Entry  Tuesday, February 26, 2013, 08:32, Anders Mjos, , , , , , , Problems/Solutions, TMSTP2 timeout / fault Vacuum_2013-02-26.PNG
    Reply  Tuesday, March 19, 2013, 09:04, Anders Mjos, , , , , , , Problems/Solutions, Venting TMS section for replacement of TP2 by vacuum group 
Message ID: 282     Entry time: Tuesday, March 19, 2013, 09:04     In reply to: 280
Author: Anders Mjos 
Target/No.#:  
Source:  
Station:  
Module:  
Target Oven W.O#:  
Heat Shield W.O#:  
Status: Problems/Solutions 
Subject: Venting TMS section for replacement of TP2 by vacuum group 

 

Anders Mjos wrote:

Tuesday, February 26, 2013, 08:24: Started turbo

Tuesday, February 26, 2013, 08:24: Turbo timed out

e-fault 6585 submitted

 

Edi called to inform that he can replace the turbo today.

Tuesday, March 19, 2013, 09:03: Stopped TP6

Tuesday, March 19, 2013, 09:35: Venting

Tuesday, March 19, 2013, 09:48 : TMS section and backing line vented


The turbo pump has been replaced see

https://elog.triumf.ca/TIS/Test-Stand/284

Some heat marks were observed on the turbo pump that was replaced. Vacuum group took pictures.

 