394
|
Friday, July 18, 2014, 11:30 |
Anders Mjos | UC#10 | LP-SIS | ITE | TM4 | 40282-5 | 40316-1 | Done | UC#10 Heat Shield Conditioning | Friday, July 18, 2014, 11:30: Roughing
Friday, July 18, 2014, 11:51: Starting turbos
Friday, July 18, 2014, 11:59: Turbos at speed.
Friday, July 18, 2014, 12:01: Vacuum at 1.4E-5 T
Monday, July 21, 2014, 08:51: Opened water for HS circuit. Small vacuum "bump" recovered to 1.5E-7 T
Monday, July 21, 2014, 09:17: Starget TGHT autoramping to 580A @ 2 A/min
Monday, July 21, 2014, 14:05: TGHT @ 580A 7.47V.
Tuesday, July 22, 2014, 10:41: Data logger installed
Device
|
Temp
[C] |
Flow
[lpm] |
HS + MSP |
37.6 |
3.7 |
TBHT |
28.5 |
6.1 |
COIL + EE |
28.7 |
4.8 |
TGHT |
31.0 |
5.4 |
Tuesday, July 22, 2014, 13:41: BIAS / EZL / EE to 30 / 14 /2 kV. EE:RDCUR 695 uA
Tuesday, July 22, 2014, 14:23: Starting cool down of TGHT 2A/min. Vacuum at 2.7E-7 T
Wednesday, July 23, 2014, 09:05: BIAS / EZL / EE off. Turbos off. Vacuum at 1.3E-7 T.
Device |
Temp
[C] |
Flow
[lpm] |
HS + MSP |
28.5 |
3.7 |
TBHT |
28.3 |
6.1 |
COIL + EE |
29.2 |
5.2 |
TGHT |
28.4 |
5.7 |
Wednesday, July 23, 2014, 14:05: Purged HS water line.
Wednesday, July 23, 2014, 14:07 : Venting
Wednesday, July 23, 2014, 14:33: Heat Shield removed |
395
|
Wednesday, July 23, 2014, 14:34 |
Anders Mjos | | | | | | | In progress | Empty chamber | Wednesday, July 23, 2014, 14:34: Roughing
Wednesday, July 23, 2014, 15:03: Starting turbos.
Wednesday, July 23, 2014, 15:11: Turbos at speed
Wednesday, July 23, 2014, 15:13: Vacuum at 7.4E-6 T |
396
|
Friday, August 01, 2014, 08:39 |
Anders Mjos | | | | | | | Problems/Solutions | TMS:RP2 noisy | Friday, August 01, 2014, 08:39: Backing pressure 0 / 11 mT |
397
|
Friday, August 08, 2014, 12:45 |
Anders Mjos | ZrC#6 | LP-SIS | ITW | TM1 | 40282-3 | 39230-5 | Done | Condictioning ZrC#6 | Friday, August 08, 2014, 12:44: Stopped turbos
Friday, August 08, 2014, 14:42: Venting
Target assembly inserted
Friday, August 08, 2014, 15:08: Roughing
Friday, August 08, 2014, 15:29: Turbos started
Friday, August 08, 2014, 15:37: Turbos at speed
Friday, August 08, 2014, 15:39: Vacuum at 1.4E-5 T
Monday, August 11, 2014, 08:58: Opened HS cooling water. Vacuum stable at 1.6E-7 T
Tuesday, August 12, 2014, 10:31: IV4 Opened
Tuesday, August 12, 2014, 10:35: EZL / EE / BIAS to 14 / -1.5 / 30 kV
Tuesday, August 12, 2014, 10:39: Starting target heat to 300 A / 96 (115) A
Wednesday, August 13, 2014, 08:03 : Continue heating to 580 A / 190 (228) A
Wednesday, August 13, 2014, 08:24: Aborting target heating. Cu-LCW pressure and flow is reduced due to a problem with a pump.
