursday, April 14, 2016, 15:20: Ramping down TGHT from 300A to 250A @ 2A/min.


Friday, April 15, 2016, 8:23:  Slow ramping TGHT to 300A/ @ 1/2A/min.

Friday, April 15, 2016, 10:30: Begin ramping down TGHT/TBHT. @3A/2A per min.

Friday, April 15, 2016, 12:54: Sources off.

Friday, April 15, 2016, 13:09 :Water lines purged & power down.


Monday, April 18, 2016, 08:23: Opened water. Auto ramping TGHT/TBHT to 300A/200A @ 3A/2A per min. BIAS/EZL/EE to 30/13/1.5kV

Monday, April 18, 2016, 09:58: Ramping TBHT to 230A @ 2A/min

Monday, April 18, 2016, 12:54: Sources off. Ramping down @ 2A/min.


Tuesday, April 19, 2016, 09:37 : BIAS and EE off - AM

Tuesday, April 19, 2016, 15:30: Water, Ion gauge and Turbos off. 


Thursday, April 21, 2016, 13:41: Venting - AM

Entry  Friday, April 15, 2016, 16:07, Anders Mjos, , , , , , , Problems/Solutions, ANODE polarity switched to positive 

to test the effect of extraction when biasing of the target.

    Reply  Wednesday, April 20, 2016, 08:27, Anders Mjos, , , , , , , Problems/Solutions, ANODE polarity switched to negative 

Anders Mjos wrote:

to test the effect of extraction when biasing of the target.

 Testing finished. Switched back to negative polarity.

Entry  Friday, June 03, 2016, 14:50, Aaron Schmidt, , , , , , , , Pumping down empty chamber. 

Friday, June 03, 2016, 14:50: Turbo pumps started.

Friday, June 03, 2016, 15:22:  RGA on.


Monday, June 06, 2016, 15:40: RGA still connected. OK. Screen shot saved. Vacuum @ 8.5E-07T


Wednesday, June 08, 2016, 15:26: RGA off

Wednesday, June 08, 2016, 15:29: Ion gauge off. Turbo pumps off.


Thursday, June 09, 2016, 12:44: Venting -AM

Entry  Thursday, June 09, 2016, 14:56, Aaron Schmidt, , LP-SIS, , , , , , TUBE ONLY Tube_only_SIS_test.zip

Thursday, June 09, 2016, 14:50: Begin roughing.

Thursday, June 09, 2016, 15:34: Turbo pumps started.

Thursday, June 09, 2016, 15:42: Ion gauge on.


Friday, June 10, 2016, 08:27: RGA on.

Friday, June 10, 2016, 08:35: Water opened. RGA ok. Vacuum stable @ 1.9E-7T

Friday, June 10, 2016, 08:50: BIAS/EZL/EE to 30/13/1.5kV.

Friday, June 10, 2016, 08:52: Auto ramping TBHT only @ 2A min to 50A.

Friday, June 10, 2016, 10:02: Auto ramping TBHT only @ 1A min to 100A.

Friday, June 10, 2016, 11:14: Continue ramping to 150 A -AM

Friday, June 10, 2016, 11:28: Stopped ramping ag 110 A -AM


Monday, June 13, 2016, 08:12: Auto ramping TBHT only @ 1A min to 150A.

Monday, June 13, 2016, 09:59: Ramping to 150 A - AM


Monday, June 13, 2016, 15:51: Ramping down.


Tuesday, June 14, 2016, 07:47: IV4 Reset. Ion gauge off. Turbos off.

Tuesday, June 14, 2016, 07:52: Power/sources off. Water purged.

Tuesday, June 14, 2016, 09:20: Venting.

Entry  Friday, June 10, 2016, 12:42, Anders Mjos, , , , , , , Problems/Solutions, FC0 BIAS probelm 

 Graham Waters is looking into this problem. The IOC has been rebooted a couple of times.

Entry  Tuesday, June 14, 2016, 10:46, Aaron Schmidt, , LP-SIS, , , , , , TUBE ONLY - NO PLASMA ELECTRODE Tube_only_SIS_test-all-160615.zip2016-06-13.zip2016-06-15.zipre-em-plots.zip

Tuesday, June 14, 2016, 10:46: Begin roughing.

Tuesday, June 14, 2016, 11:16: Turbo pumps started.

Tuesday, June 14, 2016, 11:23: Ion gauge on.


Wednesday, June 15, 2016, 07:45: Water opened. RGA ok. Vacuum stable @ 1.9E-7T. Power/sources on.

Wednesday, June 15, 2016, 08:24: BIAS / EZL / EE to 30 / 13 / 1.5 kV

Wednesday, June 15, 2016, 08:24: Ramping TBHT to 120 A at 1 A/min

Wednesday, June 15, 2016, 10:23: EZL P/S was not on. Switched on and set to 13 kV

Wednesday, June 15, 2016, 15:05: Ramping down.


Thursday, June 16, 2016, 08:57: IV4 reset. RGA off. Ion gauge off. Turbo pumps off.

Thursday, June 16, 2016, 13:22: Water lines purged. Power/sources off. Venting.

Entry  Thursday, June 16, 2016, 14:34, Aaron Schmidt, , LP-SIS, , , , , , TUBE ONLY (3) Tube_only-full-fernando_test-160617-PE-RPE.zipTube_only-full-fernando_test-160617-WPE.zip

Thursday, June 16, 2016, 14:33: Roughing. Plasma Electrode re-attached. Salts replaced.

Thursday, June 16, 2016, 15:12: Turbo pumps started.

Thursday, June 16, 2016, 15:22: Ion gauge on.


Friday, June 17, 2016, 08:32: Water opened. RGA ok. Vacuum stable @ 2.4E-7T. Power/sources on.


Saturday, June 18, 2016, 09:31: Cool down started.


Monday, June 20, 2016, 09:48: Sources/power/voltages off.

Monday, June 20, 2016, 10:06: IV4 reset. Water lines purged.

 Monday, June 20, 2016, 10:11: RGA off. Ion gauge off. Turbos off.

Monday, June 20, 2016, 11:50: Venting

ELOG V2.9.2-2455