ID |
Date |
Author |
Target/No.# |
Source |
Station |
Module |
Target Oven W.O# |
Heat Shield W.O# |
Status |
Subject |
267
|
Monday, January 14, 2013, 13:51 |
Sebastian Raeder | RFQ empty | | | | | | In progress | heating | Started heating the target, now Silica sleevings are installed for wire insulation and the gap target -- repeller is now 0.6mm (was 0.25mm) |
268
|
Monday, January 14, 2013, 18:18 |
Friedhelm Ames | | | | | | | | TMS:CBC1 not working | The optics at the teststand has been switched on, but TMS:CBC1 is not working. A fault report has been send to controls. |
269
|
Tuesday, January 15, 2013, 15:12 |
Sebastian Raeder | RFQ empty | | | | | | | Start cooling | Start cooling of Target RFQ empty |
270
|
Tuesday, January 15, 2013, 16:10 |
Anders Mjos | RFQ empty | | | | | | | Turbos off |
Sebastian Raeder wrote: |
Start cooling of Target RFQ empty
|
Tuesday, January 15, 2013, 16:09: Turbos off
Tuesday, January 15, 2013, 21:15: Start venting with nitrogen- SR |
271
|
Wednesday, January 16, 2013, 01:06 |
Sebastian Raeder | RFQ empty | | | | | | | Target installed - pumping down | RFQ empty target installed
Wednesday, January 16, 2013, 01:05: roughing started
Wednesday, January 16, 2013, 01:34: turbos started
Wednesday, January 16, 2013, 01:43: turbos at speed
Wednesday, January 16, 2013, 01:44: vacuum at 1.7E-5T |
272
|
Thursday, January 17, 2013, 08:16 |
Sebastian Raeder | RFQ empty | | | | | | In progress | heating | Thursday, January 17, 2013, 08:16: started heating of the target, vacuum at 2.6E-7T
Thursday, January 17, 2013, 14:55: current at 572A/6.95V (panel reading), vacuum at 6.7E-7T
Thursday, January 17, 2013, 18:40: measurements done, vacuum at 5.3E-7T, current 572V/6.94V, start cooling down |
273
|
Friday, January 18, 2013, 11:28 |
Sebastian Raeder | RFQ empty | | | | | | | stop turbos | Friday, January 18, 2013, 11:28: turbos stopped |
274
|
Friday, January 18, 2013, 15:34 |
Anders Mjos | empty | | | | | | | Pumping down empty chamber | Started roughing
Friday, January 18, 2013, 15:25: Started turbos
Friday, January 18, 2013, 15:33: Turbos at speed
Friday, January 18, 2013, 15:35: Vacuum at 1.5E-5 T |
275
|
Friday, January 18, 2013, 15:57 |
Anders Mjos | | | | | | | Problems/Solutions | Conductor bolts to be replaced | After the last test at the test stand, one of the conductor bolts (ITD0058) is damaged. To prevent damage to the thread inserts, all conductor bolts will be replaced with new ones. |
276
|
Friday, January 18, 2013, 16:17 |
Anders Mjos | RFQ empty | | | | | | In progress | heating |
Sebastian Raeder wrote: |
Thursday, January 17, 2013, 08:16: started heating of the target, vacuum at 2.6E-7T
Thursday, January 17, 2013, 14:55: current at 572A/6.95V (panel reading), vacuum at 6.7E-7T
Thursday, January 17, 2013, 18:40: measurements done, vacuum at 5.3E-7T, current 572V/6.94V, start cooling down
|
The temperature of the cooling water was logged during this test. See attachments for details. Note that current and voltage read back is not available due to trouble with the power supply. One thermocouple (Heat Shield circuit) came loose before the end of the test (not shown in plot). |
277
|
Monday, January 28, 2013, 12:56 |
Anders Mjos | Empty | | | | | | | Venting | For conductor bolt work
Monday, January 28, 2013, 12:56: Turbos off
Monday, January 28, 2013, 14:18: Venting |
278
|
Monday, January 28, 2013, 14:41 |
Anders Mjos | Empty | | | | | | | Pumping down | Monday, January 28, 2013, 14:41: Roughing
Monday, January 28, 2013, 15:35: Starting turbos
Monday, January 28, 2013, 15:43: Turbos at speed
Monday, January 28, 2013, 15:45: Vacuum at 3.9 E-6 T |
279
|
Tuesday, February 19, 2013, 08:28 |
Anders Mjos | | | | | | | Problems/Solutions | Opened all backing valves after scheduled site wide air outage | |
280
|
Tuesday, February 26, 2013, 08:32 |
Anders Mjos | | | | | | | Problems/Solutions | TMSTP2 timeout / fault | Tuesday, February 26, 2013, 08:24: Started turbo
Tuesday, February 26, 2013, 08:24: Turbo timed out
e-fault 6585 submitted |
281
|
Monday, March 04, 2013, 09:11 |
Anders Mjos | | | | | | | Problems/Solutions | Restarted turobos after planned power outage | Started archivers
Started turbos
Switched on ion gauges
TMSTP2 out as per precious e-log entry (and e-fault 6585) |
282
|
Tuesday, March 19, 2013, 09:04 |
Anders Mjos | | | | | | | Problems/Solutions | Venting TMS section for replacement of TP2 by vacuum group |
Anders Mjos wrote: |
Tuesday, February 26, 2013, 08:24: Started turbo
Tuesday, February 26, 2013, 08:24: Turbo timed out
e-fault 6585 submitted
|
Edi called to inform that he can replace the turbo today.