Device |
Flow
[lpm] |
Temp
[C]
|
HS + MSP |
1.9 |
27.7 |
TBHT |
4.1 |
23.9 |
COIL + EE |
3.5 |
25.1 |
TGHT |
3.7 |
25.6 |
SUPPLY |
|
24.4 |
Supply pressure ~ 52 psi
Return pressure ~ 11 psi
Wednesday, August 13, 2014, 08:31: Starting cool down as flow rate on HS + MSP is low. A low flow trip of the TGHT should be avoided.
Wednesday, August 13, 2014, 11:54 : Curtis Ballard contacted me and asked if they could valve off the Cu-LCW circuit to the Test Stand. Heaters had been previously brought down. Bias off and power supplies are switched off. IV4 closed.
Wednesday, August 13, 2014, 12:00: Cooling water syupply valved off to Test Stand.
Flow rates are back to normal since yesterday evening
Device |
Flow
[lpm] |
Temp
[C] |
HS + MSP |
3.1 |
27.8 |
TBHT |
5.9 |
27.4 |
COIL + EE |
5.0 |
28.3 |
TGHT |
5.4 |
27.6 |
SUPPLY |
|
28.1 |
Thursday, August 14, 2014, 08:00: Conditioning on hold due to FC0 problem
Wednesday, August 20, 2014, 07:50: Conditioning continues. Auto-ramping to 400 / 150 ( 180) A @ 4/2 A/min
Wednesday, August 20, 2014, 09:35 : Continue heating to 580 / 165 (200) A @ 2/1 A/min
Wednesday, August 20, 2014, 09:50
Device |
Flow
[lpm] |
Temp
[C] |
HS + MSP |
3.6 |
32.9 |
TBHT |
6.5 |
28.5 |
COIL + EE |
5.4 |
29.2 |
TGHT |
5.8 |
29.7 |
SUPPLY |
|
28.8 |
Wednesday, August 20, 2014, 15:15: Power lost to TBHT, TGHT and EE during nominal operation (580/ 183 (220) A). Fault report submitted.
PLC cabinet work finished. Resuming conditioning.
Tuesday, August 26, 2014, 16:35:EZL / EE / BIAS to 14 / -1.5 / 30 kV
Tuesday, August 26, 2014, 16:35: Starting target heat to 50 A / 25 A
Wednesday, August 27, 2014:
Continued conditioning. Heating to 580 /190 (228) A
Thursday, August 28, 2014, 08:34
Device |
Flow
[lpm] |
Temp
[C] |
HS + MSP |
3.5 |
38.0 |
TBHT |
6.4 |
28.0 |
COIL + EE |
5.5 |
29.8 |
TGHT |
5.8 |
30.3 |
SUPPLY |
|
28.2 |
Friday, August 29, 2014, 10:30: EE conditioned for ~20 min @ 2kV.
Friday, August 29, 2014, 10:32 : Starting cool down at 4/2 A/min
Friday, August 29, 2014, 11:55: Closed IV4
Friday, August 29, 2014, 11:56: BIAS, EE and EZL to 0
Friday, August 29, 2014, 13:10: Stopped turbos.
Friday, August 29, 2014, 14:06: Venting
Friday, August 29, 2014, 14:51: Target removed |
398
|
Tuesday, August 12, 2014, 09:52 |
Anders Mjos | | | | | | | Problems/Solutions | RTD installed on Supply water | Travis assisted in installing a temperature reading RTD from Omega (SA1-RTD-MTP) on the water supply. The RTD has been installed with a 503 Ohm resistor => 0V = -175.75 C, 10V = 205.71 C. The RTD has been connected to Ch 9 on the data logger.
Offset calibration data towards the SUPPLY temperature reading is attached. |
399
|
Thursday, August 14, 2014, 08:45 |
Anders Mjos | | | | | | | Problems/Solutions | FC0 reading full current | since yesterday around 19h. See attached screen shot of archived data
Thursday, August 14, 2014, 08:40: Rebooted IOC. Still reading full scale only. FC0 reads full scale with signal cable removed.
e-fault 7545
Thursday, August 14, 2014, 11:28: Graham called to inform me that all of the 8 channels on the module was reading high. TRIUMF does not have a spare. He will arrange to have the module repaired.
