Entry  Monday, January 18, 2016, 08:41, Anders Mjos, , , , , , , Problems/Solutions, TSG:RP1 nor performing 
    Reply  Monday, January 18, 2016, 15:38, Aurelia Laxdal, , , , , , , Problems/Solutions, TSG:RP1 nor performing 2016-01-18_Pumping_on_Ta46Clone_(leak_at_Lid-Base_HS).png
       Reply  Tuesday, January 19, 2016, 18:34, Aurelia Laxdal, , , , , , , Problems/Solutions, TSG:RP1 nor performing 
          Reply  Wednesday, January 20, 2016, 14:26, Aurelia Laxdal, , , , , , , Problems/Solutions, TSG:RP1 nor performing 
             Reply  Wednesday, January 20, 2016, 19:11, Aurelia Laxdal, , , , , , , Problems/Solutions, TSG:RP1 nor performing 
                Reply  Thursday, January 21, 2016, 13:04, Aurelia Laxdal, , , , , , , Problems/Solutions, TSG:RP1 nor performing 
                   Reply  Friday, January 22, 2016, 13:35, Aurelia Laxdal, , , , , , , Problems/Solutions, TSG:RP1 nor performing 
Message ID: 486     Entry time: Monday, January 18, 2016, 08:41     Reply to this: 487
Author: Anders Mjos 
Target/No.#:  
Source:  
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#:  
Status: Problems/Solutions 
Subject: TSG:RP1 nor performing 

The pump failed to pump down below 2 Torr. on Friday 15th E-fault 8680 submitted. Vacuum group will replace the pump today