Tuesday, March 19, 2013, 09:03: Stopped TP6
Tuesday, March 19, 2013, 09:35: Venting
Tuesday, March 19, 2013, 09:48 : TMS section and backing line vented
The turbo pump has been replaced see
https://elog.triumf.ca/TIS/Test-Stand/284
Some heat marks were observed on the turbo pump that was replaced. Vacuum group took pictures.
|
283
|
Tuesday, March 19, 2013, 12:34 |
Anders Mjos | SiC#28 | | ITE | TM4 | | | Done | Installation of SiC#28 LP-RFQ | Tuesday, March 19, 2013, 12:32 : Turbos off (vaccum at 2E-7 Torr)
Tuesday, March 19, 2013, 13:35: Venting
Target SiC#28 LP-RFQ inserted
New bolts used. Old bolts removed.
All bolts torqued to 120 in lbs
By Sebastian (SR) & Henning
modification of 9 Pin connector needed to match wiring in TM4 (see separate e-log entry)
Tuesday, March 19, 2013, 18:32 : started roughing - SR
Tuesday, March 19, 2013, 18:52: started turbos - SR
Tuesday, March 19, 2013, 18:57: TSGIP1 on - SR
Tuesday, March 19, 2013, 19:00: turbos at speed - SR
Tuesday, March 19, 2013, 19:02: vacuum at 1.68E-5T
By Anders
Wednesday, March 20, 2013, 08:18: Opened cooling water. Vacuum stable at 6.8E-7 Torr
By Sebastian (SR) & Henning
Wednesday, March 20, 2013, 11:39: 9PIN connector in HV cage connected
4,5,6,9 on GND 1,2 to RF, 7,8,RFoffest,Source for now also on GND
RF: 800kHz, 20Vampl, 0.128mA
HV cage locked up for heating
Wednesday, March 20, 2013, 16:42: heating is taken care of by ISAC operations, now at 300A / 3V TGHT and 250A / 1.47V TBHT reading on the panel is really close
Friedhelm restarted some of the CANBUS ports, since not all optics were working properly
Thursday, March 21, 2013, 10:53 start cooling down
Vacuum not perfect was around 2E-6T, over nigth not full current
Suppression tested yesterday: full beam (SRC +3V, others GND) was 40nA, while no signal on FB0B with SRC +3V, IGOffset&Exit +25V
!!!!! but short on #7 --> 2nd Repeller, was OK when tested, after some minutes on 25V short was there, reading now (Thursday, March 21, 2013, 10:58 ) <1OHM, will be checked while heating down
Magnet had wrong polarity - so no mass scans yesterday evening, Friedhelm looked into this this morning
Mass scan only for good transmission mode (SRC +3V) this morning - see attached scan (seen Na, Al, K, Ca, Cr, Rb, Sr, Cs and Ba)
Thursday, March 21, 2013, 12:26: stopped turbos
#7 still short
By Anders
Thursday, March 21, 2013, 13:25: Venting |
284
|
Tuesday, March 19, 2013, 17:25 |
Sebastian Raeder | | | | | | | Problems/Solutions | new turbo installed | Edi replaced the faulty turbo pump in the mass separator section.