Tuesday, August 19, 2014, 16:27: Graham has brought the system back into operation with a new vqsx module from the ICB stand. |
400
|
Wednesday, August 20, 2014, 16:25 |
Anders Mjos | | | | | | | Problems/Solutions | Lost power on TGHT, TBHT and EE simultaniously | Possible controls problem. Breaker 18 found latched. Can not be re-energized. Burnt smell in PLC / HV area. e-faut 7561
Thursday, August 21, 2014: Dave Morris had a look and was able to isolate the problem to be with one of the low voltage power supplies in the PLC panel.
Friday, August 22, 2014: New 12V and 24V power supplies installed. PLC cabinet vacuumed. A new 24V fan with filter will also be installed.
Tuesday, August 26, 2014: Power restored to PLC cabinet. System is operational again. |
401
|
Wednesday, August 27, 2014, 12:55 |
Anders Mjos | | | | | | | Problems/Solutions | Water leak on MB1 | e-faulted by operations Aug 26th |
402
|
Friday, August 29, 2014, 14:52 |
Anders Mjos | Ta#44 | HP-SIS | ITE | TM4 | 38817-9 | 40316-11 | Done | Conditioning Ta#44 | Friday, August 29, 2014, 14:51: Roughing
Friday, August 29, 2014, 15:11: Starting turbos.
Friday, August 29, 2014, 15:19: Turbos at speed
Friday, August 29, 2014, 15:21: Vacuum at 1.6E-5 T
Tuesday, September 02, 2014, 08:36: HS cooling water supply opened. Vacuum stable at 1.4E-7 T
Tuesday, September 02, 2014, 08:50 : BIAS/ EZL / EE to 30 / 14 / -1.5 kV. Started auto ramping to 500 / 150 (180) A
Tuesday, September 02, 2014, 09:23
Supply ~97psi, Return ~7psi
Device
|
Flow
[lpm] |
Temp
[C] |
HS + MSP |
3.9 |
28.0 |
TBHT |
6.5 |
27.6 |
COIL + EE |
5.4 |
28.6 |
TGHT |
5.8 |
27.8 |
SUPPLY |
|
28.2 |
Thursday, September 04, 2014, 12:38 : Starting cool-down
Thursday, September 04, 2014, 15:20: Closed IV4
Thursday, September 04, 2014, 15:37 : BIAS / EZL / EE to 0
Friday, September 05, 2014
Target cooled down. Power supplies switched off.
Monday, September 08, 2014, 14:07: Turbos stopped.
Monday, September 08, 2014, 15:15: Venting. HS cooling water lines purged.
Monday, September 08, 2014, 16:00: Target removed. |
403
|
Monday, September 08, 2014, 16:23 |
Anders Mjos | UC#11 | | | TM4 | 40282-5 | | Done | UC#11 Heat Shield Conditioning | T/C installed
CH 1: Attached to TGHT outside middle
CH 2: Through HS outside TGHT right
CH 3: Through HS inside TGHT right
CH 4: Attached to HS on left gripper. Does not read temp
Monday, September 08, 2014, 16:22: Roughing
Monday, September 08, 2014, 16:43: Started turbos
Monday, September 08, 2014, 16:51: Turbos at speed
Monday, September 08, 2014, 16:53: Vacuum at 2.7E-5 T
Tuesday, September 09, 2014, 08:20 : Opened HS water supply. Vacuum stable at 3.7E-7 T
Tuesday, September 09, 2014, 08:21: Starting auto ramping. TGHT to 580 A at 2A/min
Tuesday, September 09, 2014, 08:50 :
Device |
Flow
[lpm] |
Temp
[C] |
HS + MSP |
3.8 |
26.7 |
TBHT |
6.5 |
26.2 |
COIL + EE |
5.3 |
26.9 |
TGHT |
5.8 |
26.3 |
SUPPLY |
|
27.0 |
Wednesday, September 24, 2014, 11:30: T/C attached to tube does no longer read a correct temperature. Cooling down.
Thursday, September 25, 2014, 08:50: Turbos stopped.
Thursday, September 25, 2014, 11:07: Venting
Thursday, September 25, 2014, 14:00: Heat shield removed |
404
|
Thursday, September 25, 2014, 15:44 |
Anders Mjos | ThO#1 | | ITW | TM1 | 40282-5 | | Done | ThO#1 Heat Shield Conditioning | Thursday, September 25, 2014, 15:44: Roughing
Thursday, September 25, 2014, 16:06: Starting turbos
Thursday, September 25, 2014, 16:14: Turbos at speed.
Thursday, September 25, 2014, 16:28: Vacuum at 1.9E-5 T
Vacuum was coming down slowly yesterday. Vented this morning to clean o-ring on door.
Friday, September 26, 2014, 08:40: Roughing
Friday, September 26, 2014, 09:02: Starting turbos
Friday, September 26, 2014, 09:10: Turbos at speed
Friday, September 26, 2014, 09:12: Vacuum at 9.7E-6 T
Monday, September 29, 2014, 08:40: Water opened for HS circuit. Vacuum stable at 1.8E-7 T
Monday, September 29, 2014, 13:51: Opened and closed IV4
Wednesday, October 01, 2014, 13:13 : Target cooled down.
Monday, October 06, 2014, 09:10: Turbos stopped. Vacuum at 1.3E-7 T
Monday, October 06, 2014, 10:49: Venting
Tuesday, October 07, 2014, 09:31: Heat Shield removed |
405
|
Tuesday, October 07, 2014, 09:32 |
Anders Mjos | | | | | | | In progress | Pumping down empty chamber | Tuesday, October 07, 2014, 09:30: Roughing
Tuesday, October 07, 2014, 10:24: Starting turbos
Tuesday, October 07, 2014, 10:32 : Turbos at speed. Vacuum at 3.3E-5 T |
406
|
Monday, October 20, 2014, 09:17 |
Anders Mjos | | | | | | | Problems/Solutions | Power bump this weekend tripped off all turbo pumps | Monday, October 20, 2014, 09:17: Roughing
Monday, October 20, 2014, 09:18 : Turbos started
Monday, October 20, 2014, 09:29 : All turbos at speed
Monday, October 20, 2014, 10:11: Switched on optics |
407
|
Monday, October 27, 2014, 09:26 |
Anders Mjos | | | | | | | Problems/Solutions | TSG:TP1B noisy | e-fault 7748
Monday, October 27, 2014, 09:21: Switched off turbos
Friday, October 31, 2014, 10:43 : Venting
Friday, October 31, 2014, 14:3: Turbo replaced by vacuum group |
408
|
Friday, October 31, 2014, 14:57 |
Anders Mjos | | LP-FEBIAD | | | Tube only | 38307-9 | In progress | Test | Friday, October 31, 2014, 14:47: Starting turbos
Friday, October 31, 2014, 14:57: Turbos at speed. Vacuum at 2.9E-5 T
Monday, November 03, 2014, 10:08 : Opened HS water circuit. Vacuum stable at 1.7E-7 T
Monday, November 03, 2014, 10:22: Starting auto ramping to 228A on TBHT at 1 A/min
Monday, November 03, 2014, 13:44: Target at temperature. Opening IV4.