Roughing and turbo started
vacuum @ 9E-7T after 2.5h |
285
|
Tuesday, March 19, 2013, 19:13 |
Sebastian Raeder | | | | | | | Problems/Solutions | 9 Pin connector rewired to match wiring in TM4 | The 9 Pin connector was rewired in the ISAC teststand to match the wiring in TM4
The wiring from the connection board in the HV cage to the connector (view from the target unit onto module) is now the following
---------------------------
\ 4 8 9 7 6 /
\ 5 1 2 x /
-----------------
with the pairs of wires
1,2 (kapton wire twisted pair all way)
4,5 (kapton wire twisted pair all way)
6,7 (kapton wire twisted pair inside the vacuum chamber, other twisted pair from top of vacuum chamber to HV cage)
8,9 (kapton wire twisted pair inside the vacuum chamber, other twisted pair from top of vacuum chamber to HV cage)
___ for completeness the wiring on top of the vacuum chamber (view from top onto the feedthrough)
---------------------------
\ 1 2 x 4 5 /
\ 6 7 8 9 /
-----------------
NOTE: with this rewiring the metal screws on the PEEK 9Pin connector have been grounded using Ta foil
Thursday, March 21, 2013: there was a short in one of the lines - most probably due to a shielding strand into the connector, has been resolved by fixation of the shielding in a position further away with Cu wire
|
286
|
Thursday, March 21, 2013, 15:05 |
Sebastian Raeder | SiC#28 | | ITE | TM4 | | | Done | 2nd heating of SiC#28 LP-RFQ - short resolved |
Anders Mjos wrote:
|
Tuesday, March 19, 2013, 12:32 : Turbos off (vaccum at 2E-7 Torr)
Tuesday, March 19, 2013, 13:35: Venting
Target SiC#28 LP-RFQ inserted
By Sebastian (SR) & Henning
modification of 9 Pin connector needed to match wiring in TM4 (see separate e-log entry)
Tuesday, March 19, 2013, 18:32 : started roughing - SR
Tuesday, March 19, 2013, 18:52: started turbos - SR
Tuesday, March 19, 2013, 18:57: TSGIP1 on - SR
Tuesday, March 19, 2013, 19:00: turbos at speed - SR
Tuesday, March 19, 2013, 19:02: vacuum at 1.68E-5T
By Anders
Wednesday, March 20, 2013, 08:18: Opened cooling water. Vacuum stable at 6.8E-7 Torr
By Sebastian (SR) & Henning
Wednesday, March 20, 2013, 11:39: 9PIN connector in HV cage connected
4,5,6,9 on GND 1,2 to RF, 7,8,RFoffest,Source for now also on GND
RF: 800kHz, 20Vampl, 0.128mA
HV cage locked up for heating
Wednesday, March 20, 2013, 16:42: heating is taken care of by ISAC operations, now at 300A / 3V TGHT and 250A / 1.47V TBHT reading on the panel is really close
Friedhelm restarted some of the CANBUS ports, since not all optics were working properly
Thursday, March 21, 2013, 10:53 start cooling down
Vacuum not perfect was around 2E-6T, over nigth not full current
Suppression tested yesterday: full beam (SRC +3V, others GND) was 40nA, while no signal on FB0B with SRC +3V, IGOffset&Exit +25V
!!!!! but short on #7 --> 2nd Repeller, was OK when tested, after some minutes on 25V short was there, reading now (Thursday, March 21, 2013, 10:58 ) <1OHM, will be checked while heating down
Magnet had wrong polarity - so no mass scans yesterday evening, Friedhelm looked into this this morning
Mass scan only for good transmission mode (SRC +3V) this morning - see attached scan (seen Na, Al, K, Ca, Cr, Rb, Sr, Cs and Ba)
Thursday, March 21, 2013, 12:26: stopped turbos
#7 still short
By Anders
Thursday, March 21, 2013, 13:25: Venting
|
Thursday, March 21, 2013, 14:46: started roughing
Target was out, visibly inspected, nothing to be seen, no short on the target - wiring of the 9Pin connector shows short circuit inside vacuum chamber
Wires removed - short could be reproduced with the strandings of the shielding from the kapton twisted pairs going into the peek connector
wire shieldings now fixed to position further away with Cu wire
all wires against ground and each other tested for holding 250V - all fine
everything reconnected and target put in, torcked w 120 inch pounds
Thursday, March 21, 2013, 15:05 : turbos started
Thursday, March 21, 2013, 15:14: turbos at speed
Thursday, March 21, 2013, 15:17: vacuum at 1.4E-5T
Thursday, March 21, 2013, 18:01: vacuum at 1.45E-6T opening water lines - vacuum is stable
Thursday, March 21, 2013, 19:19 : vacuum at 8.6E-7T - start ramping heater to 580A / 250 A
Friday, March 22, 2013, 00:08: target is heated full way up
setpoint 570A and 7.250V voltage limit
readback 564.1A and 7.201V --> needs more voltage than the normal target !
vacuum at 1.2E-6T
Friday, March 22, 2013, 15:15: vacuum at 5.4E-7T
preparing for HV test and mass scan
transmission mode: Source +3V, everything else on GND: 12nA - mass scan see attachment
suppression mode 1: Source -15V, everything else on GND: 20pA - mass scan see attachment
suppression mode 2: Source +3V, everything else on +25V: <1pA - FC0 current while biasing see attachment
NOTE: the legs of the target are glowing differently, the left leg (view from the lid side onto the target unit) glows brighter, this side was open during the sintering process of the SiC and needed more alignment at the jig --> see attached picture
NOTE2: there is a slight increase in TGHT voltage over time: in ~ 22h from 7.201V to 7.216V
Friday, March 22, 2013, 21:33 : vacuum at 4.8E-7, start ramping down
Friday, March 22, 2013, 22:47: heaters down and turned off, vacuum at 2.7E-7T
Monday, March 25, 2013, 00:15: vacuum at 1.4E-7T, IG off, turbos off
By Anders
Monday, March 25, 2013, 08:18: Venting
Monday, March 25, 2013, 08:33: Purging water lines
Monday, March 25, 2013, 08:42: Target removed |
|