Monday, November 03, 2014, 14:45: IV4 closed
Monday, November 03, 2014, 15:00: Starting cool down. 1 A/min |
409
|
Monday, November 03, 2014, 14:50 |
Anders Mjos | | | | | | | Problems/Solutions | IV4 did not close until 4th attempt | Indicated with red valve on the EPICS vacuum page |
410
|
Monday, November 24, 2014, 08:41 |
Anders Mjos | | | | | | | Problems/Solutions | TSG:RP1 replaced | by Edi on Friday Nov 11th |
411
|
Friday, December 12, 2014, 13:11 |
Anders Mjos | | | | | | | Problems/Solutions | HV inspection and cleaning | by Ray D and Anders in preparation for 60kV test. Rack insulators and f/t insulators cleaned with windex |
412
|
Friday, December 12, 2014, 13:11 |
Anders Mjos | | | | | | | Problems/Solutions | HV inspection and cleaning | by Ray D and Anders in preparation for 60kV test. Rack insulators and f/t insulators cleaned with windex |
413
|
Friday, December 12, 2014, 14:09 |
Anders Mjos | | LP-FEBIAD | | | Tube only | | In progress | HV BIAS Test | BIAS current limit pot changed from 2.40 to 0.25
EZL current limit pot changed from 0.50 to 0.20
Testing max HV bias with Ray
Tested successfully to plc limit of 50kV.
Dave M updated limit to 59kV. the limit will reset to 50 kV if PLC is restarted
Friday, December 12, 2014, 14:43: BIAS at 59kV and 55 uA. EZL at 20kV and 73 uA. No sparking observed.
Tuesday, December 16, 2014, 09:12: BIAS and EZL to 40kV and 20kV
Tuesday, December 16, 2014, 09:53: BIAS at 50 kV. One spark w/vaccum response at 50 kV
Tuesday, December 16, 2014, 10:20: BIAS and EZL to 0 to try and restart TP1B TP6
Tuesday, December 16, 2014, 10:33: Both turbos restated. BIAS and EZL at 50 kV and 20 kV
Tuesday, December 16, 2014, 11:23: BIAS at 60 kV. One audible spark with vacuum response.
Tuesday, December 16, 2014, 11:37: Another spark took out TP1B and TP6 again.
Tuesday, December 16, 2014, 11:42: Restarted TP1B and TP6
EE power supply switched on
Wednesday, December 17, 2014, 10:19: BIAS at 60kV for 10 min. EZL at 20kV
Wednesday, December 17, 2014, 13:13 : 3h at 60 kV (see attached screen shot)
Wednesday, December 17, 2014, 13:24: BIAS off
Wednesday, December 17, 2014, 13:40: All power supplies ON. TBHT autoramping to 290 A (240 A0. 4A / min
Wednesday, December 17, 2014, 13:46: IV4 opened
Wednesday, December 17, 2014, 16:10: Source on at 30 kV (previously tested to 50 kV)
Thursday, December 18, 2014, 08:21 : Starget autoraming to 290 A (240 A). 4 A / min
Thursday, December 18, 2014, 08:48: 40 kV
Thursday, December 18, 2014, 08:57: 50 kV
Thursday, December 18, 2014, 09:18: 60 kV. Extracting 1E-7 A on FC0
Thursday, December 18, 2014, 09:29: Increased COIL and ANODE to 3.6 A and 60 V
Thursday, December 18, 2014, 10:11: Large spark? Vacuum in source box compromised 6E-4 T.
Thursday, December 18, 2014, 10:24: Closed IV4 (red, but closed - IG6 vacuum good). Stopping turbos. Vacuum is increasing on CG1.
Thursday, December 18, 2014, 10:26: Shutting off water supply.
Thursday, December 18, 2014, 10:29: Venting through turbo vent valves.
Thursday, December 18, 2014, 10:35: Closed turbo vent valves.
Thursday, December 18, 2014, 10:37: Roughing
Thursday, December 18, 2014, 10:42: Pumping curve changing slope abruptly around 30 T and again around 2.5 T
Thursday, December 18, 2014, 10:48: Stopped roughing
Thursday, December 18, 2014, 12:14 : Venting
Thursday, December 18, 2014, 13:43: Roughing
|
|